99-25468. Entergy Operations, Inc.; Arkansas Nuclear One, Unit No. 2 Environmental Assessment and Finding of No Significant Impact  

  • [Federal Register Volume 64, Number 189 (Thursday, September 30, 1999)]
    [Notices]
    [Pages 52804-52805]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-25468]
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket No. 50-368]
    
    
    Entergy Operations, Inc.; Arkansas Nuclear One, Unit No. 2 
    Environmental Assessment and Finding of No Significant Impact
    
        The U.S. Nuclear Regulatory Commission (the Commission) is 
    considering issuance of an exemption from certain requirements of its 
    regulations for Facility Operating License No. NPF-6 issued to Entergy 
    Operations, Inc. (the licensee), for operation of Arkansas Nuclear One, 
    Unit 2 (ANO-2), located in Pope County, Arkansas.
    
    Environmental Assessment
    
    Identification of Proposed Action
    
        The proposed action would exempt the licensee from the requirements 
    of Title 10 of the Code of Federal Regulations, Part 50 (10 CFR part 
    50), appendix R, Section III.G.2.c, regarding the fire protection of 
    the safe shutdown capability for equipment located below the 354 foot 
    elevation of the ANO-2 intake structure. The licensee is requesting an 
    exemption from the specific requirement to provide fire detectors and 
    an automatic fire suppression system to protect redundant trains of 
    safe shutdown equipment that are located in the same fire zone.
        The proposed action is in accordance with the licensee's 
    application for exemption dated October 8, 1997, as supplemented by 
    letter dated February 25, 1999.
        The purpose of 10 CFR part 50, appendix R, Section III.G.2, is to 
    ensure that adequate fire protection features are provided for 
    redundant cables or equipment located in the same fire area outside of 
    primary containment such that at least one of the redundant trains of 
    safe shutdown equipment will remain available during and after any 
    postulated fire in the plant to achieve and maintain safe shutdown 
    conditions. Section III.G.2.c requires the following means of 
    assurance:
    
        Enclosure of cable and equipment and associated non-safety 
    circuits of one redundant train in a fire barrier having a 1-hour 
    rating. In addition, fire detectors and an automatic fire 
    suppression system shall be installed in the fire area.
    
        The ANO-2 intake structure below the 354 foot elevation consists of 
    three service water intake bays, which contain service water (SW) 
    piping and conduits. The bays are approximately 7 feet by 32 feet and 
    are separated from one another by 2-foot thick, non-rated concrete 
    walls. The bays are separated from the ground level by an 18-inch 
    thick, non-rated concrete slab on metal decking. The floor of the bays 
    is typically covered with water 16 feet deep. The ceiling height is 
    approximately 14 feet above the normal pool level. Of the three bays, 
    only the ``A'' SW intake bay contains redundant cables. The licensee 
    stated that the total in-situ combustible loading is 3,469,060 BTUs, 
    which is equivalent to a fire severity to a standard fire duration of 
    less than 4 minutes. Each bay is administratively controlled as a 
    ``confined space,'' thus limiting access by personnel during routine 
    operations and precluding the accumulation of combustibles. In 
    addition, the licensee's administrative procedures limit the transient 
    combustibles to 5 pounds unless personnel are continuously present in 
    the area. In such cases, the personnel could be either the craft 
    personnel responsible for using the combustible materials or a 
    continuous fire watch. Water to the bay is normally provided
    
    [[Page 52805]]
    
    through a sluice gate for the bays where the circulating pumps take 
    suction.
        Service water is required to be available to supply cooling water 
    for various safe shutdown components including the diesel generators 
    and the shutdown cooling heat exchangers. Additionally, SW can be 
    aligned to the emergency feedwater system in the event that the desired 
    condensate source is depleted. The time critical function is to supply 
    cooling for the diesel generators. The licensee stated that, on the 
    basis of its calculations, the diesel generators (and therefore the SW 
    system components) are not required to be operated during the first 30 
    minutes of a postulated fire event. The licensee allows the operators 
    to manually align the SW system because the diesel generators are not 
    required during the first 30 minutes of a fire event and sufficient 
    time is available to complete the alignment.
        The SW system consists of two independent seismic category 1 flow 
    paths that furnish cooling water to two independent trains of 100 
    percent capacity engineered safety feature equipment, and two non-
    seismic category 1 flow paths. The SW system has three 100 percent 
    capacity pumps. One pump is dedicated to each of the two SW trains 
    while the third pump is designated as a swing pump and can be aligned 
    to either train. The two loops of the SW system are also electrically 
    independent with two separate divisions of electrical power designated 
    as the red and green train. The red train power for SW is aligned to 
    either SW pump 2P4A or SW pump 2P4B, while the green train power is 
    aligned to either SW pump 2P4C or SW pump 2P4B.
        The four power cables associated with the 2P4A, 2P4B, and 2P4C SW 
    pumps interface with the ``A'' SW intake bay challenging the protection 
    criteria specified in Section III.G.2 of Appendix R. The red train 
    power to 2P4A is provided with a fire wrap rated as a 1-hour rated 
    barrier. The red train power to 2P4B is embedded in the concrete wall 
    of the ``A'' SW intake bay, which provides an equivalent 1-hour rated 
    fire barrier. The green train power to 2P4B is provided with a fire 
    wrap rated for a 1-hour barrier. The cables for the red train power to 
    2P4A and the green train power to 2P4B are routed together inside of a 
    protective moisture barrier. The green train power to 2P4C is routed 
    independently and is approximately 6 feet (horizontally) from the 
    protective moisture barrier providing some physical separation. 
    Therefore, based on the preceding discussion, this area would require 
    the addition of fire detectors and an automatic fire suppression system 
    in order to comply with the requirements of 10 CFR part 50, appendix R, 
    Section III.G.2.c.
        Power and control cables for the sluice gates are also located in 
    the SW intake bays. Sluice gate valves 2CV1470-1, 2CV1472-5, and 
    2CV1474-2 are normally open, which corresponds to the safe shutdown 
    position. The redundant control cables are separated horizontally by 
    approximately 8 feet. As stated previously, the time critical function 
    of the SW system is to provide cooling to the diesel generators. The 
    licensee stated that if a fire were to cause the sluice gates to 
    spuriously close, adequate time would be available before service water 
    was required to manually realign any affected component.
    
    The Need for the Proposed Action
    
        The proposed action is needed because the addition of fire 
    detectors and an automatic fire suppression system to the SW intake 
    bays is considered infeasible due to the construction of the intake 
    structure and the fact that the room is partially water-filled during 
    normal conditions.
    
    Environmental Impacts of the Proposed Action
    
        The Commission has completed its evaluation of the proposed action 
    and concludes that there is no significant environmental impact if the 
    exemption is granted.
        The proposed action will not increase the probability or 
    consequences of accidents, no changes are being made in the types of 
    any effluents that may be released off site, and there is no 
    significant increase in occupational or public radiation exposure. 
    Therefore, there are no significant radiological environmental impacts 
    associated with the proposed action.
        With regards to potential nonradioactive impacts, the proposed 
    action does not involve any historic sites. It does not affect 
    nonradiological plant effluents and has no other environmental impacts. 
    Therefore, there are no significant nonradiological environmental 
    impacts associated with the proposed action.
        Accordingly, the Commission concludes that there are no significant 
    environmental impacts associated with the proposed action.
    
    Alternatives to the Proposed Action
    
        As an alternative to the proposed action, the staff considered 
    denial of the requested action (i.e., the ``no-action'' alternative). 
    Based on the physical characteristics of the SW intake bays, the NRC 
    staff has determined that there is a low probability of occurrence for 
    a fire event in the ANO-2 intake structure below the 354 foot 
    elevation. This low probability of occurrence combined with the lack of 
    combustible material, administrative controls, and the fire protection 
    features provided is sufficient to show adequate protection for 
    redundant equipment in the SW system. Therefore, the features 
    associated with the ANO-2 Intake Structure below the 354 foot elevation 
    are sufficient to achieve the underlying purpose of Appendix R, Section 
    III.G.2.c. Therefore, denial of the application would result in no 
    change in the current environmental impacts. The environmental impacts 
    of the proposed action and the alternative action are similar.
    
    Alternative Use of Resources
    
        This action does not involve the use of any resources not 
    previously considered in the Final Environmental Statement for Arkansas 
    Nuclear One, Unit 2.
    
    Agencies and Persons Consulted
    
        In accordance with its stated policy, on June 24, 1999, the staff 
    consulted with the Arkansas State official, Mr. Bernie Bevill, 
    Supervisor, Quality and Evaluation Section, Division of Radiation 
    Control and Emergency Management, regarding the environmental impact of 
    the proposed action. The State official had no comments.
    
    Finding of No Significant Impact
    
        On the basis of the environmental assessment, the Commission 
    concludes that the proposed action will not have a significant effect 
    on the quality of the human environment. Accordingly, the Commission 
    has determined not to prepare an environmental impact statement for the 
    proposed action.
        For further details with respect to the proposed action, see the 
    licensee's letter dated October 8, 1997, as supplemented by letter 
    dated February 25, 1999. These letters are available for public 
    inspection at the Commission's Public Document Room, The Gelman 
    Building, 2120 L Street, NW., Washington, DC, and at the local public 
    document room at the Tomlinson Library, Arkansas Tech University, 
    Russellville, Arkansas.
    
        For the Nuclear Regulatory Commission.
    Robert A. Gramm,
    Chief, Section 1, Project Directorate IV & Decommissioning, Division of 
    Licensing Project Management, Office of Nuclear Reactor Regulation.
    [FR Doc. 99-25468 Filed 9-29-99; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
09/30/1999
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
99-25468
Pages:
52804-52805 (2 pages)
Docket Numbers:
Docket No. 50-368
PDF File:
99-25468.pdf