95-21929. Georgia Power Company, et al. (Vogtle Electric Generating Plant, Unit 1); Exemption  

  • [Federal Register Volume 60, Number 171 (Tuesday, September 5, 1995)]
    [Notices]
    [Pages 46135-46137]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-21929]
    
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket No. 50-424]
    
    
    Georgia Power Company, et al. (Vogtle Electric Generating Plant, 
    Unit 1); Exemption
    
    I
        Georgia Power Company, et al. (the licensee) is the holder of 
    Facility Operating License No. NPR-68, which authorizes operation of 
    the Vogtle Electric Generating Plant (VEGP), Unit 1. The license 
    provides, among other things, that the licensee is subject to all 
    rules, regulations, and orders of the Commission now or hereafter in 
    effect.
        The facility consists of a pressurized water reactor, VEGP Unit 1, 
    at the licensee's site located near Waynesboro, Georgia.
    II
        Section III.D.1.(a) of Appendix J to 10 CFR Part 50 requires the 
    performance of three Type A containment integrated leakage rate tests 
    (ILRTs), at approximately equal intervals during each 10-year service 
    period of the primary containment. The third test of each set shall be 
    conducted when the plant is shutdown for the 10-year inservice 
    inspection of the primary containment.
    III
        By letter dated May 12, 1995, as supplemented by letter dated June 
    6, 1995, the licensee requested temporary relief from the requirement 
    to perform a set of three Type A tests at approximately equal intervals 
    during each 10-year service period of the primary containment. The 
    requested exemption would permit a one-time interval extension of the 
    third Type A test by approximately 18 months (from the March, 1996, 
    refueling outage, to the September, 1997, refueling outage) and would 
    permit the third Type A test of the second 10-year inservice inspection 
    period to not correspond with the end of the current American Society 
    of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code) 
    inservice inspection interval.
        The licensee's request cites the special circumstances of 10 CFR 
    50.12, paragraph (a)(2) (ii), (iii) and (vi) as the basis for the 
    exemption. They point out that the existing Type B and C testing 
    programs are not being modified by this request and will continue to 
    effectively detect containment leakage caused by the degradation of 
    active containment isolation components as well as containment 
    penetrations. It has been the experience at Vogtle Unit 1 during the 
    three Type A tests (one preoperational and two during the first 10 year 
    inservice inspection period) conducted from 1986 to date, that any 
    significant containment leakage paths are detected by the Type B and C 
    testing. The Type A test results have only been confirmatory of the 
    results of the Type B and C test results. Therefore, application of the 
    regulation in this particular circumstance is not necessary to achieve 
    the underlying purpose of the rule.
        Additionally, the licensee stated that their exemption request 
    meets the requirements of 10 CFR 50.12 for the following reasons:
    
    10 CFR 50.12  Requirements
    
        In accordance with 10 CFR 50.12, the Commission may grant an 
    exemption to the requirements of the regulations of 10 CFR 50 if the 
    exemption is authorized by law, will not present an undue risk to 
    the public health and safety, is consistent with the common defense 
    and security, and special circumstances are present.
    
    The Requested Exemption is Authorized by Law
    
        There is no known law that would be violated by the granting of 
    the proposed exemption. 10 CFR 50.12 provides the basis for granting 
    exemptions to the requirements of 10 CFR 50 regulations. The NRC has 
    granted similar exemptions in the past. Therefore, the exemption is 
    authorized by law.
    
    The Requested Exemption Does Not Present an Undue Risk to the 
    Public Health and Safety
    
        10 CFR 50, Appendix J states that the purpose of the regulation 
    is to assure that leakage through primary containment and systems 
    and components penetrating containment does not exceed allowable 
    values, as specified in the Technical Specifications or associated 
    bases, and that proper maintenance and repair are performed 
    throughout the service life of the containment boundary components. 
    The ILRT history for VEGP, Unit 1 during the first 10 year service 
    period inspection interval indicated that the containment structure 
    has not experienced degradation. The NRC has conducted a detailed 
    study of integrated leak rate tests performed from 1987 to 1993. 
    That study, documented in draft NUREG-1493, determined that 97% of 
    the leakage rate tests that exceed the acceptance criteria are 
    identified by LLRT programs. The LLRT program at VEGP, Unit 1 has 
    been successful in maintaining low Type B and C containment leakage. 
    Since there has been no identified containment structural leakage, 
    the 
    
    [[Page 46136]]
    LLRT program has contributed to the successful ILRTs. Therefore, as 
    shown in the NRC study and as indicated by the VEGP, Unit 1 
    containment performance history, postponing the ILRT by one 
    refueling cycle remains consistent with the intent of the regulation 
    and will not present an undue risk to the public health and safety.
    
    The Requested Exemption Will Not Endanger the Common Defense and 
    Security
    
        GPC interprets the term ``common defense and security'' as 
    referring principally to the safeguarding of special nuclear 
    material, the absence of foreign control over the applicant, and the 
    protection of restricted data. The granting of the requested 
    exemption will not affect any of those matters, and thus, the 
    granting of the exemption is consistent with the common defense and 
    security of the United States.
    
    Special Circumstances are Present Which Necessitate the Request for 
    an Exemption to the Regulations of 10 CFR 50, Appendix J, Section 
    III.A.5(b)(2)
    
        The special circumstances of 10 CFR 50.12(a)(2) (ii), (iii), and 
    (vi) apply to this requested exemption.
    50.12(a)(2)(ii)--Application of the Regulation is Not Necessary to 
    Achieve the Underlying Purpose of the Rule
    
        The underlying purpose of 10 CFR 50, Appendix J will still be 
    served if a third ILRT is not conducted during the first 10-year 
    service period. Appendix J states that the leakage test requirements 
    provide for periodic verification by tests of the leak tight 
    integrity of the primary reactor containment. The Appendix further 
    states that the purpose of the tests is to assure that leakage 
    through the primary reactor containment shall not exceed the 
    allowable leakage rate values as specified in the Technical 
    Specifications or associated bases.
        10 CFR 50, Appendix J, Section III.D.1(a) states that a set of 
    three periodic tests shall be performed at approximately equal 
    intervals during each 10-year period and that the third test shall 
    be conducted when the plant is shut down for the 10-year plant 
    inservice inspections. The proposed exemption would permit delaying 
    of the scheduled Type A test and permit performance of the Type A 
    test after the completion of the first 10-year inservice inspection 
    interval in accordance with the schedule to be provided in the 
    proposed revision to Appendix J. The methodology, acceptance 
    criteria, and Technical Specifications leakage limits for 
    performance of the Type A test will not change.
        The testing history, structural capability of the containment, 
    and the risk assessment discussed previously establish that 1) VEGP, 
    Unit 1 has had acceptable containment leakage rate test results, 2) 
    the structural integrity of containment is assured, and 3) there is 
    negligible risk impact in changing the Type A test schedule on a 
    one-time basis.
        Thus, there is significant assurance that the extended interval 
    between Type A tests in concert with the Type B and C testing 
    continue to provide periodic verification of the leak tight 
    integrity of the containment.
    
    10 CFR 50.12(a)(2)(iii)--Compliance With the Regulation Would 
    Result in Undue Hardship or Other Costs That Are Significantly in 
    Excess of Those Contemplated When the Regulation Was Adapted
    
        Postponing the ILRT for VEGP, Unit 1 will eliminate unnecessary 
    testing without any reduction in plant safety. The ILRT typically 
    requires two-to-three days to perform, with the possibility of 
    significant extended time requirements. Outage activities are 
    severely impacted during the preparation period prior to the ILRT 
    and during the performance of the ILRT. A cost savings can be 
    realized by a reduction in outage time, eliminating the impact of 
    the ILRT on other outage activities, and direct costs related to 
    obtaining equipment and services necessary for performance of the 
    ILRT. This proposed exemption could result in a total cost benefit 
    of about $1,100,000, by eliminating one ILRT.
    
    10 CFR 50.12(a)(2)(vi)--Presence of Material Circumstances Not 
    Considered When the Regulation Was Adopted
    
        Certain material circumstances were not considered when the 
    regulation was adopted. The benefit of time has provided experience 
    and information that give a better perspective about containment 
    integrity. Two important material circumstances are testing history 
    and the development of probabilistic risk assessments (PRAs).
        Since the promulgation of 10 CFR 50, Appendix J, in 1973, more 
    than 20 years of nuclear power plant operating experience has been 
    obtained. A review of industry data did not find any instances where 
    a Type A test failed to meet Appendix J acceptance criteria as a 
    result of a containment structural leak not due to initial 
    fabrication or a plant modification. That operating history provides 
    a significant indicator that containment structural integrity 
    (passive structure) is not a significant safety concern.
        Plant specific PRAs were not available in 1973, and therefore, 
    were not considered when the regulation requiring compliance with 
    Appendix J [10 CFR 50.54(o)] was adopted. Overall plant risk due to 
    containment leakage is relatively small given the small probability 
    of containment leakage itself. The predominant contributor to 
    degraded containment integrity is the phenomenological effects of a 
    severe accident, not pre-existing containment integrity conditions. 
    An assessment of the risk impact in the exemption request indicates 
    that there is no undue risk to the public health and safety as a 
    result of the proposed scheduler extension of the Type A test.
        There have been no modifications to the containment structure or 
    liner that would impact the overall containment integrity and leak 
    tightness.
    IV
        Section III.D.1.(a) of Appendix J to 10 CFR Part 50 states that a 
    set of three Type A leakage rate tests shall be performed at 
    approximately equal intervals during each 10-year service period.
        The licensee proposes an exemption to this section which would 
    provide a one-time interval extension for the Type A test by 
    approximately 18 months. The Commission has determined that pursuant to 
    10 CFR 50.12(a)(1) this exemption is authorized by law, will not 
    present an undue risk to the public health and safety, and is 
    consistent with the common defense and security. The Commission further 
    determines that special circumstances as provided in 10 CFR 
    50.12(a)(2)(ii) are present justifying the exemption. Specifically, 
    these circumstances are that application of the regulation in the 
    particular circumstances is not necessary to achieve the underlying 
    purpose of the rule. The purpose of the tests is to assure that leakage 
    through the primary reactor containment shall not exceed allowable 
    leakage rate values. The staff has concluded, for the reasons set forth 
    herein, that the purpose of the rule will continue to be achieved with 
    the licensee's proposed exemption.
        The NRC staff has reviewed the basis and supporting information 
    provided by the licensee in the exemption request. The NRC staff has 
    noted that the licensee has a good record of ensuring a leak-tight 
    containment. All of the Type A tests have passed and the licensee has 
    noted that the results of the Type A testing have been confirmatory of 
    the Type B and C tests which will continue to be performed. The 
    licensee will perform the general containment inspection although it is 
    only required by Appendix J (Section V.A.) to be performed in 
    conjunction with Type A tests. The NRC staff considers that these 
    inspections, though limited in scope, provide an important added level 
    of confidence in the continued integrity of the containment boundary.
        The NRC staff has also made use of a draft staff report, NUREG-
    1493, which provides the technical jusification for the present 
    Appendix J rulemaking effort which also includes a 10-year test 
    interval for Type A tests. The integrated leakage rate test, or Type A 
    test, measures overall containment leakage. However, operating 
    experience with all types of containments used in this country 
    demonstrates that essentially all containment leakage can be detected 
    by local leakage rate tests (Type B and C). According to results given 
    in NUREG-1493, out of 180 ILRT reports covering 110 individual reactors 
    and approximately 770 years of operating history, only 5 ILRT failures 
    were found which local leakage rate testing could not detect. This is 
    3% of all failures. This study agrees well with previous NRC staff 
    studies which show that Type B and C testing can detect a very large 
    percentage of containment leaks. 
    
    [[Page 46137]]
    
        The Nuclear Management and Resources Council (NUMARC), now the 
    Nuclear Energy Institute (NEI), collected and provided the NRC staff 
    with summaries of data to asssist in the Appendix J rulemaking effort. 
    NUMARC collected results of 144 ILRTs from 33 units; 23 ILRTs exceeded 
    1.0La. Of these, only nine were not due to Type B or C leakage 
    penalties. The NEI data also added another perspective. The NEI data 
    show that in about one-third of the cases exceeding allowable leakage, 
    the as-found leakage was less than 2La; in one case the leakage 
    was found to be approximately 2La; in one case the as-found 
    leakage was less than 3La; one case approached 10La; and in 
    one case the leakage was found to be approximately 21La. For about 
    half of the failed ILRTs, the as-found leakage was not quantified. 
    These data show that, for those ILRTs for which the leakage was 
    quantified, the leakage values are small in comparison to the leakage 
    value at which the risk to the public starts to increase over the value 
    of risk corresponding to La (approximately 200La, as 
    discussed in NUREG-1493).
        Based on generic and plant specific data, the NRC staff finds the 
    basis for the licensee's proposed exemption to allow a one-time 
    exemption to permit a schedular extension of one cycle for the 
    performance of the Appendix Type A test to be acceptable.
        Pursuant to 10 CFR 51.32, the Commission has determined that 
    granting this Exemption will not have a significant impact on the 
    environment (60 FR 44514).
        This Exemption is effective upon issuance and shall expire at the 
    completion of the 1997 refueling outage.
    
        Dated at Rockville, Maryland, this 29th day of August 1995.
    
        For the Nuclear Regulatory Commission.
    Steven A. Varga,
    Director, Division of Reactor Projects--I/II, Office of Nuclear Reactor 
    Regulation.
    [FR Doc. 95-21929 Filed 9-1-95; 8:45 am]
    BILLING CODE 7590-01-P
    
    

Document Information

Published:
09/05/1995
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
95-21929
Pages:
46135-46137 (3 pages)
Docket Numbers:
Docket No. 50-424
PDF File:
95-21929.pdf