2018-19243. Notice of Availability of the Environmental Assessment for the Proposed Columbia Gas Transmission, LLC Line 8000 Replacement Project  

  • Start Preamble

    The staff of the Federal Energy Regulatory Commission (FERC or Commission) has prepared an environmental assessment (EA) for the Line 8000 Replacement Project (Project), proposed by Columbia Gas Transmission, LLC (Columbia) in the above-referenced docket. Columbia requests authorization to modernize and upgrade Columbia's Line 8000 pipeline system by replacing and abandoning existing pipeline and constructing new pipeline and appurtenant facilities in Mineral County, West Virginia and Allegany County, Maryland.

    The EA assesses the potential environmental effects of the construction and operation of the Project in accordance with the requirements of the National Environmental Policy Act (NEPA). The FERC staff concludes that approval of the proposed project, with appropriate mitigating measures, would not constitute a major federal action significantly affecting the quality of the human environment.

    The proposed Line 8000 Project would consist of:

    • Replacement of a total of approximately 13.25 miles of existing 12-inch-diameter bare steel pipeline, with approximately 13.54 miles of new, coated 12-inch-diameter natural gas transmission pipeline in five sections and four modification points along Line 8000 and Lateral Line 8006;
    • Replacement of a total of approximately 0.54 miles of existing 4-inch-diameter bare steel pipeline, with approximately 0.67 miles of new coated 4-inch-diameter natural gas transmission pipeline along two laterals (Lateral Lines 8225 and 8244);
    • Installation of two new pig [1] launcher and receiver sites and four new mainline valves associated with pipeline facilities;
    • Modifications/abandonment of three existing mainline valves and three existing side tap valve sites and modification of tie-ins at two regulator stations; and
    • Abandonment of 13 active residential taps and 109 inactive taps.

    The FERC staff mailed copies of the EA to federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American tribes; potentially affected landowners and other interested individuals and groups; and newspapers and libraries in the project area. In addition, the EA is available for public viewing on the FERC's website (www.ferc.gov) using the eLibrary link. A limited number of copies of the EA are available for distribution and public inspection at: Federal Energy Regulatory Commission, Public Reference Room, 888 First Street NE, Room 2A, Washington, DC 20426, (202) 502-8371.

    Any person wishing to comment on the EA may do so. Your comments should focus on the EA's disclosure and discussion of potential environmental effects, reasonable alternatives, and Start Printed Page 45234measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure that the Commission has the opportunity to consider your comments prior to making its decision on this project, it is important that we receive your comments in Washington, DC on or before 5:00 p.m. Eastern Time on September 28, 2018.

    For your convenience, there are three methods you can use to file your comments to the Commission. In all instances, please reference the project docket number (CP18-13-000) with your submission. The Commission encourages electronic filing of comments and has staff available to assist you at (866) 208-3676 or FercOnlineSupport@ferc.gov.

    (1) You can file your comments electronically using the eComment feature on the Commission's website (www.ferc.gov) under the link to Documents and Filings. This is an easy method for submitting brief, text-only comments on a project;

    (2) You can also file your comments electronically using the eFiling feature on the Commission's website (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on eRegister. You must select the type of filing you are making. If you are filing a comment on a particular project, please select Comment on a Filing; or

    (3) You can file a paper copy of your comments by mailing them to the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426.

    Any person seeking to become a party to the proceeding must file a motion to intervene pursuant to Rule 214 of the Commission's Rules of Practice and Procedures (18 CFR 385.214). Only intervenors have the right to seek rehearing or judicial review of the Commission's decision. The Commission may grant affected landowners and others with environmental concerns intervenor status upon showing good cause by stating that they have a clear and direct interest in this proceeding which no other party can adequately represent. Simply filing environmental comments will not give you intervenor status, but you do not need intervenor status to have your comments considered.

    Additional information about the project is available from the Commission's Office of External Affairs, at (866) 208-FERC, or on the FERC website (www.ferc.gov) using the eLibrary link. Click on the eLibrary link, click on General Search, and enter the docket number in the Docket Number field, excluding the last three digits (i.e., CP18-13). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, contact (202) 502-8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings.

    In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/​docs-filing/​esubscription.asp.

    Start Signature

    Dated: August 29, 2018.

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    Footnotes

    1.  A pig is a tool that the pipeline company inserts into and pushes through the pipeline for cleaning the pipeline, conducting internal inspections, or other purposes.

    Back to Citation

    [FR Doc. 2018-19243 Filed 9-5-18; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Published:
09/06/2018
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2018-19243
Pages:
45233-45234 (2 pages)
Docket Numbers:
Docket No. CP18-13-000
PDF File:
2018-19243.pdf