02-5821. Federal Acquisition Regulation; Definitions for “Contract Action” and “Contracting Action”  

  • Start Preamble Start Printed Page 13053

    AGENCIES:

    Department of Defense (DoD), General Services Administration (GSA), and National Aeronautics and Space Administration (NASA).

    ACTION:

    Final rule.

    SUMMARY:

    The Civilian Agency Acquisition Council and the Defense Acquisition Regulations Council (Councils) have agreed to amend the Federal Acquisition Regulation (FAR) to provide for consistent use of the term “contract action” and to make other editorial changes to clarify the text.

    DATES:

    Effective Date: April 4, 2002.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    The FAR Secretariat, Room 4035, GS Building, Washington, DC 20405, (202) 501-4755, for information pertaining to status or publication schedules. For clarification of content, contact Ms. Victoria Moss, Procurement Analyst, at (202) 501-4764. Please cite FAC 2001-06, FAR case 2000-402.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    A. Background

    This rule amends the FAR to provide for consistent use of the term “contract action.” The rule changes the term “contracting action” to “contract action” throughout the FAR and makes other editorial changes to clarify the text.

    DoD, GSA, and NASA published a proposed rule in the Federal Register on May 31, 2000 (65 FR 34894). One respondent submitted comments on the proposed rule. Based on those comments, the rule was changed to provide for more consistent use of the term “contract action” and to place definitions in the proper FAR sections.

    This is not a significant regulatory action and, therefore, was not subject to review under section 6(b) of Executive Order 12866, Regulatory Planning and Review, dated September 30, 1993. This rule is not a major rule under 5 U.S.C. 804.

    B. Regulatory Flexibility Act

    The Department of Defense, the General Services Administration, and the National Aeronautics and Space Administration certify that this final rule will not have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq., because we are not substantively changing procedures for award and administration of contracts. We did not receive any comments regarding this determination as a result of publication of the proposed rule in the Federal Register on May 31, 2000 (65 FR 34894).

    C. Paperwork Reduction Act

    The Paperwork Reduction Act does not apply because the changes to the FAR do not impose information collection requirements that require Office of Management and Budget approval under 44 U.S.C. 3501, et seq.

    Start List of Subjects

    List of Subjects in 48 CFR Parts 1, 5, 6, 8, 17, 19, 32, and 52

    • Government procurement
    End List of Subjects Start Signature

    Dated: March 6, 2002.

    Al Matera,

    Director, Acquisition Policy Division.

    End Signature Start Amendment Part

    Therefore, DoD, GSA, and NASA amend 48 CFR parts 1, 5, 6, 8, 17, 19, 32, and 52 as set forth below:

    End Amendment Part Start Amendment Part

    1. The authority citation for 48 CFR parts 1, 5, 6, 8, 17, 19, 32, and 52 continues to read as follows:

    End Amendment Part Start Authority

    Authority: 40 U.S.C. 486(c); 10 U.S.C. chapter 137; and 42 U.S.C. 2473(c).

    End Authority Start Part

    PART 1—FEDERAL ACQUISITION REGULATIONS SYSTEM

    End Part Start Amendment Part

    2. Revise section 1.403 to read as follows:

    End Amendment Part
    Individual deviations.

    Individual deviations affect only one contract action, and, unless 1.405(e) is applicable, may be authorized by the agency head. The contracting officer must document the justification and agency approval in the contract file.

    Start Amendment Part

    3. Revise the introductory paragraph of section 1.404 to read as follows:

    End Amendment Part
    Class deviations.

    Class deviations affect more than one contract action. When an agency knows that it will require a class deviation on a permanent basis, it should propose a FAR revision, if appropriate. Civilian agencies, other than NASA, must furnish a copy of each approved class deviation to the FAR Secretariat.

    * * * * *
    [Amended]
    Start Amendment Part

    4. Amend the first sentence of section 1.701 by removing the word “contracting” and adding “contract” in its place.

    End Amendment Part
    [Amended]
    Start Amendment Part

    5. Amend section 1.703 in paragraph (a) by removing the word “contracting” each time it appears (3 times) and adding “contract” in its place.

    End Amendment Part Start Amendment Part

    6. Amend section 1.705 by revising paragraph (b) to read as follows:

    End Amendment Part
    Supersession and modification.
    * * * * *

    (b) The contracting officer need not cancel the solicitation if the D&F, as modified, supports the contract action.

    Start Part

    PART 5—PUBLICIZING CONTRACT ACTIONS

    End Part Start Amendment Part

    7. Revise section 5.001 to read as follows:

    End Amendment Part
    Definition.

    Contract action, as used in this part, means an action resulting in a contract, as defined in subpart 2.1, including actions for additional supplies or services outside the existing contract scope, but not including actions that are within the scope and under the terms of the existing contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.

    Start Part

    PART 6—COMPETITION REQUIREMENTS

    [Amended]
    End Part Start Amendment Part

    8. Amend section 6.502 in paragraph (b)(1)(iv) by removing the word “contracting” and adding “contract” in its place.

    End Amendment Part Start Part

    PART 8—REQUIRED SOURCES OF SUPPLIES AND SERVICES

    End Part Start Amendment Part

    9. Revise section 8.102 to read as follows:

    End Amendment Part
    Policy.

    When practicable, agencies must use excess personal property as the first source of supply for agency and cost-reimbursement contractor requirements. Agency personnel must make positive efforts to satisfy agency requirements by obtaining and using excess personal property (including that suitable for adaptation or substitution) before initiating a contract action.

    Start Part Start Printed Page 13054

    PART 17—SPECIAL CONTRACTING METHODS

    [Amended]
    End Part Start Amendment Part

    10. Amend section 17.104 in the second sentence of paragraph (b) by removing the words “contracting action” and adding “contract” in their place.

    End Amendment Part Start Amendment Part

    11. Amend section 17.503 by revising the introductory text of paragraph (b) to read as follows:

    End Amendment Part
    Determinations and findings requirements.
    * * * * *

    (b) If the Economy Act order requires contract action by the servicing agency, the D&F must also include a statement that at least one of the following circumstances applies:

    * * * * *
    Start Part

    PART 19—SMALL BUSINESS PROGRAMS

    [Amended]
    End Part Start Amendment Part

    12. Amend section 19.302 in the first sentence of paragraph (h)(4) by removing the words “contracting action” and adding “contract action” in their place.

    End Amendment Part Start Amendment Part

    13. Amend section 19.505 by revising paragraph (c) to read as follows:

    End Amendment Part
    Rejecting Small Business Administration recommendations.
    * * * * *

    (c) If the head of the contracting activity agrees that the contracting officer's rejection was appropriate—

    (1) Within 1 working day, the SBA procurement center representative may request the contracting officer to suspend action on the acquisition until the SBA Administrator appeals to the agency head (see paragraph (f) of this section); and

    (2) The SBA must be allowed 15 working days after making such a written request, within which the Administrator of SBA—

    (i) May appeal to the Secretary of the Department concerned; and

    (ii) Must notify the contracting officer whether the further appeal has, in fact, been taken. If notification is not received by the contracting officer within the 15-day period, it is deemed that the SBA request to suspend the contract action has been withdrawn and that an appeal to the Secretary was not taken.

    * * * * *
    Start Part

    PART 32—CONTRACT FINANCING

    End Part Start Amendment Part

    14. Revise the introductory paragraph of section 32.000 to read as follows:

    End Amendment Part
    Scope of part.

    This part prescribes policies and procedures for contract financing and other payment matters. This part addresses—

    * * * * *
    Start Amendment Part

    15. Amend section 32.001 by revising the definition “Contract action” to read as follows:

    End Amendment Part
    Definitions.
    * * * * *

    Contract action means an action resulting in a contract, as defined in subpart 2.1, including actions for additional supplies or services outside the existing contract scope, but not including actions that are within the scope and under the terms of the existing contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.

    * * * * *
    [Amended]
    Start Amendment Part

    16. Amend section 32.703-2 in the first sentence of the introductory text of paragraph (a) by removing the words “contracting action” and adding “contract action” in their place; by removing the semicolon after the word “available” and adding a comma in its place; and by removing the comma after the word “provided”.

    End Amendment Part Start Amendment Part

    17. Amend section 32.705-1 by revising paragraph (a) to read as follows:

    End Amendment Part
    Clauses for contracting in advance of funds.

    (a) Insert the clause at 52.232-18, Availability of Funds, in solicitations and contracts if the contract will be chargeable to funds of the new fiscal year and the contract action will be initiated before the funds are available.

    * * * * *
    Start Part

    PART 52—SOLICITATION PROVISIONS AND CONTRACT CLAUSES

    End Part Start Amendment Part

    18. Amend section 52.232-18 by revising the introductory text to read as follows:

    End Amendment Part
    Availability of Funds.

    As prescribed in 32.705-1(a), insert the following clause:

    * * * * *
    End Supplemental Information

    [FR Doc. 02-5821 Filed 3-19-02; 8:45 am]

    BILLING CODE 6820-EP-P

Document Information

Published:
03/20/2002
Department:
National Aeronautics and Space Administration
Entry Type:
Rule
Action:
Final rule.
Document Number:
02-5821
Pages:
13053-13054 (2 pages)
Docket Numbers:
FAC 2001-06, FAR Case 2000-402, Item II
RINs:
9000-AI76
Topics:
Government procurement
PDF File:
02-5821.pdf
CFR: (17)
48 CFR 1.403
48 CFR 1.404
48 CFR 1.701
48 CFR 1.703
48 CFR 1.705