07-3879. Notice of Quarterly Report (April 1, 2007-June 30, 2007)  

  • Start Preamble

    AGENCY:

    Millennium Challenge Corporation.

    SUMMARY:

    The Millennium Challenge Corporation (MCC) is reporting for the Start Printed Page 44868quarter April 1, 2007 through June 30, 2007 with respect to both assistance provided under Section 605 of the Millennium Challenge Act of 2003 (Pub. L. 108-199, Division D (the Act)), and transfers of funds to other federal agencies pursuant to Section 619 of that Act. The following report shall be made available to the public by means of publication in the Federal Register and on the Internet Web site of the MCC (www.mcc.gov) in accordance with Section 612(b) of the Act.

    Assistance Provided Under Section 605

    ProjectsObligatedObjectivesCumulative disbursementsMeasures
    Country: Madagascar  Year: 2007  Quarter 3  Total Obligation: $109,773,000
    Entity to which the assistance is provided: MCA Madagascar Total Quarterly Disbursement: 3,485,000
    Land Tenure Project$37,803,000Increase Land Titling and Security$2,279,000Legislative proposal (“loin de cadrage”) reflecting the PNF submitted to Parliament and passed. Percentage of land documents inventoried, restored, and/or digitized. Average time and cost required to carry out property-related transactions at the local and/or national land services offices. Time/cost to respond to information request, issue titles and to modify titles after the first land right. Number of land disputes reported and resolved in the target zones and sites of implementation. Percentage of land in the zones that is demarcated and ready for titling. Promote knowledge and awareness of land tenure reforms among inhabitants in the zones (surveys).
    Finance Project$35,888,000Increase Competition in the Financial Sector$1,495,000Submission to Parliament and passage of new laws recommended by outside experts and relevant commissions. CPA Association (CSC) list of accountants registered. Maximum check clearing delay. Volume of funds in payment system and number of transactions. Public awareness of new financial instruments (surveys). Report of credit and payment information to a central database.
    Number of holders of new denomination T-bill holdings, and T-bill issuance outside Antananarivo as measured by Central Bank report of redemption date.
    Volume of production covered by warehouse receipts in the zones.
    Volume of MFI lending in the zones.
    MFI portfolio-at-risk delinquency rate.
    Number of new bank accounts in the zones.
    Agricultural Business Investment Project$17,683,000Improve Agricultural Projection Technologies and Market Capacity in Rural Areas$2,607,000Number of rural producers receiving or soliciting information from ABCs about the opportunities. Zones identified and description of beneficiaries within each zone submitted. Number of cost-effective investment strategies developed. Number of plans prepared. Number of farmers and business employing technical assistance received.
    Program Administration* and Control, Monitoring and Evaluation$18,399,000$8,076,000
    Pending Subsequent Report **$3,499,000
    Start Printed Page 44869
    ProjectsObligatedObjectivesCumulative disbursementsMeasures
    Country: Honduras  Year: 2007  Quarter 3  Total Obligation: $215,000,000
    Entity to which the assistance is provided: MCA Honduras  Total Quarterly Disbursement: $3,497,000
    Rural Development Project*$72,195,000Increase the productivity and business skills of farmers who operate small and medium-size farms and their employees$5,264,000Hours of technical assistance delivered to Program Farmers (thousands). Funds lent by MCA-Honduras to financial institutions (cumulative). Hours of technical assistance to financial institutions (cumulative). Lien Registry equipment installed. Kilometers of farm-to-market road upgraded (cumulative).
    Transportation Project$125,700,000Reduce transportation costs between targeted production centers and national, regional and global markets$478,000Kilometers of highway upgraded. Kilometers of secondary road upgraded. Number of weight stations built.
    Program Administration* and Control, Monitoring and Evaluation$17,105,000$1,253,000
    Pending Subsequent Report **$2,290,000
    ProjectsObligatedObjectivesCumulative disbursementsMeasures
    Country: Cape Verde  Year: 2007  Quarter 3  Total Obligation: $110,078,000
    Entity to which the assistance is provided: MCA Cape Verde  Total Quarterly Disbursement: $2,077,000
    Watershed and Agricultural Support$10,848,000Increase agricultural production in three targeted watershed areas on three islands$247,000Productivity: Horticulture (tons per hectare). Value-added for farms and agribusiness (millions of dollars).
    Infrastructure Improvement$78,760,000Increase integration of the internal market and reduce transportation costs$4,084,000Volume of goods shipped between Praia and other islands (tons). Mobility Ratio: Percentage of beneficiary population who take at least 5 trips per month. Savings on transport costs from improvements (million dollars).
    Private Sector Development$7,200,000Spur private sector development on all islands through increased investment in the priority sectors and through financial sector reform$88,000Value added in priority sectors above current trends (escudos) Volume of private investment in priority sectors above current trends.
    Program Administration* and Control, Monitoring and Evaluation$13,270,000$4,979,000
    Pending Subsequent Report **$3,815,000
    ProjectsObligatedObjectivesCumulative disbursementsMeasures
    Country: Nicaragua  Year: 2007  Quarter 3  Total Obligation: $174,925,000
    Entity to which the assistance is provided: MCA Nicaragua  Total Quarterly Disbursement: $2,300,000
    Property Regularization Project$26,400,000Increase Investment by strengthening property rights$685,000Automated registry-cadastre database installed. Number of parcels with a registered title, rural and urban (total of 21,000 and 22,000, rural and urban, respectively). Projected areas demarcated. Number of projected area management plans implemented. Number of conflicts resolved by program mediation.
    Transportation Project$92,800,000Reduce transportation costs between Leon and Chinandega and national, regional and global markets$58,000N-1 Road: Kilometers of road upgraded. Secondary Roads: Kilometers of secondary road upgraded.
    Start Printed Page 44870
    Rural Business Development Project$33,500,000Increase the value added of farms and enterprises in the region$1,623,000Rural business development centers: Value of TA and support services delivered to program businesses. Improvement of water supply for farming and forest production: Watershed Management Action Plan. Funds disbursed for improvement of water supply for farming and forest production projects.
    Program Administration*, Due Diligence, Monitoring and Evaluation$22,225,000$2,700,000
    Pending Subsequent Report **$0$2,445,000
    ProjectsObligatedObjectivesCumulative disbursementsMeasures
    Country: Georgia  Year: 2007  Quarter 3  Total Obligation: $294,693,000
    Entity to which the assistance is provided: MCA Georgia  Total Quarterly Disbursement: $3,500,000
    Regional Infrastructure Rehabilitation$211,700,000Key Regional Infrastructure Rehabilitated$13,330,000Reduction in journey time: Akhalkalaki-Ninotsminda-Teleti (hours). Reduction in vehicle operating costs (cumulative). Increase in internal regional traffic volumes (cumulative). Decreased technical losses. Reduction in the production of greenhouse gas emissions measured in tons of CO2 equivalent.
    Increased in collection rate of GGIC.
    Number of household beneficiaries served by RID projects (cumulative).
    Actual operations and maintenance expenditures (USD).
    Regional Enterprise Development$47,500,000Enterprises in Regions Developed$6,439,000Increase in annual revenue in portfolio companies (in 1,000 USD) Increase in number of portfolio company employees and number of local suppliers. Increase in portfolio companies” wages and payments to local suppliers (in 1,000 USD). Jobs created. Increase in aggregate incremental net revenue to project assisted firms (in 1,000 USD and cumulative over five years).
    Direct household net income (in 1,000 USD cumulative over five years).
    Direct household net income for market information initiative beneficiaries (in 1,000 USD cumulative over five years).
    Number of beneficiaries.
    Program Administration*, Due Diligence, Monitoring and Evaluation$35,493,000$4,806,000
    Pending Subsequent Report **$0$4,462,000
    ProjectsObligatedObjectiveCumulative disbursementsMeasures
    Country: Vanuatu  Year: 2007  Quarter 3  Total Obligation: $65,690,000
    Entity to which the assistance is provided: MCA Vanuatu  Total Quarterly Disbursement: $0
    Transportation Infrastructure Project$60,690,000Facilitate transportation to increase tourism and business development$2,000Traffic volume (average annual daily traffic). Days road is closed (number per annum). Number of S-W Bay, Malekula flights cancelled due to flooding (per annum). Time of wharf (hours/vessel).
    Start Printed Page 44871
    Program Administration*, Due Diligence, Monitoring and Evaluation$5,000,000$1,035,000
    Pending Subsequent Report **$684,000
    ProjectsObligatedObjectiveCumulative disbursementsMeasures
    Country: Armenia  Year: 2007  Quarter 3  Total Obligation: $235,150,000
    Entity to which the assistance is provided: MCA Armenia  Total Quarterly Disbursement: $2,157,000
    Irrigated Agriculture Project$145,680,000Increase agricultural productivity and Improve Quality of Irrigation$2,496,000Increase in hectares covered by HVA crops (i.e., vegetables, potato, fruits, grapes). Percentage of respondents satisfied with irrigation services. Share of WUA water charges compared WUA annual operations and maintenance cost (percentage). Number of farmers using better on-farm water management: drip irrigation; ET Gage, and soil moisture monitoring. Loans provided under the project (USD in thousands).
    Rural Road Rehabilitation Project$67,100,000Better access to economic and social infrastructure$445,000Annual increase in irrigated land in Project area (hectares). State budget expenditures on maintenance of irrigation system (AMD in millions). Reduction in Kilowatt hours used (thousand KWh). Share of water losses compared to total water intake (percentage). Share of WUA water charges compared to WUA annual operations and maintenance cost (percentage).
    Program Administration*, Due Diligence, Monitoring and Evaluation$22,370,000$1,382,000
    Pending Subsequent Report **$0$1,425,000
    ProjectsObligatedObjectiveCumulative disbursementsMeasures
    Country: Benin  Year: 2007  Quarter 3  Total Obligation: $305,761,000
    Entity to which the assistance is provided: MCA Benin  Total Quarterly Disbursement: $1,872,000
    Access to Financial Services$19,650,000Expand Access to Financial Services$271,000Strengthen capacity of select financial institutions. Strengthen monitoring capacity of Supervisory Authority. Total incremental increase in value of new credit extended and savings received by financial institutions participating in the project. Share value of all loans outstanding that have one or more installments of principal past due over 30 days. Total number of loans guaranteed by land titles, per year.
    Access to Justice$34,270,000Improved Ability of Justice System to Enforce Contracts and Reconcile Claims$76,000Increase efficiency and improved services of courts and the arbitration center. Increase access to court system. Improve enterprise registration center.
    Access to Land$36,020,000Strengthen property rights and increase investment in rural and urban land$45,000Value of investments made to rural land parcels per year; land investment data will come from self-reported data through EMICoV. Value of investments made to urban land parcels per year; land investment data will come from self-reported data through EMICoV.
    Start Printed Page 44872
    Access to Markets$168,020,000Improve Access to Markets through Improvements to the Port of Cotonou$4,000Total volume of exports and imports passing through Port of Cotonou, per year in million metric tons.
    Program Administration*, Due Diligence, Monitoring and Evaluation$22,370,000$2,770,000
    Pending Subsequent Report **$02,159,000
    ProjectsObligatedObjectiveCumulative disbursementsMeasures
    Country: Ghana  Year: 2007  Quarter 3  Total Obligation: $536,639,000
    Entity to which the assistance is provided: MCA Ghana  Total Quarterly Disbursement: $2,174,000
    Agriculture Project$239,552,000Enhance Profitability of cultivation, services to agriculture and product handling in support of the expansion of commercial agriculture among groups of smallholder farms$0Number of hectares irrigated. Number of days to conduct a land transaction. Number of land disputes in the pilot registration districts. Registration of land rights in the pilot registration districts. Volume of products passing through post-harvest treatment (metric tons). Portfolio-at-risk of agriculture loan fund. Value of loans disbursed to clients from agricultural loan fund (US$). Number of additional loans. Vehicle operating costs (on roads requiring minor, medium and major rehabilitation).
    Rural Development$101,288,000Strengthen the rural institutions that provide services complementary to, and supportive of, agricultural and agriculture business development$0Time/quality per procurement. Score card of citizen satisfaction with services. Gross enrollment rates. Gender parity in school enrollment. Distance to collect water. Time to collect water. Distance to sanitation facility. Travel time to sanitation facility. Incidence of guinea worm, diarrhea or bilharzias. Average number of days lost due to guinea worm, diarrhea or bilharzias. Percentage of households, schools, and agricultural processing plants in target districts with electricity. Number of inter-bank transactions. Value of deposit accounts in rural banks.
    Transportation$136,804,000Reduce the transportation costs affecting agriculture commerce at sub-regional levels$0Volume capacity ratio. Vehicles per hour at peak hour. Travel time at peak hour. International roughness index. Annual average daily traffic. Travel time for walk-on passengers and small vehicles.
    Travel time for trucks.
    Program Administration*, Due Diligence, Monitoring and Evaluation$22,370,000$0
    Pending Subsequent Report **$2,915,000
    * Program administration funds are used to pay items such as salaries, rent, and the cost of office equipment.
    ** Pending subsequent report amounts represent funds that have been disbursed to the country for specific projects and activities that will be reported by project in the subsequent quarterly.
    619 Transfer funds
    U.S. agency to which funds were transferredAmountDescription of program or project
    $0
    Start Signature
    Start Printed Page 44873

    Dated: August 3, 2007.

    Frances C. McNaught,

    Vice President, Congressional and Public Affairs, Millennium Challenge Corporation.

    End Signature End Preamble

    [FR Doc. 07-3879 Filed 8-8-07; 8:45 am]

    BILLING CODE 9211-03-P

Document Information

Published:
08/09/2007
Department:
Millennium Challenge Corporation
Entry Type:
Notice
Document Number:
07-3879
Pages:
44867-44873 (7 pages)
Docket Numbers:
MCC 07-08
PDF File:
07-3879.pdf