2011-15260. Union Electric Company (dba Ameren Missouri); Notice of Application Accepted for Filing and Soliciting Motions To Intervene and Protests  

  • Start Preamble

    Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection.

    a. Type of Application: New Major License.

    b. Project No.: 2277-023.

    c. Date filed: June 24, 2008.

    d. Applicant: Union Electric Company (dba Ameren Missouri).

    e. Name of Project: Taum Sauk Pumped Storage Project.

    f. Location: On the East Fork of the Black River, in Reynolds County, Missouri. The project occupies no federal lands.

    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).

    h. Applicant Contact: Michael O. Lobbig, P.E., Managing Supervisor, Hydro Licensing, Ameren Missouri, 3700 S. Lindbergh Blvd, St. Louis, MO 63127; telephone 314-957-3427; e-mail at mlobbig@ameren.com.

    i. FERC Contact: Janet Hutzel, telephone (202) 502-8675, or by e-mail at janet.hutzel@ferc.gov.

    j. Deadline for filing motions to intervene and protests: August 15, 2011.

    All documents may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site http://www.ferc.gov/​docs-filing/​efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at http://www.ferc.gov/​docs-filing/​ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY, (202) 502-8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and seven copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426.

    The Commission's Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Start Printed Page 35875Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.

    k. This application has been accepted, but is not ready for environmental analysis at this time.

    l. The existing Taum Sauk Pumped Storage Project consists of: (1) A lower reservoir impounded by a concrete gravity dam downstream of the confluence of the East Fork Black River and Taum Sauk Creek; (2) an upper reservoir on the top of Proffit Mountain impounded by a rebuilt roller-compacted concrete dam; (3) vertical shaft, rock and concrete-lined tunnel sections, and a penstock conduit; (4) a pump-generating plant with two reversible pump units and two motor generators with a total installed capacity of 408 megawatts; (5) an excavated tailrace and open channel to the lower reservoir; (6) a 138-kilovolt switchyard/substation; (7) a gravel and sedimentation trap (bin wall) on the East Fork of the Black River; and (8) associated ancillary equipment.

    m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's Web site at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. A copy is also available for inspection and reproduction at the address in item h above.

    You may also register online at http://www.ferc.gov/​docs-filing/​esubscription.asp to be notified via e-mail of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support.

    n. Anyone may submit a protest or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, 385.211, and 385.214. In determining the appropriate action to take, the Commission will consider all protests filed, but only those who file a motion to intervene in accordance with the Commission's Rules may become a party to the proceeding. Any protests or motions to intervene must be received on or before the specified deadline date for the particular application.

    All filings must (1) bear in all capital letters the title “PROTEST” or “MOTION TO INTERVENE;” (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application.

    Start Signature

    Dated: June 14, 2011.

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    [FR Doc. 2011-15260 Filed 6-17-11; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Comments Received:
0 Comments
Published:
06/20/2011
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2011-15260
Pages:
35874-35875 (2 pages)
Docket Numbers:
Project No. 2277-023
PDF File:
2011-15260.pdf