Start Preamble
On June 5, 2014, Commission staff issued a letter to Pennamaquan Tidal Power LLC (Pennamaquan Tidal) stating that Pennamaquan Tidal's proposed study plan for the Pennamaquan Tidal Power Plant Project (P-13884) filed on December 12, 2013, meets the requirements of section 5.11 of the Commission's regulations and that the Integrated Licensing Process (ILP) can resume. According to section 5.11(e) of the Commission's regulations, the next step in the ILP is the initial study plan meeting. In its June 5, 2014, letter, Commission staff indicated that the initial study plan meeting must be held within 75 days of, but no sooner than 60 days from, June 5, 2014. Accordingly, Pennamaquan Tidal has scheduled the meetings listed below:
Meetings in Bangor, ME
Dates and Times: August 6 and 7, 2014. 8:00 a.m. to 5:00 p.m.
Location: Maine Department of Environmental Protection, Eastern Maine Regional Office, 106 Hogan Road, Bangor, Maine 04401.
Contact: Ramez Attiya, Pennamaquan Tidal, (281) 467-0846.
Meeting in Pembroke, ME
Date and Time: August 8, 2014. 12:00 p.m. to 2:00 p.m.
Location: Pembroke Town Office, 48 Old County Road, Pembroke, ME 04666.
Contact: Ramez Attiya, Pennamaquan Tidal, (281) 467-0846.
A revised process plan that includes new dates for completing the ILP is provided below:
Start SignatureResponsible party Pre-filing milestone Date 1 FERC regulation Pennamaquan Issue Public Notice for NOI/PAD 7/19/12 5.3(d)(2) Pennamaquan File NOI/PAD with FERC 7/19/12 5.5, 5.6 FERC Initiate Tribal Consultation 8/18/12 5.7 FERC Issue Notice of Commencement of Proceeding; Scoping Document 1 (SD1) 9/14/12 5.8 FERC Project Environmental Site Review and Scoping Meetings 10/25/12 10/26/12 5.8(b)(viii) All stakeholders PAD/SD1 Comments and Study Requests Due 12/4/12 5.9 FERC Issue Scoping Document 2 (if needed) 1/18/13 5.1 Pennamaquan File Proposed Study Plan (PSP) 12/12/13 5.11(a) All stakeholders Proposed Study Plan Meeting (scheduled for 8/6/14 to 8/8/14) Between 8/4/14 and 8/19/14 2 5.11(e) All stakeholders Proposed Study Plan Comments Due 10/18/14 5.12 Pennamaquan File Revised Study Plan 11/17/14 5.13(a) All stakeholders Revised Study Plan Comments Due 12/2/14 5.13(b) Start Printed Page 38884 FERC Director's Study Plan Determination 12/17/14 5.13(c) Mandatory Conditioning Agencies Any Study Disputes Due 1/6/15 5.14(a) Dispute Panel Third Dispute Panel Member Selected 1/21/15 5.14(d)(3) Dispute Panel Dispute Resolution Panel Convenes 1/26/15 5.14(d) Pennamaquan Applicant Comments on Study Disputes Due 1/31/15 5.14(j) Dispute Panel Dispute Resolution Panel Technical Conference 2/5/15 5.14(j) Dispute Panel Dispute Resolution Panel Findings Issued 2/25/15 5.14(k) FERC Director's Study Dispute Determination 3/17/15 5.14(l) Pennamaquan First Study Season Spring/Summer 2015 5.15(a) Pennamaquan Initial Study Report 12/17/15 5.15(c)(1) All stakeholders Initial Study Report Meeting 1/1/16 5.15(c)(2) Pennamaquan Initial Study Report Meeting Summary 1/16/16 5.15(c)(3) All stakeholders Any Disputes/Requests to Amend Study Plan Due 2/15/16 5.15(c)(4) All stakeholders Responses to Disputes/Amendment Requests Due 3/16/16 5.15(c)(5) FERC Director's Determination on Disputes/Amendments 4/15/16 5.15(c)(6) Second study season if necessary. Schedule would be adjusted accordingly. Pennamaquan File Preliminary Licensing Proposal (PLP) 12/14/16 3 5.16(a) All stakeholders PLP Comments Due 3/14/17 5.16(e) 1 If a due date falls on a weekend or holiday, the due date is the following business day. Dates prior to August 2014 are the dates when the events occurred, rather than due dates. 2 Commission staff issued a letter on June 5, 2014, requiring the proposed study plan meeting to be held between August 4, 2014, and August 19, 2014. Subsequent deadlines in the process plan were calculated from the deadline of August 19, 2014. 3 The date for filing of the PLP is a staff estimate. Dated: July 1, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-15997 Filed 7-8-14; 8:45 am]
BILLING CODE 6717-01-P
Document Information
- Published:
- 07/09/2014
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 2014-15997
- Pages:
- 38883-38884 (2 pages)
- Docket Numbers:
- Project No. 13884-001
- PDF File:
- 2014-15997.pdf