2014-28758. Public Service Company of Colorado; Notice of Application Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
-
Start Preamble
Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection:
a. Type of Application: Application for Temporary Variance of Minimum Flow Requirement.
b. Project No.: 12589-020.
c. Date Filed: November 12, 2014.
d. Applicant: Public Service Company of Colorado d.b.a. Xcel Energy (licensee).
e. Name of Project: Tacoma Project.
f. Location: Cascade Creek in San Juan and La Plata counties, Colorado.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Bruce Cotie, Hydro-West Manager, (303) 273-4917, or bruce.e.cotie@xcelenergy.com.
i. FERC Contact: John Aedo, (415) 369-3335, or john.aedo@ferc.gov.
j. Deadline for filing comments, motions to intervene, protests, and recommendations is 30 days from the issuance date of this notice by the Commission. The Commission strongly encourages electronic filing. Please file motions to intervene, protests, comments, or recommendations using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. Please include the project number (P-12589-020) on any comments, motions to intervene, protests, or recommendations filed.
k. Description of Request: The licensee requests a temporary variance of the maximum flow diversion requirements in Cascade Creek. U.S. Forest Service Section 4(e) Condition No. 17 (found in the project license) limits diversions to the flowline of no greater than 2 cubic feet per second (cfs), when natural inflow is less than 9 cfs. However, the licensee requests that it be allowed to divert 4 cfs into the flowline from December 15, 2014 to April 15, 2015. The licensee states that the increased diversion is necessary to keep a temporary, above-ground flowline from freezing while it performs repairs to a damaged section of flowline during the winter.
l. Locations of the Application: A copy of the application is available for inspection and reproduction at the Commission's Public Reference Room, located at 888 First Street NE., Room 2A, Washington, DC 20426, or by calling (202) 502-8371. This filing may also be viewed on the Commission's Web site at http://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1-866-208-3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502-8659. A copy is also available for inspection and reproduction at the address in item (h) above.
m. Individuals desiring to be included on the Commission's mailing list should so indicate by writing to the Secretary of the Commission.
n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission's Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application.
o. Filing and Service of Responsive Documents: Any filing must (1) bear in all capital letters the title “COMMENTS”, “PROTEST”, or “MOTION TO INTERVENE” as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All Start Printed Page 73058comments, motions to intervene, or protests must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). All comments, motions to intervene, or protests should relate to project works which are the subject of the variance. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. If an intervener files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
Start SignatureDated: December 2, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-28758 Filed 12-8-14; 8:45 am]
BILLING CODE 6717-01-P
Document Information
- Published:
- 12/09/2014
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 2014-28758
- Pages:
- 73057-73058 (2 pages)
- Docket Numbers:
- Project No. 12589-020
- PDF File:
- 2014-28758.pdf