2018-18247. Defense Federal Acquisition Regulation Supplement: Repeal of DFARS Clause “Removal of Contractor's Employees” (DFARS Case 2018-D042)  

  • Start Preamble

    AGENCY:

    Defense Acquisition Regulations System, Department of Defense (DoD).

    ACTION:

    Final rule.

    SUMMARY:

    DoD is issuing a final rule amending the Defense Federal Acquisition Regulation Supplement (DFARS) to remove a clause that is no longer necessary.

    DATES:

    Effective August 24, 2018.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Ms. Carrie Moore, telephone 571-372-6093.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    I. Background

    DoD is amending the DFARS to remove the DFARS clause 252.247-7006, Removal of Contractor's Employees, and the associated clause prescription at DFARS 247.270-4. The DFARS clause served as an agreement from the contractor to only use experienced, responsible, and capable people to perform the work under the stevedoring contract. The clause also advised the contractor that the contracting officer may require the contractor to remove from the job, employees who endanger persons or property or whose employment is inconsistent with the interest of military security.

    II. Discussion and Analysis

    The information conveyed in DFARS clause 252.247-7006 is directly related to performance of the work under a stevedoring contract. It is more appropriate to define what the Government considers an experienced, responsible, and capable employee to be in a performance work statement, not a contract clause, because those requirements may change depending on various factors of the work being performed. If the need to remove employees from performing under the contract exists, it should be identified in the performance work statement. The removal and replacement of employees directly relates to the contractor's ability to perform and staff the work under the contract. As such, this DFARS clause is unnecessary and can be removed.

    The removal of this DFARS text supports a recommendation from the DoD Regulatory Reform Task Force. On February 24, 2017, the President signed Executive Order (E.O.) 13777, “Enforcing the Regulatory Reform Agenda,” which established a Federal policy “to alleviate unnecessary regulatory burdens” on the American people. In accordance with E.O. 13777, DoD established a Regulatory Reform Task Force to review and validate DoD regulations, including the DFARS. A public notice of the establishment of the DFARS Subgroup to the DoD Regulatory Reform Task Force, for the purpose of reviewing DFARS provisions and clauses, was published in the Federal Register at 82 FR 35741 on August 1, 2017, and requested public input. One public comment was received on this Start Printed Page 42789clause. The comment recommended elimination of the clause, as it is unnecessary. Subsequently, the DoD Task Force reviewed the requirements of DFARS clause 252.247-7006, Removal of Contractor's Employees, and determined that the DFARS coverage was unnecessary and recommended removal.

    III. Applicability to Contracts At or Below the Simplified Acquisition Threshold and for Commercial Items, Including Commercially Available Off-the-Shelf Items

    This rule only removes obsolete DFARS clause 252.247-7006, Removal of Contractor's Employees. Therefore, the rule does not impose any new requirements on contracts at or below the simplified acquisition threshold and for commercial items, including commercially available off-the-shelf items.

    IV. Executive Orders 12866 and 13563

    E.O. 12866, Regulatory Planning and Review, and E.O. 13563, Improving Regulation and Regulatory Review, direct agencies to assess all costs and benefits of available regulatory alternatives and, if regulation is necessary, to select regulatory approaches that maximize net benefits (including potential economic, environmental, public health and safety effects, distributive impacts, and equity). E.O. 13563 emphasizes the importance of quantifying both costs and benefits, of reducing costs, of harmonizing rules, and of promoting flexibility. The Office of Management and Budget, Office of Information and Regulatory Affairs (OIRA), has determined that this is not a significant regulatory action as defined under section 3(f) of E.O. 12866 and, therefore, was not subject to review under section 6(b). This rule is not a major rule as defined at 5 U.S.C. 804(2).

    V. Executive Order 13771

    This rule is not an E.O. 13771, Reducing and Controlling Regulatory Costs, regulatory action, because this rule is not significant under E.O. 12866.

    VI. Publication of This Final Rule for Public Comment Is Not Required by Statute

    The statute that applies to the publication of the Federal Acquisition Regulation (FAR) is Office of Federal Procurement Policy statute (codified at title 41 of the United States Code). Specifically, 41 U.S.C. 1707(a)(1) requires that a procurement policy, regulation, procedure or form (including an amendment or modification thereof) must be published for public comment if it relates to the expenditure of appropriated funds, and has either a significant effect beyond the internal operating procedures of the agency issuing the policy, regulation, procedure, or form, or has a significant cost or administrative impact on contractors or offerors. This final rule is not required to be published for public comment, because DoD is not issuing a new regulation; rather, this rule merely removes an obsolete requirement from the DFARS.

    VII. Regulatory Flexibility Act

    Because a notice of proposed rulemaking and an opportunity for public comment are not required to be given for this rule under 41 U.S.C. 1707(a)(1) (see section VI. of this preamble), the analytical requirements of the Regulatory Flexibility Act (5 U.S.C. 601 et seq.) are not applicable. Accordingly, no regulatory flexibility analysis is required and none has been prepared.

    VIII. Paperwork Reduction Act

    The rule does not contain any information collection requirements that require the approval of the Office of Management and Budget under the Paperwork Reduction Act (44 U.S.C. chapter 35).

    Start List of Subjects

    List of Subjects in 48 CFR Parts 247 and 252

    • Government procurement
    End List of Subjects Start Signature

    Jennifer Lee Hawes,

    Regulatory Control Officer, Defense Acquisition Regulations System.

    End Signature

    Therefore, 48 CFR parts 247 and 252 are amended as follows:

    Start Amendment Part

    1. The authority citation for 48 CFR parts 247 and 252 continues to read as follows:

    End Amendment Part Start Authority

    Authority: 41 U.S.C. 1303 and 48 CFR chapter 1.

    End Authority Start Part

    PART 247—TRANSPORTATION

    [Amended]
    End Part Start Amendment Part

    1. Amend section 247.270-4 by—

    End Amendment Part Start Amendment Part

    a. Removing paragraph (f); and

    End Amendment Part Start Amendment Part

    b. Redesignating paragraph (g) as paragraph (f).

    End Amendment Part Start Part

    PART 252—SOLICITATION PROVISIONS AND CONTRACT CLAUSES

    [Removed and Reserved]
    End Part Start Amendment Part

    2. Remove and reserve section 252.247-7006.

    End Amendment Part
    [Amended]
    Start Amendment Part

    3. Amend section 252.247-7007, in the introductory text, by removing “247.270-4(g)” and adding “247.270-(f)” in its place.

    End Amendment Part End Supplemental Information

    [FR Doc. 2018-18247 Filed 8-23-18; 8:45 am]

    BILLING CODE 6820-ep-P

Document Information

Effective Date:
8/24/2018
Published:
08/24/2018
Department:
Defense Acquisition Regulations System
Entry Type:
Rule
Action:
Final rule.
Document Number:
2018-18247
Dates:
Effective August 24, 2018.
Pages:
42788-42789 (2 pages)
Docket Numbers:
Docket DARS-2018-0041
RINs:
0750-AK04
Topics:
Government procurement
PDF File:
2018-18247.pdf
CFR: (3)
48 CFR 247.270-4
48 CFR 252.247-7006