2019-07850. Notice of Final Federal Agency Actions on the Hunts Point Interstate Access Improvement Project, Bronx County, New York
-
Start Preamble
AGENCY:
Federal Highway Administration (FHWA), DOT.
ACTION:
Notice of limitation on claims for judicial review of actions by FHWA and other Federal agencies.
SUMMARY:
This notice announces action taken by FHWA and other Federal agencies that are final. The actions relate to the Hunts Point Interstate Access Improvement Project located in Bronx County, New York.
DATES:
By this notice, FHWA is advising the public of final agency actions subject to 23 U.S.C. 39(l)(1). A claim seeking judicial review of the Federal agency actions on the highway project will be barred unless the claim is filed on or before September 16, 2019. If the Federal law that authorizes judicial review of a claim provides a time period of less than 150 days for filing such claim, then that shorter time period still applies.
Start Further InfoFOR FURTHER INFORMATION CONTACT:
Richard J. Marquis, Division Administrator, Federal Highway Administration, Leo W. O'Brien Federal Building, Albany, New York 12207, Telephone (518) 431-4127.
End Further Info End Preamble Start Supplemental InformationSUPPLEMENTARY INFORMATION:
Notice is hereby given that FHWA and other Federal agencies have taken final agency actions by issuing approvals for the following highway project in the State of New York: Hunts Point Interstate Access Improvement Project, Bronx County, New York. The Hunts Point Interstate Access Improvement Project will include the creation of a split interchange at Edgewater Road and Leggett Avenue. Two new ramps to and from the westbound Bruckner Expressway will be constructed at Leggett Avenue, allowing westbound Bruckner Expressway traffic access to and egress from the Hunts Point Peninsula via Leggett Avenue. Three ramps to and from Edgewater Road will allow eastbound traffic from the Bruckner Expressway and southbound traffic from Sheridan Boulevard to access the Hunts Point Peninsula and will also allow traffic to exit the Hunts Point Peninsula onto northbound Sheridan Boulevard.
The actions by the Federal agencies, and the laws under which such actions were taken, are described in the FHWA Final Environmental Impact Statement Start Printed Page 16558(FEIS) for the project, approved by FHWA in the Record of Decision (ROD) issued on April 9, 2019, and in other documents in the FHWA administrative record. The FEIS, ROD, and other documents in the FHWA administrative record files are available by contacting FHWA at the address provided above. The FEIS and ROD can also be viewed and downloaded from the project website at: https://www.dot.ny.gov/southbronx/hunts-point.
This notice applies to FHWA agency decisions as of the issuance date of this notice and all laws under which such actions were taken, including but not limited to:
1. General: National Environmental Policy Act (NEPA) [42 U.S.C. 4321-4351]; Federal-Aid Highway Act [23 U.S.C. 109].
2. Air: Clean Air Act [42 U.S.C. 7401-7671(q)] (Transportation Conformity).
3. Noise: Noise Control Act of 1972 [42 U.S.C. 4901 et seq.].
4. Land: Section 4(f) of the Department of Transportation Act of 1966 [49 U.S.C. 303]; Landscaping and Scenic Enhancement (Wildflowers) [23 U.S.C. 319].
5. Wildlife: Endangered Species Act [16 U.S.C. 1531-1544 and Section 1536], Marine Mammal Protection Act [16 U.S.C. 1361], Fish and Wildlife Coordination Act [16 U.S.C. 661-667(d)], Migratory Bird Treaty Act [16 U.S.C. 703-712], Magnuson-Stevens Fishery Conservation and Management Act of 1976, as amended [16 U.S.C. 1801 et seq.].
6. Historic and Cultural Resources: Section 106 of the National Historic Preservation Act of 1966, as amended [16 U.S.C. 470(f) et seq.]; Archeological Resources Protection Act of 1977 [16 U.S.C. 470(aa)-11]; Archeological and Historic Preservation Act [16 U.S.C. 469-469(c)]; Native American Grave Protection and Repatriation Act (NAGPRA) [25 U.S.C. 3001-3013].
7. Social and Economic: Civil Rights Act of 1964 [42 U.S.C. 2000(d)-2000(d)(1)]; American Indian Religious Freedom Act [42 U.S.C. 1996].
8. Right of Way: Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970 [42 U.S.C. 4601 et seq.].
9. Wetlands and Water Resources: Coastal Zone Management Act, 16 U.S.C. 1451-1465; Land and Water Conservation Fund (LWCF), 16 U.S.C. 4601-4604; Safe Drinking Water Act (SDWA), 42 U.S.C. 300(f)-300(j)(6); 33 U.S.C. 401-406; Flood Disaster Protection Act, 42 U.S.C. 4001-4128; Clean Water Act (Section 404, Section 401, Section 319) [33 U.S.C. 1251-1377].
10. Hazardous Materials: Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), 42 U.S.C. 9601-9675; Superfund Amendments and Reauthorization Act of 1986 (SARA); Resource Conservation and Recovery Act (RCRA), 42 U.S.C. 6901-6992(k).
11. Executive Orders: E.O. 11990 Protection of Wetlands; E.O. 11988 Floodplain Management; E.O. 12898, Federal Actions to Address Environmental Justice in Minority Populations and Low Income Populations; E.O. 11593 Protection and Enhancement of Cultural Resources; E.O. 13007 Indian Sacred Sites; E.O. 13287 Preserve America; E.O. 13175 Consultation and Coordination with Indian Tribal Governments; E.O. 11514 Protection and Enhancement of Environmental Quality; E.O. 13112 Invasive Species.
(Catalog of Federal Domestic Assistance Program Number 20.205, Highway Planning and Construction. The regulations implementing Executive Order 12372 regarding intergovernmental consultation on Federal programs and activities apply to this program.)
Start SignatureIssued on: April 11, 2019.
Richard J. Marquis,
Division Administrator, Albany, NY.
[FR Doc. 2019-07850 Filed 4-18-19; 8:45 am]
BILLING CODE 4910-RY-P
Document Information
- Published:
- 04/19/2019
- Department:
- Federal Highway Administration
- Entry Type:
- Notice
- Action:
- Notice of limitation on claims for judicial review of actions by FHWA and other Federal agencies.
- Document Number:
- 2019-07850
- Dates:
- By this notice, FHWA is advising the public of final agency actions subject to 23 U.S.C. 39(l)(1). A claim seeking judicial review of the Federal agency actions on the highway project will be barred unless the claim is filed on or before September 16, 2019. If the Federal law that authorizes judicial review of a claim provides a time period of less than 150 days for filing such claim, then that shorter time period still applies.
- Pages:
- 16557-16558 (2 pages)
- PDF File:
- 2019-07850.pdf
- Supporting Documents:
- » Final Federal Agency Actions: Proposed Highway in California
- » Final Federal Agency Actions: Proposed Highway Projects in Texas
- » Transfer and Sanction Programs
- » Experimental Project To Evaluate Proposals for Delegation of Certain Program-Wide FHWA Responsibilities to States
- » Environmental Impact Statements; Availability, etc.: Multiple Counties in Alabama; Rescission
- » Federal Agency Actions: SH 205 From North of John King (Rockwall County Line) to SH 78 in Collin County, TX
- » Federal Agency Actions: Interstate 95 in City of Fredericksburg and Counties of Spotsylvania, Stafford, Prince William, and Fairfax, VA
- » Environmental Impact Statements; Availability, etc.: I-495 and I-270 Managed Lanes Study, Montgomery and Prince George's Counties, MD and Fairfax County, VA
- » Federal Agency Actions: Proposed Highway in California
- » Federal Agency Actions: California; Proposed Highway