2019-22101. ANR Pipeline Company; Notice of Application  

  • Start Preamble

    Take notice that on October 1, 2019, ANR Pipeline Company (ANR), 700 Louisiana Street, Suite 700, Houston, Texas 77002-2700, filed in Docket No. CP20-1-000 an application pursuant to sections 7(b) and 7(c) of the Natural Gas Act (NGA) for authorization to acquire certain natural gas storage assets currently leased by ANR from Mid Michigan Gas Storage Company (Mid Michigan) at the Austin, Goodwell, Lincoln-Freeman, Loreed, and Reed City storage fields, all located in central Michigan. Specifically, ANR requests authorization to: (1) Abandon the existing lease agreements with Mid Michigan to remove Mid Michigan as owner and lessor; (2) change ANR from lessee to owner of the subject assets; and (3) establish a new interim lease arrangement with Mid Michigan related to the Mid Michigan-owned based gas in the subject storage fields, all as more fully set forth in the application which is on file with the Commission and open to public inspection. The filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's website web at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208-3676 or TYY, (202) 502-8659.

    Any questions concerning this application may be directed to Sorana Linder, Director, Modernization & Certificates, ANR Pipeline Company, 700 Louisiana Street, Suite 700, Houston, Texas 77002-2700, by telephone at (832) 320-5209, or by email at sorana_linder@tcenergy.com.

    Pursuant to section 157.9 of the Commission's rules (18 CFR 157.9), within 90 days of this Notice, the Commission staff will issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff's issuance of the environmental assessment (EA) for this proposal. The issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and Start Printed Page 54139the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff's EA.

    There are two ways to become involved in the Commission's review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit seven copies of filings made in the proceeding with the Commission and must mail a copy to the applicant and to every other party. Only parties to the proceeding can ask for court review of Commission orders in the proceeding.

    However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission's rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest.

    Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission's environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission's environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission's final order.

    As of the February 27, 2018 date of the Commission's order in Docket No. CP16-4-001, the Commission will apply its revised practice concerning out-of-time motions to intervene in any new NGA section 3 or section 7 proceeding.[1] Persons desiring to become a party to a certificate proceeding are to intervene in a timely manner. If seeking to intervene out-of-time, the movant is required to “show good cause why the time limitation should be waived,” and should provide justification by reference to factors set forth in Rule 214(d)(1) of the Commission's Rules and Regulations.[2]

    The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the “eFiling” link at http://www.ferc.gov. Persons unable to file electronically should submit an original and three copies of the protest or intervention to the Federal Energy regulatory Commission, 888 First Street NE, Washington, DC 20426.

    Comment Date: 5:00 p.m. Eastern Time on October 24, 2019.

    Start Signature

    Dated: October 3, 2019.

    Nathaniel J. Davis, Sr.,

    Deputy Secretary.

    End Signature End Preamble

    Footnotes

    1.  Tennessee Gas Pipeline Company, L.L.C., 162 FERC ¶ 61,167 at ¶ 50 (2018).

    Back to Citation

    [FR Doc. 2019-22101 Filed 10-8-19; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Published:
10/09/2019
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2019-22101
Dates:
5:00 p.m. Eastern Time on October 24, 2019.
Pages:
54138-54139 (2 pages)
Docket Numbers:
Docket No. CP20-1-000
PDF File: