2021-08493. CSX Corporation and CSX Transportation, Inc., et al.-Control and Merger-Pan Am Systems, Inc., Pan Am Railways, Inc., Boston and Maine Corporation, Maine Central Railroad Company, Northern Railroad, Pan Am Southern LLC, Portland Terminal ...  

  • Start Preamble Start Printed Page 22091

    AGENCY:

    Surface Transportation Board.

    ACTION:

    Decision No. 2 in STB Finance Docket No. 36472; Notice of Proposed Procedural Schedule and Request for Comments.

    SUMMARY:

    The Surface Transportation Board (Board) invites public comments on a proposed procedural schedule for this proceeding. On February 25, 2021, CSX Corporation (CSXC), CSX Transportation Inc. (CSXT), 747 Merger Sub 2, Inc. (747 Merger Sub 2), Pan Am Systems, Inc. (Systems), Pan Am Railways, Inc. (PAR), Boston and Maine Corporation (Boston & Maine), Maine Central Railroad Company (Maine Central), Northern Railroad (Northern), Portland Terminal Company (Portland Terminal), Springfield Terminal Railway Company (Springfield Terminal), Stony Brook Railroad Company (Stony Brook), and Vermont & Massachusetts Railroad Company (V&M) (collectively, Applicants) submitted a filing with the Board. The applicants are seeking approval for: (1) CSXC, CSXT, and 747 Merger Sub 2 to control the seven railroads controlled by Systems and PAR, and (2) CSXT to merge six of the seven railroads into CSXT. In Decision No. 1, served and published on March 25, 2021, the Board accepted the February 25 submission as a prefiling notification, thus allowing Applicants to supplement their submission with the requisite information for a “significant” transaction in accordance with the Board's regulations, between April 25 and June 25, 2021 (i.e., two to four months after the prefiling notice was submitted).

    DATES:

    Written comments on the Board's proposed procedural schedule must be filed by May 6, 2021.

    ADDRESSES:

    Any filing submitted in this proceeding should be filed with the Board via e-filing on the Board's website. In addition, one copy of each filing must be sent (and may be sent by email only if service by email is acceptable to the recipient) to each of the following: (1) Secretary of Transportation, 1200 New Jersey Avenue SE, Washington, DC 20590; (2) Attorney General of the United States, c/o Assistant Attorney General, Antitrust Division, Room 3109, Department of Justice, Washington, DC 20530; (3) CSX's [1] and 747 Merger Sub 2's representative, Anthony J. LaRocca, Steptoe & Johnson LLP, 1330 Connecticut Ave. NW, Washington, DC 20036; (4) Systems',[2] PAR's, and PAR Railroads' representative, Robert B. Culliford, Pan Am Systems, Inc., 1700 Iron Horse Park, North Billerica, MA 01862; and (5) any other person designated as a Party of Record on the service list.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Amy Ziehm at (202) 245-0391. Assistance for the hearing impaired is available through the Federal Relay Service at (800) 877-8339.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    On April 1, 2021, Applicants filed a petition to establish a revised procedural schedule as directed by the Board in Decision No. 1. The Board will propose modifications to the Applicants' proposed schedule. Under 49 U.S.C. 11325(c), the Board must conclude the evidentiary proceedings for a significant transaction no later than 180 days after publication of notice in the Federal Register that the Board has accepted the application. Here, the Applicants have proposed a schedule in which the record would close 127 days after Federal Register publication. Although section 11325(c) allows the Board to set a shorter schedule, the Board finds that a schedule based on the full 180 days allowed by the statute is more appropriate. As the Board noted in Decision No. 1, slip op. at 8, in a “significant” transaction proceeding, applicants are required to submit more detailed information regarding competitive effects, operating plans, and other issues than in a “minor” transaction proceeding. Also, unlike in a “minor” transaction proceeding, parties in a “significant” transaction proceeding are permitted to file responsive applications, including inconsistent applications. Id. Given these procedural features of “significant” transactions, the Board finds that the schedule proposed by Applicants would be too compressed. Indeed, the Applicants' proposed 127-day schedule here is only 22 days longer than the 105-day schedule [3] the Applicants proposed when they sought to classify this transaction as “minor.” [4] (See Notice 14.) Moreover, the Applicants provide no explanation why such an expedited schedule is needed. Therefore, the Board will propose the following procedural schedule.[5]

    April 26, 2021Application due.
    May 26, 2021Board notice of acceptance of application to be published in the Federal Register.
    June 16, 2021Notices of intent to participate in this proceeding due.
    Start Printed Page 22092
    June 25, 2021Descriptions of anticipated responsive, including inconsistent, applications due. Petitions for waiver or clarification with respect to such applications due. Comments, protests, requests for conditions, and any other evidence and argument in opposition to the Application or Related Transactions due. This includes any comments from the U.S. Department of Justice (DOJ) and U.S. Department of Transportation (USDOT).6
    July 26, 2021Responsive, including inconsistent, applications due.
    September 8, 2021Responses to comments, protests, requests for conditions, and other opposition due, including to DOJ and USDOT filings. Responses to responsive, including inconsistent, applications due. Rebuttal in support of the Application and Related Transactions due.
    October 8, 2021Rebuttal in support of responsive, including inconsistent, applications due.
    TBDPublic hearing (if necessary).7
    November 22, 2021Final briefs due.8 (Close of the record.)
    February 18, 2022Service date of final decision.
    March 20, 2022Effective date of final decision.

    The Board invites all interested persons to submit written comments on the proposed procedural schedule. Comments must be filed by May 6, 2021. The proposed dates in this decision are subject to change depending on the comments received or other circumstances.

    The Board notes that Applicants' proposed procedural schedule included a due date for the filing of their Safety Integration Plan (SIP), as required by 49 CFR 1180.1(f)(3). The Board considers the SIP as part of its environmental review process or, if an environmental review is not required, the Board will establish case-specific procedures. 49 CFR 1106.4(b), (c). Applicants claim that an environmental review would not be required for this transaction. (Notice 34-38; CSXC and CSXT Letter to Danielle Gosselin, Acting Director, OEA, Apr. 7, 2021 (Environmental Comment EI-30550).) The Board's Office of Environmental Analysis is reviewing information submitted by Applicants on the transaction's anticipated environmental impacts and the Board will address environmental review issues in a subsequent decision.

    Start Signature

    Decided: April 19, 2021.

    By the Board, Board Members Begeman, Fuchs, Oberman, Primus, and Schultz.

    Jeffrey Herzig,

    Clearance Clerk.

    End Signature End Supplemental Information

    Footnotes

    1.  CSXT is a wholly owned subsidiary of CSXC. CSXC and CSXT are referred to collectively as CSX.

    Back to Citation

    2.  Systems directly and wholly owns PAR, which in turn directly and wholly owns four rail carriers: Boston & Maine, Maine Central, Portland Terminal, and Springfield Terminal. Boston & Maine directly and wholly owns Northern and Stony Brook, as well as a 98% interest in V&M. These seven rail carriers will be referred to collectively as the PAR Railroads.

    Back to Citation

    3.  A 105-day schedule is the maximum time permitted for the evidentiary proceeding in a “minor” transaction under 49 U.S.C. 11325(d).

    Back to Citation

    4.  Applicants' submission was filed as an application for approval as a “minor” transaction pursuant to 49 CFR 1180.2(c). However, in Decision No. 1, the Board found that the proposed transaction should be classified as a “significant” transaction, which must meet different procedural and informational requirements, and that Applicants' submission therefore could not be treated as an application. The Board determined that it would consider the February 25, 2021 submission a prefiling notification, as required in significant transactions. See 49 CFR 1180.4(b)(1).

    Back to Citation

    5.  The schedule proposed here is similar in duration to the schedule adopted for a “significant” transaction in Canadian Pacific Railway—Control—Dakota, Minnesota & Eastern Railroad, FD 35081 (STB served Dec. 27, 2007).

    Back to Citation

    6.  Although Applicants propose that such filings be due on July 9, 2021, which would be 44 days after the Federal Register notice accepting the application, section 11325(c)(1) calls for such filings to be submitted 30 days after the Federal Register notice.

    7.  The Board will decide whether to conduct a public hearing, which would be held between the filing of rebuttals and final briefs, in a later decision after the record has been more fully developed. See 49 U.S.C. 11324(a) (“The Board shall hold a public hearing unless the Board determines that a public hearing is not necessary in the public interest.”).

    8.  The Board will also determine the page limits for final briefs in a later decision after the record has been more fully developed.

    Back to Citation

    [FR Doc. 2021-08493 Filed 4-23-21; 8:45 am]

    BILLING CODE 4915-01-P

Document Information

Published:
04/26/2021
Department:
Surface Transportation Board
Entry Type:
Notice
Action:
Decision No. 2 in STB Finance Docket No. 36472; Notice of Proposed Procedural Schedule and Request for Comments.
Document Number:
2021-08493
Dates:
Written comments on the Board's proposed procedural schedule must be filed by May 6, 2021.
Pages:
22091-22092 (2 pages)
Docket Numbers:
Docket No. FD 36472, Docket No. FD 36472 (Sub-No. 1), Docket No. FD 36472 (Sub-No. 2), Docket No. FD 36472 (Sub-No. 3), Docket No. FD 36472 (Sub-No. 4), Docket No. FD 36472 (Sub-No. 5), Docket No. AB 1312X
PDF File: