2021-16063. Commission Information Collection Activities (FERC-537); Comment Request; Extension  

  • Start Preamble

    AGENCY:

    Federal Energy Regulatory Commission, Department of Energy.

    ACTION:

    Notice of information collection and request for comments.

    SUMMARY:

    In compliance with the requirements of the Paperwork Reduction Act of 1995, the Federal Energy Regulatory Commission (Commission or FERC) is soliciting public comment on a renewal of currently approved information collection, FERC-537 (Gas Pipeline Certificates: Construction, Acquisition, and Abandonment), which will be submitted to the Office of Management and Budget (OMB) for review.

    DATES:

    Comments on the collection of information are due August 27, 2021.

    ADDRESSES:

    Send written comments on FERC-537 to OMB through www.reginfo.gov/​public/​do/​PRAMain. Attention: Federal Energy Regulatory Commission Desk Officer. Please identify the OMB Control Number (1902-0060) in the subject line of your comments. Comments should be sent within 30 days of publication of this notice to www.reginfo.gov/​public/​do/​PRAMain.

    Please submit copies of your comments to the Commission. You may submit copies of your comments (identified by Docket No. IC21-24-000) by one of the following methods:

    Electronic filing through http://www.ferc.gov,, is preferred.

    • Electronic Filing: Documents must be filed in acceptable native applications and print-to-PDF, but not in scanned or picture format.
    • For those unable to file electronically, comments may be filed by USPS mail or by hand (including courier) delivery.

    Mail via U.S. Postal Service Only: Addressed to: Federal Energy Regulatory Commission, Secretary of the Commission, 888 First Street NE, Washington, DC 20426.

    Hand (Including Courier) Delivery: Deliver to: Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, MD 20852.

    Instructions: OMB submissions must be formatted and filed in accordance with submission guidelines at www.reginfo.gov/​public/​do/​PRAMain. Using the search function under the “Currently Under Review” field, select Federal Energy Regulatory Commission; click “submit,” and select “comment” to the right of the subject collection.

    FERC submissions must be formatted and filed in accordance with submission guidelines at: http://www.ferc.gov. For user assistance, contact FERC Online Support by email at ferconlinesupport@ferc.gov, or by phone at: (866) 208-3676 (toll-free).

    Docket: Users interested in receiving automatic notification of activity in this docket or in viewing/downloading comments and issuances in this docket may do so at https://www.ferc.gov/​ferc-online/​overview.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Ellen Brown may be reached by email at DataClearance@FERC.gov, telephone at (202) 502-8663.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    Title: FERC-537 (Gas Pipeline Certificates: Construction, Acquisition, and Abandonment).

    OMB Control No.: 1902-0060.

    Type of Request: Three-year extension of the FERC-537 information collection requirements with no changes to the reporting requirements.

    Abstract: The FERC-537 information collection requires natural gas companies to file the necessary information with FERC in order for the Commission to determine if the requested certificate should be authorized. The data required to be submitted in a normal certificate filing consists of identification of the company and responsible officials, factors considered in the location of the facilities and the impact on the area for environmental considerations. Also to be submitted are the following, as applicable to the specific request:

    • Flow diagrams showing the design capacity for engineering design verification and safety determination;
    • Cost of proposed facilities, plans for financing, and estimated revenues and expenses related to the proposed facility for accounting and financial evaluation.
    • Existing and proposed storage capacity and pressures and reservoir engineering studies for requests to increase storage capacity;
    • An affidavit showing the consent of existing customers for abandonment of service requests.

    Certain self-implementing construction and abandonment programs do not require the filing of applications. However, those types of programs do require the filing of annual reports, so many less significant actions can be reported in a single filing/response and less detail would be Start Printed Page 40555required. Additionally, requests for an increase of pipeline capacity must include a statement that demonstrates compliance with the Commission's Certificate Policy Statement by making a showing that the cost of the expansion will not be subsidized by existing customers and that there will not be adverse economic impacts to existing customers, competing pipelines or their customers, nor to landowners and to surrounding communities.

    The Commission reviews and analyses the information filed under the regulations subject to FERC-537 to determine whether to approve or deny the requested authorization. If the Commission failed to collect these data, it would lose its ability to review relevant information to determine whether the requested certificate should be authorized. The 60-day notice published on May 21, 2021 [1] and received no comments.

    Type of Respondents: Jurisdictional natural gas companies.

    Estimate of Annual Burden[2] : The Commission estimates the annual public reporting burden for the information collection as:

    FERC-537 (Gas Pipeline Certificates: Construction, Acquisition, and Abandonment) 3

    Number of respondentsAnnual number of responses per respondentTotal number of responsesAverage annual burden & cost per response 4Total average annual burden hours & total annual costCost per respondent ($)
    (1)(2)(1) * (2) = (3)(4)(3) * (4) = (5)(5) ÷ (1) 5
    18 CFR 157.5-.11 (Interstate Certificate and Abandonment Applications)311.3943.09500 hrs.; $41,50021,545 hrs; $1,788,235$57,685
    18 CFR 157.53 (Pipeline Purging/Testing Exemptions)11150 hrs.; $4,15050 hrs.; $4,1504,150
    18 CFR 157.201-.209; 157.211; 157.214-.218 (Blanket Certificates Prior to Notice Filings)242.12551200 hrs.; $16,60010,200 hrs.; $846,60035,275
    18 CFR 157.201-.209; 157.211; 157.214-.218 (Blanket Certificates—Annual Reports)162116250 hrs.; $4,1508,100 hrs.; $672,3004,150
    18 CFR 284.11 (NGPA Section 311 Construction—Annual Reports)7517550 hrs.; $4,1503,750 hrs.; $311,2504,150
    18 CFR 284.86 (Request for Waiver of Capacity Release Regulations)311.3943.0910 hrs.; $830430.90 hrs.; $35,764.701,153.70
    18 CFR 284.13(e) and 284.126(a) (Interstate and Intrastate Bypass Notice)21230 hrs.; $2,49060 hrs.; $4,9802,490
    18 CFR 284.221 (Blanket Certificates)111100 hrs.; $8,300100 hrs.; $8,3008,300
    18 CFR 284.224 (Hinshaw Blanket Certificates)11175 hrs.; $6,22575 hrs.; $6,2256,225
    18 CFR 157.5-.11; 157.13-.20 (Non-facility Certificate or Abandonment Applications111.3614.9675 hrs.; $6,2251,122 hrs.; $93,1268,466
    Total394.1445,432.90 hrs.; $3,770,930.70

    Comments: Comments are invited on: (1) Whether the collection of information is necessary for the proper performance of the functions of the Commission, including whether the information will have practical utility; (2) the accuracy of the agency's estimate of the burden and cost of the collection of information, including the validity of the methodology and assumptions used; (3) ways to enhance the quality, utility and clarity of the information collection; and (4) ways to minimize the burden of the collection of information on those who are to respond, including the use of automated collection techniques or other forms of information technology.

    Start Signature

    Dated: July 22, 2021.

    Debbie-Anne A. Reese,

    Deputy Secretary.

    End Signature End Supplemental Information

    Footnotes

    2.  Burden is defined as the total time, effort, or financial resources expended by persons to generate, maintain, retain, or disclose or provide information to or for a Federal agency. Refer to 5 CFR 1320.3 for additional information.

    Back to Citation

    3.  Changes to estimated number of respondents were based on average number of respondents over the past three years.

    4.  The estimates for cost per response are derived using the following formula: Average Burden Hours per Response * $83.00/hour = Average cost/response. The figure is the 2020 FERC average hourly cost (for wages and benefits) of $83.00 (and an average annual salary of $172,329/year). Commission staff is using the FERC average salary because we consider any reporting requirements completed in response to the FERC-537 to be compensated at rates similar to the work of FERC employees.

    5.  Each of the figures in this column are rounded to the nearest dollar.

    6.  A Certificate Abandonment Application would require waiver of the Commission's capacity release regulations in 18 CFR 284.8; therefore this activity is associated with Interstate Certificate and Abandonment Applications.

    Back to Citation

    [FR Doc. 2021-16063 Filed 7-27-21; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Published:
07/28/2021
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Action:
Notice of information collection and request for comments.
Document Number:
2021-16063
Dates:
Comments on the collection of information are due August 27, 2021.
Pages:
40554-40555 (2 pages)
Docket Numbers:
Docket No. IC21-24-000
PDF File:
2021-16063.pdf