    On April 30, 2021, the Town of Bedford, Virginia filed an application for a new major license for the 5.0-megawatt Bedford Hydroelectric Project No. 5596 (Bedford Project or project). On August 17, 2023, Commission staff issued a notice of intent to prepare an Environmental Assessment (EA) to evaluate the effects of relicensing the Bedford Project. The notice of intent included a schedule for preparing a single EA.

    By this notice, Commission staff is updating the procedural schedule for completing the EA. The revised schedule is shown below. Further revisions to the schedule may be made as appropriate.

    MilestoneTarget date
    Issue EAJuly 2024.1

    Any questions regarding this notice may be directed to Andy Bernick at (202) 502-8660 or andrew.bernick@ferc.gov.

    Start Signature

    Dated: April 11, 2024.

    Debbie-Anne A. Reese,

    Acting Secretary.

    End Signature End Preamble

    Footnotes

    1.  The Council on Environmental Quality's (CEQ) regulations under 40 CFR 1501.10(b)(1) (2022) require that EAs be completed within 1 year of the federal action agency's decision to prepare an EA. See National Environmental Policy Act, 42 U.S.C. 4321 et seq., as amended by section 107(g)(1)(B)(iii) of the Fiscal Responsibility Act of 2023, Public Law 118-5, 4336a, 137 Stat. 42.

    Back to Citation

    [FR Doc. 2024-08200 Filed 4-16-24; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Published:
04/17/2024
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2024-08200
Pages:
27428-27428 (1 pages)
Docket Numbers:
Project No. 5596-020
PDF File:
2024-08200.pdf