2016-24015. General Services Administration Acquisition Regulation (GSAR); Inflation of Acquisition-Related Thresholds  

  • Start Preamble

    AGENCY:

    Office of Acquisition Policy, General Services Administration (GSA).

    ACTION:

    Final rule.

    SUMMARY:

    The General Services Administration (GSA) is amending the General Services Administration Acquisition Regulation (GSAR) to make editorial changes. This case updates acquisition-related thresholds to align with the Federal Acquisition Regulation (FAR).

    DATES:

    Effective: October 4, 2016.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    For clarification of content, contact Ms. Janet Fry, Procurement Analyst, General Services Acquisition Policy Division, GSA, at 703-605-3167. For information pertaining to status or publication schedules, contact the Regulatory Secretariat at 202-501-4755. Please cite GSAR case 2016-G501.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    I. Discussion of Changes

    The General Services Administration (GSA) is amending the General Services Administration Acquisition Regulation (GSAR) to make editorial changes to align acquisition thresholds with the Federal Acquisition Regulation (FAR). There are no significant content changes resulting from this case.

    GSAR section 503.1004(a) is updated to remove the duplicative and unnecessary language regarding the outdated $5,000,000 FAR threshold for including FAR 52.203-14, Display of Hotline Poster(s). The remaining text regarding the $1,000,000 threshold for disaster assistance funds is retained with minor edits.

    Contract GSAR clauses 552.219-71, Notice to Offerors of Subcontracting Plan Requirements, and 552.219-72, Preparation, Submission and Negotiation of Subcontracting Plans, are updated to remove reference to the acquisition threshold of $650,000 and the language is restructured to no longer state the threshold but rather direct the reader to FAR 52.219-9 which clearly addresses the thresholds for subcontracting plans. By referencing back to the FAR, future inflation updates will not require amendments to the GSAR.

    GSAR clause 552.270-13, Proposals for Adjustment, is updated to replace “$500,000” with “$750,000.” Referencing the FAR for the threshold to prevent future updates was not an alternative.

    II. Public Comments Not Required

    41 U.S.C. 1707, Publication of proposed regulations, applies to the publication of the General Services Administration Acquisition Regulation. Paragraph (a)(1) of the statute requires that a procurement policy, regulation, procedure or form including amendment or modification thereof must be published for public comment if it has either a significant effect beyond the internal operating procedures of the agency issuing the policy, regulation, procedure, or form or has a significant cost or administrative impact on contractor or offerors. This final rule is not required to be published for public comment because it contains minor editorial updates without changing the meaning of content. The changes do not have a significant impact on the public.

    III. Executive Orders 12866 and 13563

    Executive Orders (E.O.s) 12866 and 13563 direct agencies to assess all costs and benefits of available regulatory alternatives and, if regulation is necessary, to select regulatory approaches that maximize net benefits (including potential economic, environmental, public health and safety effects, distributive impacts, and equity). E.O. 13563 emphasizes the importance of quantifying both costs and benefits, of reducing costs, of harmonizing rules, and of promoting flexibility. This is not a significant regulatory action and, therefore, was not subject to review under Section 6(b) of E.O. 12866, Regulatory Planning and Review, dated September 30, 1993. This rule is not a major rule under 5 U.S.C. 804.

    IV. Regulatory Flexibility Act

    The Regulatory Flexibility Analysis does not apply to this rule because this final rule does not constitute a significant GSAR revision and 41 U.S.C. 1707 does not require publication for public comment.

    V. Paperwork Reduction Act

    The final rule does not contain any information collection requirements that require approval of the Office of Management and Budget under the Paperwork Reduction Act (44 U.S.C. chapter 35).

    Start List of Subjects

    List of Subjects in 48 CFR Parts 503 and 552

    • Government procurement
    End List of Subjects Start Signature

    Dated: September 29, 2016.

    Jeffrey A. Koses,

    Senior Procurement Executive, Office of Acquisition Policy, Office of Government-wide Policy.

    End Signature

    Therefore, GSA is amending 48 CFR parts 503 and 552 as set forth below:

    Start Amendment Part

    1. The authority citation for 48 CFR parts 503 and 552 continues to read as follows:

    End Amendment Part Start Authority

    Authority: 40 U.S.C. 121(c).

    End Authority Start Part

    PART 503—IMPROPER BUSINESS PRACTICES AND PERSONAL CONFLICTS OF INTEREST

    End Part Start Amendment Part

    2. Amend section 503.1004 by revising paragraph (a) to read as follows:

    End Amendment Part
    Contract clauses.

    (a) GSA has exercised the authority provided at FAR 3.1004(b)(1)(i) to establish a lower threshold for inclusion of clause 52.203-14, Display of Hotline Poster(s). When the contract or order is funded with disaster assistance funds, the threshold is $1,000,000.

    * * * * *
    Start Part

    PART 552—SOLICITATION PROVISIONS AND CONTRACT CLAUSES

    End Part Start Amendment Part

    3. Amend section 552.219-71 by revising the date of the provision and the provision to read as follows:

    End Amendment Part
    Notice to Offerrors of Subcontracting Plan Requirements.
    * * * * *

    Notice to Offerrors of Subcontracting Plan Requirements (Oct 2016)

    The General Services Administration (GSA) is committed to assuring that maximum practicable opportunity is provided to small, HUBZone small, small disadvantaged, women-owned, veteran-owned, and service-disabled veteran-owned small business concerns to participate in the Start Printed Page 68336performance of this contract consistent with its efficient performance. GSA expects any subcontracting plan submitted pursuant to FAR 52.219-9, Small Business Subcontracting Plan, to reflect this commitment. The plan must demonstrate a creative and innovative program for involving small, HUBZone small, small disadvantaged, women-owned, veteran-owned, and service-disabled veteran-owned small business concerns as subcontractors in the performance of this contract.

    * * * * *
    Start Amendment Part

    4. Amend section 552.219-72 by revising the date of the provision and paragraph (a) to read as follows:

    End Amendment Part
    Preparation, Submission, and Negotiation of Subcontracting Plans.
    * * * * *

    Preparation, Submission, and Negotiation of Subcontracting Plans (Oct 2016)

    (a) When submitting a subcontracting plan in accordance with FAR 52.219-9, the offeror shall submit a subcontracting plan with its initial offer. The subcontracting plan will be negotiated concurrently with price and any required technical and management proposals, unless the offeror submits a previously-approved commercial plan.

    * * * * *
    Start Amendment Part

    5. Amend section 552.270-13 by revising the date of the provision; and removing from paragraph (c) introductory text and paragraph (c)(2) “500,000” and adding “750,000” in their places, respectively.

    End Amendment Part

    The revision reads as follows.

    Proposals for Adjustment.
    * * * * *

    Proposals for Adjustment (Oct 2016)

    * * * * *
    End Supplemental Information

    [FR Doc. 2016-24015 Filed 10-3-16; 8:45 am]

    BILLING CODE 6820-61-P