2014-05252. Flood Control Regulations, Marshall Ford Dam (Mansfield Dam and Lake Travis), Colorado River, Texas  

  • Start Preamble Start Printed Page 13563

    AGENCY:

    U.S. Army Corps of Engineers, DoD.

    ACTION:

    Final rule.

    SUMMARY:

    The U.S. Army Corps of Engineers (Corps) is amending the rules regarding use and administration of Marshall Ford Dam (Mansfield Dam and Lake Travis), Colorado River, Texas. In 1997, the Lower Colorado River Authority (LCRA) completed repayment of the federal government's contribution for acquisition and construction costs related to Mansfield Dam. Subsequently, the United States Bureau of Reclamation (USBR) has relinquished all rights and obligations to the project. However, the U.S. Department of the Interior and the USBR are referenced as project stakeholders in the Flood Control Regulations. Amending the referenced regulations to update project ownership will eliminate the current discrepancy between the regulations and associated project documents. The Fort Worth District of the Corps and LCRA have finalized a revised water control plan for Lake Travis (Marshall Ford Dam, aka Mansfield Dam). There is no intent to publish the updated water control plan in the Federal Register. Amending the regulations to indicate that the water control plan has been superseded would eliminate the need to amend the regulations each time the water control plan is modified.

    DATES:

    Effective Date: April 10, 2014.

    ADDRESSES:

    U.S. Army Corps of Engineers, ATTN: CECW-SWD (Sandy Gore), 441 G Street NW., Washington, DC 20314-1000.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Sandy Gore at 202-761-5237 or by email at sandy.l.gore@usace.army.mil.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    Executive Summary

    The purpose of this action is to amend the regulations to reflect changes in ownership and responsibilities of flood control management of Marshall Ford Dam (Mansfield Dam and Lake Travis) by the U.S. Army Corps of Engineers (USACE) and the Lower Colorado River Authority (LCRA) and to clarify that the published water control plan has been superseded. Specifically, 33 CFR part 208 is amended:

    (A) A change in project ownership. The Corps is revising 33 CFR 208.11(e) List of Projects, and 33 CFR 208.19, to indicate that the LCRA, is the responsible party for operating Marshall Ford Dam in the interest of flood control above elevation 714.

    (B) Revision of the Marshall Ford Dam (Mansfield Dam and Lake Travis) water control plan in 2012.

    (C) USACE intention to henceforth forego publication of the Marshall Ford Dam (Mansfield Dam and Lake Travis) water control plan in the Federal Register.

    (D) USACE and LCRA as sources for obtaining information regarding the most recently approved and therefore currently the effective water control plan.

    Background

    Mansfield Dam was funded, planned, and built by the United States Bureau of Reclamation (USBR) from February 1937 through September 1940. The Lower Colorado River Authority (LCRA) acquired the land for the project and paid for the majority of the costs related to the hydroelectric power facilities. The USBR was the project owner while LCRA was repaying the federal government contribution to the project. LCRA completed repayment in May 1997, and the USBR relinquished all rights and obligations to the project. USBR has formally requested USACE revise the water control manual (of which the water control plan is an integral part) and any other regulatory documents accordingly.

    As a result of Section 7 of the Flood Control Act of 1944, the U.S. Army Corps of Engineers (USACE) is responsible for prescribing a formal water control plan for regulation of the Lake Travis storage space allocated for flood control (elevation 681.0 to elevation 714.0). As per ER 1110-2-241, Use of Storage Allocated for Flood Control and Navigation at Non-Corps Projects (24 May 1990), paragraph 6.d.—Water Control Plan and Manual, the Corps of Engineers is responsible for developing the formal flood control regulation/water control plan, documenting the plan in a water control manual, and furnishing a copy of the manual to the project owner. A water control plan for Lake Travis was published in the Federal Register (33 CFR 208.19) in May of 1951. Subsequently, 33 CFR 208 was amended in April 1976, and again in April 1979, by revising Section 208.19 to reflect revision of the water control plan. Each of these three respective water control plans, and Section 208.11, identifies the U.S. Department of the Interior and/or the USBR as stakeholders in the project.

    In 2012, based on results of a recent study, USACE—Fort Worth District and LCRA finalized a jointly supported revision of the water control plan for Lake Travis. There being no requirement for publication of the water control plan in the Federal Register, USACE plans to henceforth forego doing so. Also in 2012, USACE—Fort Worth District and LCRA agreed on a formal Letter of Understanding (LOU) and a Water Control Agreement (WCA) in accordance with ER 1110-2-241, Use of Storage Allocated for Flood Control and Navigation at Non-Corps Projects (24 May 1990). LCRA has agreed to sign the LOU and the WCA, and adopt the new water control plan, upon amendment of the CFR to indicate the last published water control plan (April 1979) has been superseded.

    The Corps published the proposed rule in the Federal Register on 23 December 2013 (78 FR 77397). The Corps did not receive any comments in response to the proposed rule.

    Administrative Requirements

    Plain Language

    In compliance with the principles in the President's memorandum of June 1, 1998, (63 FR 31855) regarding plain language, this preamble is written using plain language. The use of “we” in this notice refers to the U.S. Army Corps of Engineers. We have also used the active voice, short sentences, and common everyday terms except for necessary technical terms.

    Paperwork Reduction Act

    This final rule does not impose any new information collection burden under the provisions of the Paperwork Reduction Act, 44 U.S.C. 3501 et seq. Therefore, this action is not subject to the Paperwork Reduction Act.

    Regulatory Flexibility Act (RFA), as Amended by the Small Business Regulatory Enforcement Fairness Act of 1996 (SBREFA), 5 U.S.C. 601 et seq.

    The RFA generally requires an agency to prepare a regulatory flexibility analysis of any rule subject to notice-and-comment rulemaking requirements under the Administrative Procedure Act or any other statute unless the agency certifies that the final rule will not have a significant economic impact on a substantial number of small entities. Small entities include small businesses, small organizations and small governmental jurisdictions.

    For purposes of assessing the impacts of this final rule on small entities, a small entity is defined as: (1) A small Start Printed Page 13564business based on Small Business Administration size standards; (2) a small governmental jurisdiction that is a government of a city, county, town, school district, or special district with a population of less than 50,000; or (3) a small organization that is any not-for-profit enterprise which is independently owned and operated and is not dominant in its field.

    After considering the economic impacts of this final rule on small entities, we believe that this action will not have a significant economic impact on a substantial number of small entities. The final rule is consistent with current agency practice, does not impose new substantive requirements, and therefore would not have a significant economic impact on a substantial number of small entities.

    Congressional Review Act

    The Congressional Review Act, 5 U.S.C. 801 et seq., as amended by the Small Business Regulatory Enforcement Fairness Act of 1996, generally provides that before a final rule may take effect, the agency promulgating the rule must submit a rule report, which includes a copy of the rule, to each House of the Congress and to the Comptroller General of the United States. We will submit a report containing this final rule and other required information to the U.S. Senate, the U.S. House of Representatives, and the Comptroller General of the United States. This final rule is not a “major rule” as defined by 5 U.S.C. 804(2).

    Start List of Subjects

    List of Subjects in 33 CFR Part 208

    • Dams
    • Flood control
    • Intergovernmental relations
    • Reservoirs
    End List of Subjects

    For the reasons set out in the preamble, the Corps amends 33 CFR part 208 as follows:

    Start Part

    PART 208—FLOOD CONTROL REGULATIONS

    End Part Start Amendment Part

    1. The authority citation for 33 CFR part 208 continues to read as follows:

    End Amendment Part Start Authority

    Authority: Sec. 7, 58 Stat. 890; 33 U.S.C. 709.

    End Authority Start Amendment Part

    2. Amend § 208.11(e) as follows:

    End Amendment Part Start Amendment Part

    a. Revise the entry for “Marshall Ford Dam & Res” on the “List of Projects” table; and

    End Amendment Part Start Amendment Part

    b. Revise footnote 4.

    End Amendment Part
    Regulations for use of storage allocated for flood control or navigation and/or project operation at reservoirs subject to prescription of rules and regulations by the Secretary of the Army in the interest of flood control and navigation.
    * * * * *

    (e) * * *

    List of Projects

    [Non-Corps projects with Corps Regulation Requirements]

    Project name 1 (1)State (2)County (3)Stream 1 (4)Project purpose 2 (5)Storage 1000 AF (6)Elev limits feet M.S.L.Area in acresAuthorizing legis.3 (11)Proj. owner 4 (12)
    Upper (7)Lower (8)Upper (9)Lower (10)
    *         *         *         *         *         *         *
    Marshall Ford Dam & ResTXTravisColorado RF NEIM779.8 810.5714.0 681.0681.0 618.029060 1895518955 8050PL 73-392 PL 78-534LCRA
    1 Cr—Creek; CS—Control Structure; Div—Diversion; DS—Drainage Structure; FG—Floodgate; Fk—Fork; GIWW—Gulf Intercoastal Waterway; Lk—Lake; L&D—Lock & Dam; PS—Pump Station; R—River; Res—Reservoir.
    2 F—Flood Control; N—Navigation; P—Corps Hydropower; E—Non Corps Hydropower; I—Irrigation; M—Municipal and/or Industrial Water Supply; C—Fish and Wildlife Conservation; A—Low Flow Augmentation or Pollution Abatement; R—Recreation; Q—Water Quality or Silt Control.
    3 FCA—Flood Control Act; FERC—Federal Energy Regulatory Comm; HD—House Document; PL—Public Law; PW—Public Works; RHA—River & Harbor Act; SD—Senate Document; WSA—Water Supply Act.
    4 Appl Pwr—Appalachian Power; Chln PUD—Chelan Cnty PUD 1; CLPC—CT Light & Power Co; Dgls PUD—Douglas Cnty PUD 1; DWR—Department of Water Resources; EB-MUD—East Bay Municipal Utility Dist; GRD—Grand River Dam Auth; Grnt PUD—Grant Cnty PUD 2; Hnbl—city of Hannibal; LCRA—Lower Colorado River Authority; M&T Irr—Modesto & Turlock Irr; Mrcd Irr—Merced Irr; NEPC—New England Power Co; Pgnt P&L—Pugent Sound Power & Light; Ptmc Comm—Upper Potomac R Comm; Rclm B—Reclamation Board; Rkfd—city of Rockford; Sttl—city of Seattle; Tac—City of Tacoma; Vale USBR—50% Vale Irr 50% USBR; WF&CWID—City of Wichita Falls and Wichita Cnty Water Improvement District No. 2; WMEC—Western MA Electric Co; YCWA—Yuba City Water Auth; Yolo FC&W—Yolo Flood Control & Water Conserv Dist.
    * * * * *
    Start Amendment Part

    3. Revise § 208.19 to read as follows:

    End Amendment Part
    Marshall Ford Dam and Reservoir (Mansfield Dam and Lake Travis), Colorado River, Texas.

    In the interest of flood control, the Lower Colorado River Authority (LCRA) shall operate the Marshall Ford Dam and Reservoir in accordance with the water control plan of regulation most recently approved by the U.S. Army Corps of Engineers (USACE), effective on the date specified in the approval. Information regarding the most recently approved water control plan of regulation may be obtained by contacting the LCRA offices in Austin, Texas, or the offices of the U.S. Army Corps of Engineers, Fort Worth Engineer District, in Fort Worth, Texas.

    Start Signature

    Dated March 6, 2014.

    Approved by:

    James C. Dalton,

    Chief of Engineering and Construction, U.S. Army Corps of Engineers.

    End Signature End Supplemental Information

    [FR Doc. 2014-05252 Filed 3-10-14; 8:45 am]

    BILLING CODE 3720-58-P

Document Information

Published:
03/11/2014
Department:
Engineers Corps
Entry Type:
Rule
Action:
Final rule.
Document Number:
2014-05252
Pages:
13563-13564 (2 pages)
Topics:
Dams, Flood control, Intergovernmental relations, Reservoirs
PDF File:
2014-05252.pdf
CFR: (2)
33 CFR 208.11
33 CFR 208.19