2015-06564. Acquisition Regulation: Technical and Administrative Changes to Department of Energy Acquisition Regulation  

  • Start Preamble

    AGENCY:

    Office of Acquisition and Project Management, Department of Energy.

    ACTION:

    Notice of proposed rulemaking.

    SUMMARY:

    The Department of Energy (DOE) is proposing to amend the Department of Energy Acquisition Regulation (DEAR) to make technical and administrative changes to the DEAR, including changes to conform to the Federal Acquisition Regulation (FAR), remove out-of-date coverage, update references, and correct minor errors and omissions. This proposed rule does not alter substantive rights or obligations under current law.

    DATES:

    Written comments on the proposed rulemaking must be received on or before close of business April 24, 2015.

    ADDRESSES:

    You may submit comments, identified by: Technical and Administrative Changes to Department of Energy Acquisition Regulation and RIN 1991-AC00, by any of the following methods:

    • Federal eRulemaking Portal: http://www.regulations.gov. Follow the instructions for submitting comments.
    • Email to: DEARrulemaking@hq.doe.gov Include DEAR: Small Business and other Socioeconomic Programs and RIN 1991-AC00 in the subject line of the message.
    • Mail to: U.S. Department of Energy, Office of Acquisition and Project Management, MA-611, 1000 Independence Avenue SW., Washington, DC 20585. Comments by email are encouraged.
    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Lawrence Butler, U.S. Department of Energy, Office of Acquisition and Project Management, MA-611, 1000 Independence Avenue SW., Washington, DC 20585-0121. Telephone: (202) 287-1945. Email: lawrence.butler@hq.doe.gov.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    I. Background

    II. Section-by-Section Analysis

    III. Procedural Requirements

    A. Review Under Executive Order 12866 and 13563

    B. Review Under Executive Order 12988

    C. Review Under the Regulatory Flexibility Act

    D. Review Under the Paperwork Reduction Act

    E. Review Under the National Environmental Policy Act

    F. Review Under Executive Order 13132

    G. Review Under the Unfunded Mandates Reform Act of 1995.

    H. Review Under the Treasury and General Government Appropriations Act, 1999

    I. Review Under Executive Order 13211

    J. Review Under the Treasury and General Government Appropriations Act, 2001

    K. Approval by the Office of the Secretary of Energy

    I. Background

    The DEAR has outdated citations and minor errors of a technical nature. The objective of this proposed rule is to update the outdated citations and correct the errors and omissions in the existing DEAR to conform to the FAR. None of these changes are substantive or of a nature to cause any significant expense for DOE or its contractors.

    II. Section-by-Section Analysis

    DOE proposes to amend the DEAR as follows:

    Part 902—DEFINITIONS OF WORDS AND TERMS

    1. Section 902.101, paragraph (2), is revised to change the title of the National Nuclear Security Agency (NNSA) Senior Procurement Executive (SPE).

    Part 909—CONTRACTOR QUALIFICATIONS

    2. Section 909.403, paragraphs (1) and (2), are revised to change the title of the NNSA SPE.

    Part 916—TYPES OF CONTRACTS

    3. Section 916.505, paragraph (b)(6)(i), is revised to change the title of the NNSA SPE.

    Part 917—SPECIAL CONTRACTING METHODS

    4. Section 917.602, paragraph (a), is revised to remove language that is no longer needed in the DEAR.

    Part 922—APPLICATION OF LABOR LAWS TO GOVERNMENT ACQUISITION

    5. Section 922.804 is no longer needed in the DEAR and is removed.

    Part 925—FOREIGN ACQUISITION

    6. Section 925.103, paragraph (a), is revised to correct the CFR reference.

    7. Section 925.1001, paragraph (b), is revised to change the title of the NNSA SPE.

    Part 931—CONTRACT COST PRINCIPLES AND PROCEDURES

    8. Section 931.205-18, paragraph (c)(2), is deleted in its entirety and replaced with a new paragraph (c).Start Printed Page 15738

    Part 936—CONSTRUCTION AND ARCHITECT-ENGINEER CONTRACTS

    9. Section 936.202-70 is no longer needed in the DEAR and is removed.

    Part 942—CONTRACT ADMINISTRATION AND AUDIT SERVICES

    10. Section 942.705-3 is revised to update the circular number and remove the paragraph numbering.

    Part 952—SOLICITATION PROVISIONS AND CONTRACT CLAUSES

    11. Section 952.204-2, paragraph (j), is revised to inform contractors of the format for submitting Foreign Ownership, Control or Influence (FOCI) information. Paragraph (h)(2)(vi), is revised to remove Contractor requirement for submitting in writing information to the head of the cognizant local DOE Security Office concerning each uncleared applicant or uncleared employee who is selected for a position requiring an access authorization.

    12. Section 952.204-73, paragraph (a), is revised to inform contractors of the format for submitting FOCI information.

    13. Section 952.236-72 is no longer needed in the DEAR and is removed.

    14. Section 952.250-70, paragraph (d)(1), is revised to raise the threshold as required by the Energy Policy Act of 2005.

    Part 970—DOE MANAGEMENT AND OPERATING CONTRACTS

    15. Section 970.5215-3 is revised to update the Order number.

    16. Section 970.5223-1 is revised to correct the prescription.

    17. Section 970.5244-1, paragraph (f) is revised to reflect threshold increase in 48 CFR 28.102-2. Paragraph (g) is revised to reflect the threshold increase in DOE's class deviation for DEAR 970.5244-1.

    18. Section 970.5245-1, Alternate I, paragraph (j)(3), is revised to update the Order number and to add language that clarifies the sentence.

    III. Procedural Requirements

    A. Review Under Executive Order 12866 and 13563

    This regulatory action has been determined not to be a “significant regulatory action” under Executive Order 12866, “Regulatory Planning and Review,” 58 FR 51735 (October 4, 1993). Accordingly, this proposed rule is not subject to review under that Executive Order by the Office of Information and Regulatory Affairs (OIRA) of the Office of Management and Budget (OMB).

    DOE has also reviewed this regulation pursuant to Executive Order 13563, issued on January 18, 2011 (76 FR 3281 (Jan. 21, 2011)). Executive Order 13563 is supplemental to and explicitly reaffirms the principles, structures, and definitions governing regulatory review established in Executive Order 12866. To the extent permitted by law, agencies are required by Executive Order 13563 to: (1) Propose or adopt a regulation only upon a reasoned determination that its benefits justify its costs (recognizing that some benefits and costs are difficult to quantify); (2) tailor regulations to impose the least burden on society, consistent with obtaining regulatory objectives, taking into account, among other things, and to the extent practicable, the costs of cumulative regulations; (3) select, in choosing among alternative regulatory approaches, those approaches that maximize net benefits (including potential economic, environmental, public health and safety, and other advantages; distributive impacts; and equity); (4) to the extent feasible, specify performance objectives, rather than specifying the behavior or manner of compliance that regulated entities must adopt; and (5) identify and assess available alternatives to direct regulation, including providing economic incentives to encourage the desired behavior, such as user fees or marketable permits, or providing information upon which choices can be made by the public.

    DOE emphasizes as well that Executive Order 13563 requires agencies to use the best available techniques to quantify anticipated present and future benefits and costs as accurately as possible. In its guidance, the Office of Information and Regulatory Affairs has emphasized that such techniques may include identifying changing future compliance costs that might result from technological innovation or anticipated behavioral changes. DOE believes that this final rule is consistent with these principles, including the requirement that, to the extent permitted by law, agencies adopt a regulation only upon a reasoned determination that its benefits justify its costs and, in choosing among alternative regulatory approaches, those approaches maximize net benefits.

    B. Review Under Executive Order 12988

    With respect to the review of existing regulations and the promulgation of new regulations, section 3(a) of Executive Order 12988, “Civil Justice Reform,” 61 FR 4729 (February 7, 1996), imposes on Executive agencies the general duty to adhere to the following requirements: (1) Eliminate drafting errors and ambiguity; (2) write regulations to minimize litigation; and (3) provide a clear legal standard for affected conduct rather than a general standard and promote simplification and burden reduction.

    With regard to the review required by section 3(a), section 3(b) of Executive Order 12988 specifically requires that Executive agencies make every reasonable effort to ensure that the regulation: (1) Clearly specifies the preemptive effect, if any; (2) clearly specifies any effect on existing Federal law or regulation; (3) provides a clear legal standard for affected conduct while promoting simplification and burden reduction; (4) specifies the retroactive effect, if any; (5) adequately defines key terms; and (6) addresses other important issues affecting clarity and general draftsmanship under any guidelines issued by the United States Attorney General. Section 3(c) of Executive Order 12988 requires Executive agencies to review regulations in light of applicable standards in section 3(a) and section 3(b) to determine whether they are met or if it is unreasonable to meet one or more of them. DOE has completed the required review and determined that, to the extent permitted by law, this proposed rule meets the relevant standards of Executive Order 12988.

    C. Review Under the Regulatory Flexibility Act

    The Regulatory Flexibility Act (5 U.S.C. 601 et seq.) requires preparation of an initial regulatory flexibility analysis for any rule that by law must be proposed for public comment, unless the agency certifies that the rule, if promulgated, will not have a significant economic impact on a substantial number of small entities. As required by Executive Order 13272, “Proper Consideration of Small Entities in Agency Rulemaking,” 67 FR 53461 (August 16, 2002), DOE published procedures and policies on February 19, 2003, to ensure that the potential impacts of its rules on small entities are properly considered during the rulemaking process (68 FR 7990). DOE has made its procedures and policies available on the Office of General Counsel's Web site at http://www.energy.gov/​gc/​office-general-counsel.

    This notice of proposed rulemaking is to amend the DEAR to make technical and administrative changes as described in the summary. This rule would not have a significant economic impact on small entities because it imposes no significant burdens. No substantive rights or obligations are altered by the proposed amendment. Consequently, this proposed rule is exempt from the Start Printed Page 15739requirements of the Regulatory Flexibility Act.

    D. Review Under the Paperwork Reduction Act

    This proposed rule does not impose a collection of information requirement subject to the Paperwork Reduction Act, 44 U.S.C. 3501 et seq. Existing burdens associated with the collection of certain contractor data under the DEAR have been cleared under OMB control number 1910-4100, with an expiration date of October 31, 2014.

    E. Review Under the National Environmental Policy Act

    DOE has concluded that promulgation of this proposed rule falls into a class of actions which would not individually or cumulatively have significant impact on the human environment, as determined by DOE's regulations (10 CFR part 1021, subpart D) implementing the National Environmental Policy Act (NEPA) of 1969 (42 U.S.C. 4321 et seq.). Specifically, this proposed rule is categorically excluded from NEPA review because the amendments to the DEAR are strictly procedural (categorical exclusion A6). Therefore, this proposed rule does not require an environmental impact statement or environmental assessment pursuant to NEPA.

    F. Review Under Executive Order 13132

    Executive Order 13132, 64 FR 43255 (August 4, 1999), imposes certain requirements on agencies formulating and implementing policies or regulations that preempt State law or that have federalism implications. Agencies are required to examine the constitutional and statutory authority supporting any action that would limit the policymaking discretion of the States and carefully assess the necessity for such actions. The Executive Order requires agencies to have an accountability process to ensure meaningful and timely input by state and local officials in the development of regulatory policies that have federalism implications.

    On March 14, 2000, DOE published a statement of policy describing the intergovernmental consultation process it will follow in the development of such regulations (65 FR 13735). DOE has examined the proposed rule and has determined that it does not preempt State law and does not have a substantial direct effect on the States, on the relationship between the national government and the States, or on the distribution of power and responsibilities among the various levels of government. No further action is required by Executive Order 13132.

    G. Review Under the Unfunded Mandates Reform Act of 1995

    The Unfunded Mandates Reform Act of 1995 (Pub. L. 104-4) generally requires a Federal agency to perform a written assessment of costs and benefits of any rule imposing a Federal mandate with costs to State, local or tribal governments, or to the private sector, of $100 million or more. This rulemaking does not impose a Federal mandate on State, local or tribal governments or on the private sector.

    H. Review Under the Treasury and General Government Appropriations Act, 1999

    Section 654 of the Treasury and General Government Appropriations Act, 1999 (Pub. L. 105-277), requires Federal agencies to issue a Family Policymaking Assessment for any rulemaking or policy that may affect family well-being. This rulemaking will have no impact on the autonomy or integrity of the family as an institution. Accordingly, DOE has concluded that it is not necessary to prepare a Family Policymaking Assessment.

    I. Review Under Executive Order 13211

    Executive Order 13211, Actions Concerning Regulations That Significantly Affect Energy Supply, Distribution, or Use, 66 FR 28355 (May 22, 2001), requires Federal agencies to prepare and submit to Office of Information and Regulatory Affairs (OIRA), of the Office of Management and Budget (OMB), a Statement of Energy Effects for any significant energy action. A “significant energy action” is defined as any action by an agency that promulgates or is expected to lead to promulgation of a final rule, and that: (1) Is a significant regulatory action under Executive Order 12866, or any successor order; (2) is likely to have a significant adverse effect on the supply, distribution, or use of energy; or (3) is designated by the Administrator of OIRA as a significant energy action. For any significant energy action, the agency must give a detailed statement of any adverse effects on energy supply, distribution, or use should the proposal be implemented, and of reasonable alternatives to the action and their expected benefits on energy supply, distribution, and use. This proposed rule is not a significant energy action. Accordingly, DOE has not prepared a Statement of Energy Effects.

    J. Review Under the Treasury and General Government Appropriations Act, 2001

    The Treasury and General Government Appropriations Act, 2001 (44 U.S.C. 3516, note) provides for agencies to review most disseminations of information to the public under guidelines established by each agency pursuant to general guidelines issued by OMB. OMB's guidelines were published at 67 FR 8452 (February 22, 2002), and DOE's guidelines were published at 67 FR 62446 (October 7, 2002). DOE has reviewed this proposed rule under the OMB and DOE guidelines and has concluded that it is consistent with applicable policies in those guidelines.

    K. Approval by the Office of the Secretary of Energy

    Issuance of this proposed rule has been approved by the Office of the Secretary of Energy.

    Start List of Subjects

    List of Subjects in 48 CFR Parts 902, 909, 916, 917, 922, 925, 931, 936, 942, 952 and 970

    • Government procurement
    End List of Subjects Start Signature

    Issued in Washington, DC on March 16, 2015.

    Patrick M. Ferraro,

    Deputy Director, Office of Acquisition and Project Management, Department of Energy.

    Joseph Waddell,

    Deputy Associate Administrator, Acquisition and Project Management, National Nuclear Security Administration.

    End Signature

    For the reasons set out in the preamble, the Department of Energy proposes to amend Chapter 9 of Title 48 of the Code of Federal Regulations as set forth below.

    Title 48—Federal Acquisition Regulations System

    Start Amendment Part

    1. The authority citation for parts 902, 903, 916, 917, 922, 925, 931, 936 and 942 continues to read as follows:

    End Amendment Part Start Authority

    Authority: 42 U.S.C. 7101 et seq. and 50 U.S.C. 2401 et seq.

    End Authority Start Part

    PART 902—DEFINITIONS OF WORDS AND TERMS

    [Amended]
    End Part Start Amendment Part

    2. Section 902.101 is amended in the definition of “Senior Procurement Executive ”, by removing “Director, Office of Acquisition and Supply Management” and adding in its place “Deputy Associate Administrator for Acquisition and Project Management”.

    End Amendment Part Start Part Start Printed Page 15740

    PART 909—CONTRACTOR QUALIFICATIONS

    [Amended]
    End Part Start Amendment Part

    3. Section 909.403 is amended in paragraphs (1) and (2), by removing “Director, Office of Acquisition and Supply Management” and adding in its place “Deputy Associate Administrator for Acquisition and Project Management”.

    End Amendment Part Start Part

    PART 916—TYPES OF CONTRACTS

    [Amended]
    End Part Start Amendment Part

    4. Section 916.505 is amended in paragraph (b)(6)(i), by removing “Director, Office of Acquisition and Supply Management,” and adding in its place “Deputy Associate Administrator for Acquisition and Project Management,”.

    End Amendment Part Start Part

    PART 917—SPECIAL CONTRACTING METHODS

    [Amended]
    End Part Start Amendment Part

    5. Section 917.602 is amended in paragraph (a), by removing “, Deputy Secretary or Under Secretary”.

    End Amendment Part Start Part

    PART 922—APPLICATION OF LABOR LAWS TO GOVERNMENT ACQUISITION

    [Removed and Reserved]
    End Part Start Amendment Part

    6. Section 922.804 is removed and reserved.

    End Amendment Part Start Part

    PART 925—FOREIGN ACQUISITION

    End Part Start Amendment Part

    7. Section 925.103 is amended by removing paragraph (a), and revising paragraph (b)(2)(ii) to read as follows:

    End Amendment Part
    Exceptions.

    (b) Nonavailabilty.

    (2)(i) Individual determinations. Contracting officers may make the determination required by 48 CFR 25.103(b)(2)(i), provided such determination is factually supported in writing. If the contract is estimated to exceed $1 million, the Head of the Contracting Activity must approve the determination.

    (ii) Proposals to add an article to the list of nonavailable articles at 48 CFR 25.104, with appropriate justifications, must be submitted for approval by the Senior Procurement Executive and submission to the appropriate council.

    [Amended]
    Start Amendment Part

    8. Section 925.1001 is amended in paragraph (b), by removing “Director, Office of Acquisition and Supply Management” and adding in its place “Deputy Associate Administrator for Acquisition and Project Management”.

    End Amendment Part Start Part

    PART 931—CONTRACT COST PRINCIPLES AND PROCEDURES

    End Part Start Amendment Part

    9. Section 931.205-18 is revised to read as follows:

    End Amendment Part
    Independent research and development (IR&D) and bid and proposal (B&P) costs.

    (c) In addition to all the other FAR requirements for allowability of IR&D costs, costs for IR&D are allowable under DOE contracts to the extent: they are not otherwise unallowable; and they have potential benefit or relationship to the DOE program. The term “DOE program” encompasses the DOE total mission and its objectives. In addition to all the other FAR requirements for allowability of B&P costs, costs for B&P are allowable under DOE contracts to the extent they are not otherwise unallowable.

    Start Part

    PART 936—CONSTRUCTION AND ARCHITECT-ENGINEER CONTRACTS

    [Removed and Reserved]
    End Part Start Amendment Part

    10. Section 936.202-70 is removed and reserved.

    End Amendment Part Start Part

    PART 942—CONTRACT ADMINISTRATION AND AUDIT SERVICES

    [Amended]
    End Part Start Amendment Part

    11. Section 942.705-3 is amended by:

    End Amendment Part Start Amendment Part

    a. Removing the paragraph numbering “(a)(2)”; and

    End Amendment Part Start Amendment Part

    b. Removing “A-88” and adding in its place “A-21”.

    End Amendment Part Start Part

    PART 952—SOLICITATION PROVISIONS AND CONTRACT CLAUSES

    End Part Start Amendment Part

    12. The authority citation for part 952 continues to read as follows:

    End Amendment Part Start Authority

    Authority: 42 U.S.C. 2201; 2282a; 2282b; 2282c; 42 U.S.C. 7101 et seq.; 50 U.S.C. 2401 et seq.

    End Authority Start Amendment Part

    13. Section 952.204-2 is amended by:

    End Amendment Part Start Amendment Part

    a. Revising the section heading;

    End Amendment Part Start Amendment Part

    b. Revising the clause heading and clause date; and

    End Amendment Part Start Amendment Part

    c. Revising introductory paragraph (h)(2)(vi) and paragraph (j)(1).

    End Amendment Part

    The revisions read as follows:

    Security requirements.
    * * * * *

    Security Requirements ([(XXX 20XX)])

    * * * * *

    (h) * * *

    (2) * * *

    (vi) The Contractor must maintain a record of information concerning each uncleared applicant or uncleared employee who is selected for a position requiring an access authorization. Upon request only, the following information will be furnished to the head of the cognizant local DOE Security Office:

    * * * * *

    (j) Foreign ownership, control, or influence. (1) The Contractor shall immediately provide the cognizant security office written notice of any change in the extent and nature of foreign ownership, control or influence over the Contractor which would affect any answer to the questions presented in the Standard Form (SF) 328, Certificate Pertaining to Foreign Interests, executed prior to award of this contract. The Contractor will submit the Foreign Ownership, Control or Influence (FOCI) information in the format directed by DOE. When completed the Contractor must print and sign one copy of the SF 328 and submit it to the Contracting Officer. In addition, any notice of changes in ownership or control which are required to be reported to the Securities and Exchange Commission, the Federal Trade Commission, or the Department of Justice, shall also be furnished concurrently to the Contracting Officer.

    * * * * *
    Start Amendment Part

    14. Section 952.204-73 is amended by:

    End Amendment Part Start Amendment Part

    a. Revising the date of the clause; and

    End Amendment Part Start Amendment Part

    b. Revising paragraph (a)(1).

    End Amendment Part

    The revisions read as follows:

    Facility clearance.
    * * * * *

    Facility Clearance ([(XXX 20XX)])

    * * * * *

    (a) Use of Certificate Pertaining to Foreign Interests, Standard Form 328. (1) The contract work anticipated by this solicitation will require access to classified information or special nuclear material. Such access will require a Facility Clearance for the Contractor's organization and access authorizations (security clearances) for Contractor personnel working with the classified information or special nuclear material. To obtain a Facility Clearance the Contractor must submit the Standard Form 328, Certificate Pertaining to Foreign Interests, and all required supporting documents to form a complete Foreign Ownership, Control or Influence (FOCI) Package. The Contractor will submit the Foreign Ownership, Control or Influence (FOCI) information in the format directed by DOE. When completed the Contractor must print and sign one copy of the SF 328 and submit it to the Contracting Officer.

    * * * * *
    Start Printed Page 15741
    [Removed and Reserved]
    Start Amendment Part

    15. Section 952.236-72 is removed and reserved.

    End Amendment Part
    [Amended]
    Start Amendment Part

    16. Section 952.250-70 is amended by:

    End Amendment Part Start Amendment Part

    a. Revising the date of the clause; and

    End Amendment Part Start Amendment Part

    b. Removing in paragraph (d)(1), “$100 million” and adding in its place “$500 million”.

    End Amendment Part

    The revision reads as follows:

    Nuclear hazards indemnity agreement.
    * * * * *

    Nuclear Hazards Indemnity Agreement ([(XXX 20XX)])

    * * * * *
    Start Part

    PART 970—DOE MANAGEMENT AND OPERATING CONTRACTS

    End Part Start Amendment Part

    17. The authority citation for part 970 continues to read as follows:

    End Amendment Part Start Authority

    Authority: 42 U.S.C. 2201; 2282a; 2282b; 2282c; 42 U.S.C. 7101 et seq.; 50 U.S.C. 2401 et seq.

    End Authority
    [Amended]
    Start Amendment Part

    18. Section 970.5215-3, paragraphs (c)(1)(i) and (c)(2)(i) are amended by removing “DOE Order 225.1A” and adding in its place “DOE Order 225.1B, or successor version”.

    End Amendment Part
    [Amended]
    Start Amendment Part

    19. Section 970.5223-1 is amended by removing “970.2303-3(b)” in the clause introductory paragraph and adding in its place, “970.2303-3(a)”.

    End Amendment Part Start Amendment Part

    20. Section 970.5244-1 is amended by:

    End Amendment Part Start Amendment Part

    a. Revising the clause date;

    End Amendment Part Start Amendment Part

    b. Removing in paragraphs (f)(1) and (f)(2) “$100,000” and adding in its place “$150,000”; and

    End Amendment Part Start Amendment Part

    c. Removing in paragraph (g) “$100,000” in both occurrences and adding in its place “$500,000”.

    End Amendment Part

    The revision read as follows:

    Contractor purchasing system.
    * * * * *

    Contractor Purchasing System ([(XXX 20XX)])

    * * * * *
    Start Amendment Part

    21. Section 970.5245-1 is amended by:

    End Amendment Part Start Amendment Part

    a. Revising the clause date;

    End Amendment Part Start Amendment Part

    b. Revising Alternate I heading and date; and

    End Amendment Part Start Amendment Part

    c. Removing in Alternate I paragraph (j)(3),

    End Amendment Part Start Amendment Part

    a. “Major System Acquisition or Major Project” and adding in its place “Major System Project”, and

    End Amendment Part Start Amendment Part

    b. “DOE Order 4700.1” and adding in its place “DOE Order 413.3B, or successor version”.

    End Amendment Part

    The revisions read as follows:

    Property.
    * * * * *

    Property ([(XXX 20XX)])

    * * * * *

    Alternate I ([(XXX 20XX)]).

    * * * * *
    End Supplemental Information

    [FR Doc. 2015-06564 Filed 3-24-15; 8:45 am]

    BILLING CODE 6450-01-P

Document Information

Published:
03/25/2015
Department:
Energy Department
Entry Type:
Proposed Rule
Action:
Notice of proposed rulemaking.
Document Number:
2015-06564
Dates:
Written comments on the proposed rulemaking must be received on or before close of business April 24, 2015.
Pages:
15737-15741 (5 pages)
RINs:
1991-AC00: DEAR--Miscellaneous Amendments
RIN Links:
https://www.federalregister.gov/regulations/1991-AC00/dear-miscellaneous-amendments
Topics:
Government procurement
PDF File:
2015-06564.pdf
Supporting Documents:
» Request for Information: Collection, Transportation, Sorting, Processing and Second Life Applications for End-of-Life Lithium Ion Batteries
» Request for Information: Grid Resilience and Innovation Partnerships Program
» Agency Information Collection Activities; Proposals, Submissions, and Approvals
» Worker Safety and Health Program
» Agency Information Collection Activities; Proposals, Submissions, and Approvals
» Application: NRG Power Marketing, LLC
» Application: Command Power Corp.
» Agency Information Collection Activities; Proposals, Submissions, and Approvals: Weatherization Assistance Program
» Agency Information Collection Activities; Proposals, Submissions, and Approvals
CFR: (18)
48 CFR 902.101
48 CFR 909.403
48 CFR 916.505
48 CFR 917.602
48 CFR 922.804
More ...