03-16041. Extensions of Payments of Principal and Interest  

  • Start Preamble

    AGENCY:

    Rural Utilities Service, USDA.

    ACTION:

    Final rule.

    SUMMARY:

    The Rural Utilities Service (RUS) is amending its regulation on extensions of payments of principal and interest, to include a maximum interest rate a RUS Borrower can charge on deferments for programs relating to consumer loans. The maximum interest rate will not be more than 300 basis points above the average interest rate on the note(s) being deferred. This limit would allow the Borrower to offset all or part of the administrative costs involved. In addition, this regulation will set forth the procedure for RUS Borrowers to request a section 12(a) extension for distributed generation projects. These changes are intended to clarify the procedures Borrowers are to follow when requesting extensions of payments of principal and interest.

    DATES:

    This rule will become effective on July 28, 2003.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Gail P. Salgado, Management Analyst, Rural Utilities Service, Electric Program, Room 4024, South Building, Stop 1560, 1400 Independence Avenue, SW., Washington, DC 20250-1560. Telephone (202) 205-3660.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    Executive Order 12866

    This rule has been determined to be not significant for the purposes of Executive Order 12866 and, therefore, has not been reviewed by the Office of Management and Budget (OMB).

    Executive Order 12988

    This rule has been reviewed under Executive Order 12988, Civil Justice Reform. RUS has determined that this rule meets the applicable standards provided in section 3 of the Executive Order. In addition, all State and local laws and regulations that are in conflict with this rule will be preempted; no retroactive effect will be given to this rule; and, in accordance with section 212(e) of the Department of Agriculture Reorganization Act of 1994 (7 U.S.C. 6912(e)) administrative appeals procedures, if any, must be exhausted before an action against the Department or its agencies may be initiated.

    Regulatory Flexibility Act Certification

    It has been determined that the Regulatory Flexibility Act is not applicable to this rule since the Rural Utilities Service is not required by 5 U.S.C. 551 et seq. or any other provision of law to publish a notice of proposed rulemaking with respect to the matter of this rule.

    Information Collection and Recordkeeping Requirements

    The reporting and recordkeeping requirements contained in this rule have been approved by the Office of Management and Budget (OMB) pursuant to the Paperwork Reduction Act of 1995 (44 U.S.C. chapter 35) under OMB control number 0572-0123.

    Unfunded Mandates

    This rule contains no Federal mandates (under the regulatory provisions of title II of the Unfunded Mandates Reform Act) for State, local, and tribal governments or the private sector. Thus, this rule is not subject to the requirements of sections 202 and 205 of the Unfunded Mandates Reform Act.

    National Environmental Policy Act Certification

    The Administrator of RUS has determined that this rule will not significantly affect the quality of the human environment as defined by the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.). Therefore, this action does not require an environmental impact statement or assessment.

    Catalog of Federal Domestic Assistance

    The program described by this rule is listed in the Catalog of Federal Domestic Assistance programs under number 10.850, Rural Electrification Loans and Loan Guarantees. This catalog is available on a subscription basis from the Superintendent of Documents, the United States Government Printing Office, Washington, DC 20402-9325, telephone number (202) 512-1800.

    Executive Order 12372

    This rule is excluded from the scope of Executive Order 12372, Intergovernmental Consultation, which may require consultation with State and local officials. See the final rule related notice entitled, “Department Programs and Activities Excluded from Executive Order 12372” (50 FR 47034) advising that RUS loans and loan guarantees are not covered by Executive Order 12372.

    Background

    On October 8, 2002, at 67 FR 62652, the Rural Utilities Service (RUS) published a proposed rule, 7 CFR parts 1710 and 1721, “Extensions of Payments of Principal and Interest,” which proposed to amend its regulation on extensions of payment of principal and interest to include a maximum interest rate a RUS Borrower can charge on deferments for programs relating to consumer loans. The maximum interest rate will not be more than 300 basis points above the average interest rate on the note(s) being deferred. This limit would allow the Borrower to offset all or part of the administrative costs involved. In addition, the proposed rule set forth the procedure for RUS Borrowers to request a section 12(a) extension for distributed generation projects. These changes were intended to clarify the procedures Borrowers are to follow when requesting extensions of payments of principal and interest.

    Written comments on the proposed rule were received and they are summarized as follows:Start Printed Page 37953

    RUS received comments dated December 4, 2002, from the National Rural Electric Cooperative Association (NRECA) and Central Electric Power Cooperative (CEPC), December 6, 2002, from Sandia National Laboratories (Sandia), and December 9, 2002, from Denetsosie Law Office on behalf of the Navajo Tribal Utility Authority (NTUA).

    NRECA recommended that RUS amend §§ 1721.101(b) and 1721.106(a) to clarify the language and ensure that it is consistent by removing the reference to principal in the first sentence of these two sections. RUS should also remove the reference to “level payment” in § 1721.101(b). These changes would make the language consistent and would help to eliminate questions regarding repayment of deferred payments. RUS agrees with these comments and has made the change to the final rule wording under §§ 1721.101(b) and 1721.106(a).

    NRECA, Sandia, and NTUA recommend revising the definition of “Off-grid renewable energy system” and NRECA and CEPC recommend revising the definition of “Renewable energy systems,” both to be more detailed. RUS is in agreement with these recommendations and has made the changes to the final rule wording under § 1710.2.

    In addition, CEPC recommended that RUS give examples of the types of fuel that could qualify as renewable and stated it would also be beneficial to define the term “Green Power.” RUS determined that the definition is clearly inclusive of all types of biomass including the examples recommended by CEPC, so no change was made. CEPC also recommended that RUS define Green Power so those organizations that offer Green Power as part of an energy portfolio could do so with certainty regarding acceptable green fuel types to that make a part of their energy mix. RUS did not define the term “Green Power” in its definitions. The definition of Green Power would require a new rulemaking. Renewable energy is considered a type of distributed generation. Additional eligibility purposes for renewable energy are included in 7 CFR 1721.104(c).

    There was a typographical error in § 1710.2, On-grid renewable energy system, definition. The word “consumer's” in the second sentence has been corrected to “customer's”.

    Start List of Subjects

    List of Subjects

    7 CFR Part 1710

    • Electric power
    • Electric utilities
    • Loan programs—energy
    • Reporting and recordkeeping requirements
    • Rural areas

    7 CFR Part 1721

    • Electric power
    • Loan programs—energy
    • Rural areas
    End List of Subjects Start Amendment Part

    For the reasons set forth in the preamble, RUS amends 7 CFR chapter XVII as follows:

    End Amendment Part Start Part

    PART 1710—GENERAL AND PRE-LOAN POLICIES AND PROCEDURES COMMON TO ELECTRIC LOANS AND GUARANTEES

    End Part Start Amendment Part

    1. The authority citation for part 1710 continues to read:

    End Amendment Part Start Authority

    Authority: 7 U.S.C. 901 et seq.; 1921 et seq., and 6941 et seq.

    End Authority

    Subpart A—General

    Start Amendment Part

    2. Amend § 1710.2(a) by adding a new definition of “Distributed generation” in alphabetical order and by revising the definitions of “Off-grid renewable energy system,” “On-grid renewable energy system,” and “Renewable energy system” as follows:

    End Amendment Part
    Definitions and rules of construction.
    * * * * *

    Distributed generation is the generation of electricity by a sufficiently small electric generating system as to allow interconnection of the electric generating system near the point of service at distribution voltages including points on the customer side of the meter. A distributed generating system may be operated in parallel or independent of the electric power system. A distributed generating system may be fueled by any source, including but not limited to renewable energy sources. A distributed generation project may include one or more distributed generation systems.

    * * * * *

    Off-grid renewable energy system is a renewable energy system not interconnected to an area electric power system (EPS). An off-grid renewable energy system in areas without access to an area EPS may include energy consuming devices and electric wiring to provide for more effective or more efficient use of the electricity produced by the system.

    On-grid renewable energy system is a renewable energy system interconnected to an area electric power system (EPS) through a normally open or normally closed device. It can be interconnected to the EPS on either side of a customer's meter.

    * * * * *

    Renewable energy system is an energy conversion system fueled from any of the following energy sources: Solar, wind, hydropower, biomass, or geothermal. Any of these energy sources may be converted to heat or electricity, provided heat is a by-product of electricity generation. Non-renewable energy sources may be used by a renewable energy system for incidental and necessary means such as, but not limited to, system start up, flame stabilization, continuity of system processes, or reduction of the moisture content of renewable fuels. Energy from bio-mass may be converted from any organic matter available on a renewable basis, including dedicated energy crops and trees, agricultural food and feed crops, agricultural crop wastes and residues, wood wastes and residues, aquatic plants, animal wastes, municipal wastes, and other waste materials.

    * * * * *
    Start Part

    PART 1721—POST LOAN POLICIES AND PROCEDURES FOR INSURED ELECTRIC LOANS

    End Part Start Amendment Part

    3. The authority citation for part 1721 continues to read:

    End Amendment Part Start Authority

    Authority: 7 U.S.C. 901 et seq.; 1921 et seq., and 6941 et seq.

    End Authority

    Subpart B—Extensions of Payments of Principal and Interest

    Start Amendment Part

    4. Amend § 1721.101 by revising paragraph (b) to read as follows:

    End Amendment Part
    General.
    * * * * *

    (b) The total amount of interest that has been deferred, including interest on deferred principal, will be added to the principal balance, and the total amount of principal and interest that has been deferred will be reamortized over the remaining life of the applicable note beginning in the first year the deferral period ends.

    * * * * *
    Start Amendment Part

    5. Amend § 1721.103 by adding paragraph (c) to read as follows:

    End Amendment Part
    Policy.
    * * * * *

    (c) The maximum interest rate a RUS Borrower can charge on deferments for programs relating to consumer loans, e.g., energy resource conservation (ERC) program, contribution-in-aid of construction (CIAC), etc., will not be more than 300 basis points above the average interest rate on the note(s) being deferred. For example, if the RUS Borrower's average interest rate on the note(s) being deferred is 5 percent, the Start Printed Page 37954RUS Borrower can charge a maximum interest rate of 8 percent.

    Start Amendment Part

    6. Amend § 1721.104 by:

    End Amendment Part Start Amendment Part

    A. Revising paragraph (c)(1)(ii);

    End Amendment Part Start Amendment Part

    B. Redesignating paragraph (d) as (e); and

    End Amendment Part Start Amendment Part

    C. Adding a new paragraph (d).

    End Amendment Part

    This revision and addition are to read as follows:

    Eligible purposes.
    * * * * *

    (c) * * *

    (1) * * *

    (ii) Electric power system interfaces;

    * * * * *

    (d) Deferments for distributed generation projects.

    (1) A Borrower may request that RUS defer principal payments to enable the Borrower to finance distributed generation projects. Amounts deferred under this program can be used to cover costs to install all or part of a distributed generation system that:

    (i) The Borrower will own and operate, or

    (ii) The consumer owns, provided the system owned by the consumer does not exceed 5KW.

    (2) A distributed generation project may include one or more individual systems.

    * * * * *
    Start Amendment Part

    7. Amend § 1721.105 by redesignating paragraph (d) as (e) and by adding a new paragraph (d) to read as follows:

    End Amendment Part
    Application documents.
    * * * * *

    (d) Deferments for distributed generation projects. A Borrower requesting principal deferments for distributed generation projects must submit the following information and approval is also subject to any applicable terms and conditions of the Borrower's loan contract, mortgage, or indenture:

    (1) A letter from the Borrower's General Manager requesting an extension of principal payments for the purpose of financing distributed generation projects and describing the details of the project, and

    (2) A copy of the board resolution establishing the distributed generation projects program.

    * * * * *
    Start Amendment Part

    8. Amend § 1721.106 by revising paragraph (a) and the heading of paragraph (b) to read as follows:

    End Amendment Part
    Repayment of deferred payments.

    (a) Deferments relating to financial hardship. The total amount of interest that has been deferred, including interest on deferred principal, will be added to the principal balance, and the total amount of principal and interest that has been deferred will be reamortized over the remaining life of the applicable note beginning in the first year the deferral period ends. For example: the amount of interest deferred in years 2003, 2004, 2005, 2006, and 2007, will be added to the principal balance and reamortized over the life of the applicable note for repayment starting in year 2008.

    (b) Deferments relating to the ERC loan program, renewable energy project(s), distributed generation project(s), and the contribution(s)-in-aid of construction. * * *

    * * * * *
    Start Signature

    Dated: May 30, 2003.

    Hilda Gay Legg,

    Administrator, Rural Utilities Service.

    End Signature End Supplemental Information

    [FR Doc. 03-16041 Filed 6-25-03; 8:45 am]

    BILLING CODE 3410-15-P

Document Information

Effective Date:
7/28/2003
Published:
06/26/2003
Department:
Rural Utilities Service
Entry Type:
Rule
Action:
Final rule.
Document Number:
03-16041
Dates:
This rule will become effective on July 28, 2003.
Pages:
37952-37954 (3 pages)
RINs:
0572-AB79: Extensions of Payments of Principal and Interest
RIN Links:
https://www.federalregister.gov/regulations/0572-AB79/extensions-of-payments-of-principal-and-interest
Topics:
Electric power, Electric utilities, Loan programs-energy, Reporting and recordkeeping requirements, Rural areas
PDF File:
03-16041.pdf
CFR: (6)
7 CFR 172.101
7 CFR 1710.2
7 CFR 1721.103
7 CFR 1721.104
7 CFR 1721.105