06-3686. Federal Acquisition Regulation; FAR Case 2004-031, Fast Payment Procedures  

  • Start Preamble

    AGENCIES:

    Department of Defense (DoD), General Services Administration (GSA), and National Aeronautics and Space Administration (NASA).

    ACTION:

    Final rule.

    SUMMARY:

    The Civilian Agency Acquisition Council and the Defense Acquisition Regulations Council (Councils) have agreed on a final rule amending the Federal Acquisition Regulation (FAR) by revising fast payment procedures. The revision permits, but does not require, fast payment when invoices and/or outer shipping containers are not marked “Fast Pay” provided the contract includes the “Fast Payment Procedure” clause. As highlighted in the clause, if the clause is in the contract, the invoices will no longer be rejected, as is the current practice. Instead, they will be paid using either fast payment or normal payment procedures. In addition, the revision deletes the requirement for marking invoices “No Receiving Report Prepared.”

    DATES:

    Effective Date: May 19, 2006.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    For clarification of content, contact Mr. Jeremy Olson, Procurement Analyst, at (202) 501-3221. Please cite FAC 2005-09, FAR case 2004-031. For information pertaining to status or publication schedules, contact the FAR Secretariat at (202) 501-4755.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    A. Background

    DoD, GSA, and NASA published a proposed rule, FAR case 2004-031, at 70 FR 40279 on July 13, 2005, to obtain comments on a proposal to amend the policies and contract clause regarding Fast Pay procedures. No comments were submitted and the rule was converted to a final rule without change from the proposed rule. FAR 52.213-1, Fast Payment Procedure, is revised to permit acceptance and payment under invoices that are not prominently marked “FAST PAY.”

    This change provides the payment office flexibility to make fast payments when invoices and/or outer shipping containers are not marked “FAST PAY.” The change permits, but does not require, fast payment when invoices and/or outer shipping containers are not marked “FAST PAY” provided the contract includes the “Fast Payment Procedure” clause. However, if the payment office decides to not process invoices as “FAST PAY” because the proper markings are not present, the payment date will be the payment date that would have applied had the “Fast Payment Procedure” clause not been in the contract. In this manner, an unmarked invoice will not be rejected. This change does not eliminate the requirement for the contractor to annotate an invoice “FAST PAY;” the contractor remains at risk that fast payment procedures will not be applied unless the invoice is annotated accordingly.

    If a receiving report is not prepared, it is imperative that the invoice includes sufficient information to facilitate follow-up verification that the item was received. The FAR revision does not eliminate that requirement for such information on the invoice. However, the revision does not require the statement “No Receiving Report Prepared” on the invoice.

    This is not a significant regulatory action and, therefore, was not subject to Start Printed Page 20309review under Section 6(b) of Executive Order 12866, Regulatory Planning and Review, dated September 30, 1993. This rule is not a major rule under 5 U.S.C. 804.

    B. Regulatory Flexibility Act

    The Department of Defense, the General Services Administration, and the National Aeronautics and Space Administration certify that this final rule will not have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq., because it will have a beneficial, but small, impact. Under the prior policy and clause, small businesses which failed to follow the fast payment clause instructions to mark the invoice “FAST PAY” had their invoices rejected, which means they would not be paid until they sent a corrected invoice. The clause revisions mean the invoices would not have to be automatically rejected. No comments were received from small entities or other members of the public.

    C. Paperwork Reduction Act

    The Paperwork Reduction Act does not apply because the changes to the FAR do not impose information collection requirements that require the approval of the Office of Management and Budget under 44 U.S.C. 3501, et seq.

    Start List of Subjects

    List of Subjects in 48 CFR Parts 52

    • Government procurement
    End List of Subjects Start Signature

    Dated: April 12, 2006.

    Gerald Zaffos,

    Director,Contract Policy Division.

    End Signature Start Amendment Part

    Therefore, DoD, GSA, and NASA amend 48 CFR part 52 as set forth below:

    End Amendment Part Start Part

    PART 52—SOLICITATION PROVISIONS AND CONTRACT CLAUSES

    End Part Start Amendment Part

    1. The authority citation for 48 CFR part 52 continues to read as follows:

    End Amendment Part Start Authority

    Authority: 40 U.S.C. 121(c); 10 U.S.C. chapter 137; and 42 U.S.C. 2473(c).

    End Authority Start Amendment Part

    2. Amend section 52.213-1 by revising the date of the clause and paragraphs (c)(1)(ii), (c)(3), and (e) to read as follows:

    End Amendment Part
    Fast Payment Procedure.
    * * * * *

    FAST PAYMENT PROCEDURE (APR 2006)

    * * * * *

    (c) * * *

    (1) * * *

    (ii) Display prominently on the invoice “FAST PAY.” Invoices not prominently marked “FAST PAY” via manual or electronic means may be accepted by the payment office for fast payment. If the payment office declines to make fast payment, the Contractor shall be paid in accordance with procedures applicable to invoices to which the Fast Payment clause does not apply.

    * * * * *

    (3) If this contract, order, or blanket purchase agreement requires the preparation of a receiving report, the Contractor shall either—

    (i) Submit the receiving report on the prescribed form with the invoice; or

    (ii) Include the following information on the invoice:

    (A) Shipment number.

    (B) Mode of shipment.

    (C) At line item level—

    (1) National stock number and/or manufacturer's part number;

    (2) Unit of measure;

    (3) Ship-To Point;

    (4) Mark-For Point, if in the contract; and

    (5) FEDSTRIP/MILSTRIP document number, if in the contract.

    * * * * *

    (e) Fast pay container identification. The Contractor shall mark all outer shipping containers “FAST PAY.” When outer shipping containers are not marked “FAST PAY,” the payment office may make fast payment. If the payment office declines to make fast payment, the Contractor shall be paid in accordance with procedures applicable to invoices to which the Fast Payment clause does not apply.

    (End of clause)

    End Supplemental Information

    [FR Doc. 06-3686 Filed 4-18-06; 8:45 am]

    BILLING CODE 6820-EP-S

Document Information

Published:
04/19/2006
Department:
National Aeronautics and Space Administration
Entry Type:
Rule
Action:
Final rule.
Document Number:
06-3686
Pages:
20308-20309 (2 pages)
Docket Numbers:
FAC 2005-09, FAR Case 2004-031, Item IX, Docket FAR-2006-0020
RINs:
9000-AK24
PDF File:
06-3686.pdf
CFR: (1)
48 CFR 52.213-1