2021-15511. Removing Profile Drawing Requirement for Qualifying Conduit Notices of Intent and Revising Filing Requirements for Major Hydroelectric Projects 10 MW or Less  

  • Start Preamble

    AGENCY:

    Federal Energy Regulatory Commission, Department of Energy.

    ACTION:

    Final rule.

    SUMMARY:

    In this final rule, the Federal Energy Regulatory Commission (Commission) is amending its regulations governing the filing requirements for qualifying conduits and certain major hydroelectric power projects. Specifically, the Commission is removing the requirement that a notice of intent to construct a qualifying conduit include a profile drawing showing the source of the hydroelectric potential in instances where a dam would be constructed in association with the facility and extending the licensing requirements that currently apply to major projects up to 5 megawatts (MW) to major projects 10 MW or less, consistent with the amended definition of a small hydroelectric power project in the Hydropower Regulatory Efficiency Act of 2013.

    DATES:

    This rule is effective October 4, 2021.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Heather Campbell (Technical Information), Office of Energy Projects, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, (202) 502-6182, heather.e.campbell@ferc.gov.

    Kelly Houff (Technical Information), Office of Energy Projects, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, (202) 502-6393, kelly.houff@ferc.gov.

    John Matkowski (Technical Information), Office of Energy Projects, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, (202) 502-8576, john.matkowski@ferc.gov.

    Rachael Warden (Legal Information), Office of the General Counsel, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, (202) 502-8717, rachael.warden@ferc.gov.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    I. Background

    1. By this final rule, the Federal Energy Regulatory Commission (Commission or FERC) is amending parts 4 and 5 of its regulations governing the filing requirements for qualifying conduits and certain major hydroelectric power projects. The Commission, under Part I of the Federal Power Act (FPA), licenses hydropower projects that are developed by non-Federal entities including individuals, private entities, states, municipalities, electric cooperatives, and others.

    2. The Hydropower Regulatory Efficiency Act of 2013 (2013 HREA) [1] was signed into law on August 9, 2013. As explained below, changes implemented in response to the 2013 HREA form the basis for these revisions to the Commission's regulations.

    II. Notice of Proposed Rulemaking

    3. On February 18, 2021, the Commission issued a notice of proposed rulemaking (NOPR) proposing to: (1) Remove the requirement that a notice of intent to construct a qualifying conduit include a profile drawing showing the source of the hydroelectric potential in instances where a dam would be constructed in association with the facility; and (2) extend the licensing requirements that currently apply to major projects up to 5 megawatts (MW) to major projects 10 MW or less, consistent with the amended definition of a small hydroelectric power project in the 2013 HREA.[2] The Commission did not receive any comments in response to the NOPR. The proposal set forth in the NOPR and the Commission's determination are discussed below.

    III. Discussion

    A. Qualifying Conduits

    4. The NOPR explained that the 2013 HREA amended section 30 of the FPA to create a subset of small conduit facilities that are categorically excluded from the licensing and exemption requirements of the FPA. In 2014, the Commission issued Order No. 800, which became effective February 23, 2015, defining a “qualifying conduit hydropower facility” at § 4.30(b)(26) of its regulations.[3] Subsequently, section 30 of the FPA was amended by the Start Printed Page 42711America's Water Infrastructure Act of 2018.[4]

    5. In accordance with section 30(a)(2)(A),[5] any person, State, or municipality proposing to construct a “qualifying conduit hydropower facility” must file a notice of intent demonstrating the facility meets the following “qualifying criteria”: [6]

    • Be located on and use only the hydroelectric potential of a non-federally owned conduit;
    • have a proposed installed capacity that does not exceed 40 MW; [7] and
    • be proposed for construction and, as of the date of enactment of the 2013 HREA, not be licensed under, or exempted from, the licensing requirements of Part I of the FPA.

    6. Under the 2013 HREA, as amended,[8] the Commission is required to determine whether proposed projects meet the criteria to be considered qualifying conduit hydropower facilities. Qualifying conduit hydropower facilities are not required to be licensed or exempted by the Commission; however, the entity proposing to construct a facility that meets the criteria must file a Notice of Intent to Construct a Qualifying Conduit Hydropower Facility (NOI) with the Commission that demonstrates the facility meets the qualifying criteria discussed above.

    7. The NOI must contain: An introductory statement; a statement that the proposed project will use the hydroelectric potential of a non-federally owned conduit; a statement that the proposed facility has not been licensed or exempted on or before August 9, 2013; a description of the facility proposal; project drawings; the preliminary permit project number of the proposed facility, if applicable; and verification in a sworn notarized statement or an unsworn statement.[9] Specifically with respect to the project drawings, the NOI must include a plan (or overhead view); a location map showing the facilities and their relationship to the nearest town; and if a dam would be constructed in association with the facility, a profile drawing showing that the conduit, and not the dam, creates the hydroelectric potential.[10]

    8. On June 18, 2015, in Soldier Canyon Filter Plant,[11] the Commission stated:

    In determining whether a proposed qualifying conduit hydropower facility meets the requirement of FPA section 30(a) that it use “only the hydroelectric potential of a non-federally owned conduit” and (if it meets the other section 30(a) requirements) is thus excluded from the licensing requirements of the FPA, we see no reason to apply a different, more stringent standard than was established in 1980 for small conduit facility exemptions. We view small conduit facilities and qualifying conduits as simply generating hydroelectricity by using the water within a conduit operated for the distribution of water for agricultural, municipal, or industrial consumption and not primarily for the generation of electricity. Whether, or in what proportion, the conduit's ability to generate hydropower is due to the conduit's gradient or the head from an upstream dam is not relevant.[12]

    This holding indicates that the profile drawings are no longer relevant and should not be required as part of the NOI submittal. Consequently, the Commission proposed to amend its regulations to remove this requirement.

    B. Major Projects Greater Than 5 MW and up to and Including 10 MW

    9. Section 405 of the Public Utility Regulatory Policies Act of 1978 (PURPA) [13] provided that certain hydropower projects that produce 5,000 kilowatts, or 5 MW, or less of power were exempted from the licensing requirements of Part 1 of the FPA.

    10. In 1981, the Commission adopted the 5-MW demarcation for certain major hydroelectric projects required to be licensed under Part 1 of the FPA to parallel PURPA's 5-MW demarcation regarding exemptions.[14] Part 4 of the Commission's regulations includes three relevant licensing subparts: (1) Subpart E—Application for License for Major Unconstructed Project and Major Modified Project (see 18 CFR 4.40); (2) Subpart F—Application for License for Major Project—Existing Dam (see 18 CFR 4.50); and (3) Subpart G—Application for License for Minor Water Power Projects and Major Water Power Projects 5 MW or Less (see 18 CFR 4.60; 4.61).[15] Subparts E and F apply to projects greater than 5 MW, and include additional filing requirements beyond subpart G, which applies to projects less than or equal to 5 MW.

    11. Likewise, part 4 of Commission's regulations include two subparts that rely on the same 5-MW limit to determine minimum filing requirements for an application for license solely for transmission lines that transmit power from a licensed water power projects as well amendments to licensed water power projects: (1) Subpart H—Application for License for Transmission Line Only (see 18 CFR 4.71); and (2) Subpart L—Application for Amendment of License (see 18 CFR 4.201), respectively.

    12. Part 5 of the Commission's regulations rely on the 5-MW limit to determine minimum filing requirements for applications for license for water power projects filed and processed using the integrated licensing process (see 18 CFR 5.18).

    13. The 2013 HREA amended section 405 to increase the limit for exemptions to 10,000 kilowatts, or 10 MW, with the goal of facilitating the speed at which such hydropower projects could be built. Order 800 amended the Commission's regulations to reflect the 10-MW limit.[16]

    14. As a result of these changes, the Commission's limit for license application provisions no longer parallels the limit for exemptions. We stated in the NOPR that we continue to believe that a parallel demarcation is appropriate to “expedite hydropower development by easing the burden of preparing an application for license and by assisting the Commission in more rapid processing of applications.” 17 Start Printed Page 42712Moreover, the 5-MW limit in the Commission's regulations could be burdensome to projects greater than 5 MW and up to and including 10 MW, in terms of the cost and time associated with the additional filing requirements of subparts E and F.

    15. Therefore, the Commission proposed to amend parts 4 and 5 of its regulations to extend the licensing and amendment filing requirements that currently apply to major projects up to 5 MW to major projects 10 MW or less, consistent with the amended definition of a small hydroelectric power project in the 2013 HREA.[18]

    C. Commission Determination

    16. For the reasons discussed above, the Commission adopts the NOPR's proposal to: (1) Remove the requirement that an NOI include a profile drawing showing the source of the hydroelectric potential in instances where a dam would be constructed in association with the facility; and (2) extend the licensing requirements that currently apply to major projects up to 5 MW to major projects 10 MW or less.

    IV. Regulatory Requirements

    A. Information Collection Statement

    17. The Paperwork Reduction Act [19] requires each Federal agency to seek and obtain the Office of Management and Budget's (OMB) approval before undertaking a collection of information directed to 10 or more persons or contained in a rule of general applicability. OMB regulations require approval of certain information collection requirements contained in final rules published in the Federal Register.[20] Upon approval of a collection of information, OMB will assign an OMB control number and an expiration date. Respondents subject to the filing requirements of a rule will not be penalized for failing to respond to the collection of information unless the collection of information displays a valid OMB control number.

    18. Public Reporting Burden: By revising regulations governing the filing requirements for qualifying conduits and for major hydroelectric power projects greater than 5 MW and up to and including 10 MW, this final rule will modify certain reporting and recordkeeping requirements included in FERC-500 (OMB Control No 1902-0058) [21] and FERC-505 (OMB Control No. 1902-0115).[22]

    19. These revisions to the Commission's regulations will align the filing requirements for qualifying conduits with Commission precedent and align the filing requirements for major projects greater than 5 MW and up to and including 10 MW to be consistent with the amended definition of a small hydroelectric power project in the 2013 HREA. Both revisions represent a slight decrease in the reporting requirements and burden information for FERC-500 and FERC-505.

    20. The estimated burden and cost for the requirements affected by this final rule follow.

    Changes Due to the Final Rule in Docket No. RM20-21-000

    Numbers of respondentsNumbers of responses 23 per respondentTotal number of responsesAvg. burden hrs. & cost per response 24Total annual burden hours & total annual cost
    (1)(2)(1) × (2) = (3)(4)(3) × (4) = 5
    FERC-500313320 hours/$26,560 reduction960 hours/$79,680 reduction.
    FERC-50581810 hours/$830 reduction80 hours/$6,640 reduction.
    Total111,040 hours/$86,320 reduction.

    21. Titles: FERC-500 (Application for License/Relicense for Water Projects with More than 5 Megawatt (MW) Capacity) and FERC-505 (Small Hydropower Projects and Conduit Facilities including License/Relicense, Exemption, and Qualifying Conduit Facility Determination).

    22. Action: Revisions to information collections FERC-500 and FERC-505.

    23. OMB Control Nos.: 1902-0058 (FERC-500) and 1902-0115 (FERC-505).

    24. Respondents: Municipalities, businesses, private citizens, and for-profit and not-for-profit institutions.

    25. Frequency of Information: Ongoing.

    26. Necessity of Information: The revised regulations remove the Commission's requirement for notices of intent to construct a qualifying conduit to include a profile drawing, consistent with Commission precedent, and align the Commission's filing requirements for major projects greater than 5 MW and up to and including 10 MW to be consistent with the amended definition of a small hydroelectric power project in the 2013 HREA. The revised regulations affect only the number of entities that would file applications with the Commission for these two project types and reduce information collection requirements.

    27. Internal Review: The Commission has reviewed the revisions and has determined that they are necessary. These requirements conform to the Commission's need for efficient information collection, communication, and management within the energy industry. The Commission has assured Start Printed Page 42713itself, by means of internal review, that there is specific, objective support for the burden estimates associated with the information collection requirements.

    28. Interested persons may obtain information on the reporting requirements by contacting the Federal Energy Regulatory Commission at one of the following methods:

    • USPS at: Federal Energy Regulatory Commission, Ellen Brown, Office of the Executive Director, 888 First Street NE, Washington, DC 20426.
    • Hard copy communication other than USPS: Federal Energy Regulatory Commission, Ellen Brown, Office of the Executive Director, 12225 Wilkins Avenue, Rockville, Maryland 20852.
    • email to: DataClearance@ferc.gov.
    • phone: (202) 502-8663, or by fax: (202) 273-0873.

    29. Please send comments concerning the collection of information and the associated burden estimates to: Office of Information and Regulatory Affairs, Office of Management and Budget [Attention: Federal Energy Regulatory Commission Desk Officer]. Due to security concerns, comments should be sent directly to www.reginfo.gov/​public/​do/​PRAMain. Comments submitted to OMB should be sent within 30 days of publication of this notification in the Federal Register and should refer to FERC-500 (OMB Control No 1902-0058) and FERC-505 (OMB Control No. 1902-0115).

    B. Environmental Analysis

    30. The Commission is required to prepare an Environmental Assessment or an Environmental Impact statement for any action that may have a significant effect on the human environment.[25] Excluded from this requirement are rules that are clarifying, corrective, or procedural, or that do not substantially change the effect of legislation or the regulations being amended.[26] This final rule revises the filing requirements for qualifying conduit projects and the filing requirements for license applications for major hydroelectric projects with an installed capacity of 10 MW or less. Because this final rule is procedural and does not substantially change the effect of the regulations being amended, preparation of an Environmental Assessment or Environmental Impact Statement is not required.

    C. Regulatory Flexibility Act

    31. The Regulatory Flexibility Act of 1980 (RFA) [27] generally requires a description and analysis of final rules that will have significant economic impact on a substantial number of small entities. The RFA mandates consideration of regulatory alternatives that accomplish the stated objectives of a rulemaking and minimize any significant economic impact on a substantial number of small entities.[28] In lieu of preparing a regulatory flexibility analysis, an agency may certify that a final rule will not have a significant economic impact on a substantial number of small entities.[29]

    32. The Small Business Administration's (SBA) Office of Size Standards develops the numerical definition of a small business.[30] The SBA size standard for electric utilities is based on the number of employees, including affiliates.[31] Under SBA's current size standards, a hydroelectric power generator (NAICS code 221111) [32] is small if, including its affiliates, it employs 500 or fewer people.[33] The Commission, however, currently does not require information regarding the number of individuals employed by hydroelectric generators to administer Part 1 of the Federal Power Act and therefore is unable to estimate the number of small entities under the SBA definition. Regardless, the Commission anticipates that this final rule will affect few entities.

    33. As noted earlier, the final rule will only affect entities filing notices of intent to construct a qualifying conduit in instances where a dam would be constructed in association with the facility and entities filing licensing or amendment applications for major hydroelectric projects with an installed capacity of greater than 5 MW and up to and including 10 MW. From 2013 to 2020, the Commission received approximately 140 total notices to construct qualifying conduits and 18 applicable licensing applications. The revisions will eliminate the filing requirement for profile drawings and reduce the filing requirements for major hydroelectric projects with an installed capacity greater than 5 MW and up to and including 10 MW, thus reducing the burden on small hydro developers going forward.

    34. Accordingly, pursuant to section 605(b) of the RFA, the Commission certifies that this final rule would not have a significant economic impact on a substantial number of small entities.

    D. Document Availability

    35. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission's Home Page (http://www.ferc.gov). At this time, the Commission has suspended access to the Commission's Public Reference Room due to the March 13, 2020 proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID-19).

    36. From the Commission's Home Page on the internet, this information is available on eLibrary. The full text of this document is available on eLibrary in PDF and Microsoft Word format for viewing, printing, and/or downloading. To access this document in eLibrary, type the docket number excluding the last three digits of this document in the docket number field.

    37. User assistance is available for eLibrary and the Commission's website during normal business hours from the Commission's Online Support at (202) 502-6652 (toll free at 1-866-208-3676) or email at ferconlinesupport@ferc.gov, or the Public Reference Room at (202) 502-8371, TTY (202) 502-8659. Email the Public Reference Room at public.referenceroom@ferc.gov.

    E. Effective Date and Congressional Notification

    38. These regulations are effective October 4, 2021. The Commission has determined, with the concurrence of the Administrator of the Office of Information and Regulatory Affairs of OMB, that this rule is not a “major rule” as defined in section 351 of the Small Business Regulatory Enforcement Fairness Act of 1996. This rule is being submitted to the Senate, House, Government Accountability Office, and Small Business Administration.

    Start List of Subjects

    List of Subjects in 18 CFR Parts 4 and 5

    • Administrative practice and procedure
    • Electric power
    • Reporting and recordkeeping requirements
    End List of Subjects Start Signature

    By direction of the Commission.

    Start Printed Page 42714

    Issued: July 15, 2021.

    Debbie-Anne A. Reese,

    Deputy Secretary.

    End Signature

    In consideration of the foregoing, the Commission amends parts 4 and 5, chapter I, title 18, Code of Federal Regulations, as follows:

    Start Part

    PART 4—LICENSES, PERMITS, EXEMPTIONS, AND DETERMINATION OF PROJECT COSTS

    End Part Start Amendment Part

    1. The authority citation for part 4 continues to read as follows:

    End Amendment Part Start Authority

    Authority: 16 U.S.C. 791a-825r; 42 U.S.C. 7101-7352.

    End Authority Start Amendment Part

    2. In § 4.32, revise paragraph (a)(5)(ii) to read as follows:

    End Amendment Part
    Acceptance for filing or rejection; information to be made available to the public; requests for additional studies.

    (a) * * *

    (5) * * *

    (ii) License for a minor water power project and a major water power project 10 MW or less: § 4.61;

    * * * * *
    Start Amendment Part

    3. In § 4.40, revise paragraph (a) to read as follows:

    End Amendment Part
    Applicability.

    (a) Applicability. The provisions of this subpart apply to any application for an initial license for a major unconstructed project that would have a total installed capacity of more than 10 megawatts, and any application for an initial or new license for a major modified project with a total installed capacity more than 10 megawatts. An applicant for license for any major unconstructed or major modified water power project that would have a total installed generating capacity of 10 megawatts or less must submit application under subpart G of this part (§§ 4.60 and 4.61).

    * * * * *
    Start Amendment Part

    4. In § 4.50, revise paragraphs (a)(1) and (3) to read as follows:

    End Amendment Part
    Applicability.

    (a) * * *

    (1) Except as provided in paragraph (a)(2) of this section, the provisions of this subpart apply to any application for either an initial license or new license for a major project—existing dam that is proposed to have a total installed capacity of more than 10 megawatts.

    * * * * *

    (3) An applicant for license for any major project—existing dam that would have a total installed capacity of 10 megawatts or less must submit application under subpart G of this part (§§ 4.60 and 4.61).

    * * * * *
    Start Amendment Part

    5. Revise the heading to subpart G to read as follows:

    End Amendment Part

    Subpart G—Application for License for Minor Water Power Projects and Major Water Power Projects 10 Megawatts or Less

    Start Amendment Part

    6. In § 4.60, revise paragraphs (a)(2) and (3) and (b) to read as follows:

    End Amendment Part
    Applicability and notice to agencies.

    (a) * * *

    (2) Any major project—existing dam, as defined in § 4.30(b)(16), that has a total installed capacity of 10 MW or less; or

    (3) Any major unconstructed project or major modified project, as defined in § 4.30(b)(15) and (14) respectively, that has a total installed capacity of 10 MW or less.

    (b) Notice to agencies. The Commission will supply interested Federal, state, and local agencies with notice of any application for license for a water power project 10 MW or less and request comment on the application. Copies of the application will be available for inspection at the Commission's Public Reference Room. The applicant shall also furnish copies of the filed application to any Federal, state, or local agency that so requests.

    * * * * *
    Start Amendment Part

    7. In § 4.61, revise paragraphs (a)(3), (b) introductory text, (d)(1) introductory text, and (d)(2) introductory text to read as follows:

    End Amendment Part
    Contents of application.

    (a) * * *

    (3) Each application for a license for a water power project 10 megawatts or less must include the information requested in the initial statement and lettered exhibits described by paragraphs (b) through (f) of this section, and must be provided in the form specified. The Commission reserves the right to require additional information, or another filing procedure, if data provided indicate such action to be appropriate.

    (b) * * *

    Before the Federal Energy Regulatory Commission

    Application for License for a [Minor Water Power Project, or Major Water Power Project, 10 Megawatts or Less, as Appropriate]

    * * * * *

    (d) * * *

    (1) For major unconstructed and major modified projects 10 MW or less. Any application must contain an Exhibit E conforming with the data and consultation requirements of § 4.41(f), if the application is for license for a water power project which has or is proposed to have a total installed generating capacity greater than 1.5 MW but not greater than 10 MW, and which:

    * * * * *

    (2) For minor projects and major projects at existing dams 10 MW or less. An application for license for either a minor water power project with a total proposed installed generating capacity of 1.5 MW or less or a major project—existing dam with a proposed total installed capacity of 10 MW or less must contain an Exhibit E under this paragraph (d)(2). See § 4.38 for consultation requirements. The Environmental Report must contain the following information:

    * * * * *
    Start Amendment Part

    8. In § 4.71, revise paragraphs (b)(1) and (2) to read as follows:

    End Amendment Part
    Contents of application.
    * * * * *

    (b) * * *

    (1) For any transmission line that, at the time the application is filed, is not constructed and is proposed to be connected to a licensed water power project with an installed generating capacity of more than 10 MW—Exhibits A, B, C, D, E, F, and G under § 4.41;

    (2) For any transmission line that, at the time the application is filed, is not constructed and is proposed to be connected to a licensed water power project with an installed generating capacity of 10 MW or less—Exhibits E, F, and G under § 4.61; and

    * * * * *
    Start Amendment Part

    9. In § 4.201, revise paragraphs (b)(1) and (3) through (5) to read as follows:

    End Amendment Part
    Contents of application.
    * * * * *

    (b) * * *

    (1) For amendment of a license for a water power project that, at the time the application is filed, is not constructed and is proposed to have a total installed generating capacity of more than 10 MW—Exhibits A, B, C, D, E, F, and G under § 4.41;

    * * * * *

    (3) For amendment of a license for a water power project that, at the time the application is filed, is not constructed and is proposed to have a total installed generating capacity of 10 MW or less, but more than 1.5 MW—Exhibits F and G under § 4.61, and Exhibit E under § 4.41;

    (4) For amendment of a license for a water power project that, at the time the Start Printed Page 42715application for amendment is filed, has been constructed, and is proposed to have a total installed generating capacity of 10 MW or less—Exhibit E, F, and G under § 4.61; and

    (5) For amendment of a license for a water power project that, at the time the application is filed, has been constructed and is proposed to have a total installed generating capacity of more than 10 MW—Exhibits A, B, C, D, E, F, and G under § 4.51.

    * * * * *
    [Amended]
    Start Amendment Part

    10. In § 4.401, remove paragraph (f)(3).

    End Amendment Part Start Part

    PART 5—INTEGRATED LICENSE APPLICATION PROCESS

    End Part Start Amendment Part

    11. The authority citation for part 5 continues to read as follows:

    End Amendment Part Start Authority

    Authority: 16 U.S.C. 792-828c, 2601-2645; 42 U.S.C. 7101-7352.

    End Authority Start Amendment Part

    12. In § 5.18, revise paragraph (a)(5)(i) to read as follows:

    End Amendment Part
    Application content.

    (a) * * *

    (5) * * *

    (i) License for a minor water power project and a major water power project 10 MW or less: § 4.61 of this chapter (General instructions, initial statement, and Exhibits A, F, and G);

    * * * * *
    End Supplemental Information

    Footnotes

    1.  Public Law 113-23, 127 Stat. 493 (2013).

    Back to Citation

    2.  Removing Profile Drawing Requirement for Qualifying Conduit Notices of Intent and Revising Filing Requirements for Major Hydroelectric Projects 10 MW or Less, 86 FR 13506 (Mar. 9, 2021), 174 FERC ¶ 61,105 (2021).

    Back to Citation

    3.  See Revisions and Technical Corrections to Conform the Commission's Regulations to the Hydropower Regulatory Efficiency Act of 2013, Order No. 800, 79 FR 59105 (Oct. 1, 2014), 148 FERC ¶ 61,197 (2014).

    Back to Citation

    4.  Public Law 115-270, 132 Stat. 3765 (2018).

    Back to Citation

    6.  Id. 823a(a)(3)(C). The qualifying conduit hydropower facility must also meet the requirements for a small conduit facility as defined in section 30(a)(3)(A) of the FPA. Id. 823a(a)(3)(A).

    Back to Citation

    7.  The 2013 HREA required that qualifying conduit hydropower facilities not exceed 5 MW. This limit was revised to 40 MW at section 3002(2) in the America's Water Infrastructure Act of 2018 (codified at 16 U.S.C. 823a(a)(3)(C)(ii)).

    Back to Citation

    8.  Public Law 115-270, 132 Stat. 3765.

    Back to Citation

    10.  Id. § 4.401(f).

    Back to Citation

    11.  151 FERC ¶ 61,228 (2015).

    Back to Citation

    12.  Id. P 13.

    Back to Citation

    14.  Regulations Governing Applications for License for Major Unconstructed Projects and Major Modified Projects; Applications for License for Transmission Line Only and Applications for Amendment to License, Order No. 184, 46 FR 55926 (Nov. 13, 1981), FERC Stats. & Regs. ¶ 30,308 (1981) (cross-referenced at 17 FERC ¶ 61,122); Regulations Governing Applications for License for Minor Water Power Projects and Major Water Power Projects 5 Megawatts or Less, Order No. 185, 46 FR 55944 (Nov. 13, 1981), FERC Stats. & Regs. ¶ 30,309 (1981) (cross-referenced at 17 FERC ¶ 61,121).

    Back to Citation

    15.  The Commission has maintained a distinction between major and minor projects based on section 10(i) of the FPA. However, the license application procedures set forth in § 4.61 of the Commission's regulations apply to both minor projects and major projects less than 5 MW (with the exception of Exhibit E for unconstructed projects). These revisions do not affect minor projects.

    Back to Citation

    16.  See Revisions and Technical Corrections to Conform the Commission's Regulations to the Hydropower Regulatory Efficiency Act of 2013, Order No. 800, 148 FERC ¶ 61,197 (2014).

    Back to Citation

    17.  Applications for License for Minor Water Power Projects and Major Water Power Projects 5 Megawatts or Less, 46 FR 9637 (Jan. 29, 1981), FERC Stats. & Regs. ¶ 32,106 (1981) (cross-referenced at 14 FERC ¶ 61,042).

    Back to Citation

    18.  Section 4.32(a)(5)(ii), which contains a cross-reference to § 4.61, will also be revised.

    Back to Citation

    21.  FERC-500 includes the reporting and recordkeeping requirements for “Application for License/Relicense for Water Projects with More than 5 Megawatt (MW) Capacity.”

    Back to Citation

    22.  FERC-505 includes the reporting and recordkeeping requirements for “Small Hydropower Projects and Conduit Facilities including License/Relicense, Exemption, and Qualifying Conduit Facility Determination.”

    Back to Citation

    23.  We consider the filing of an application or notice of intent to be a “response.”

    24.  Commission staff estimates that the industry's skill set and cost (for wages and benefits) for FERC-500 and FERC-505 are approximately the same as the Commission's average cost. The FERC 2020 average salary plus benefits for one FERC full-time equivalent (FTE) is $172,329/year (or $83.00/hour).

    Back to Citation

    25.  Regulations Implementing the National Environmental Policy Act of 1969, Order No. 486, 52 FR 47897 (Dec. 17, 1987), FERC Stats. & Regs. ¶ 30,783 (1987) (cross-referenced at 41 FERC ¶ 61,284).

    Back to Citation

    28.  Id. 603(c).

    Back to Citation

    29.  Id. 605(b).

    Back to Citation

    31.  Id. § 121.201.

    Back to Citation

    32.  The North American Industry Classification System (NAICS) is an industry classification system that Federal statistical agencies use to categorize businesses for the purpose of collecting, analyzing, and publishing statistical data related to the U.S. economy. United States Census Bureau, North American Industry Classification System, https://www.census.gov/​eos/​www/​naics/​.

    Back to Citation

    33.  13 CFR 121.201 (Sector 22—Utilities).

    Back to Citation

    [FR Doc. 2021-15511 Filed 8-4-21; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Effective Date:
10/4/2021
Published:
08/05/2021
Department:
Federal Energy Regulatory Commission
Entry Type:
Rule
Action:
Final rule.
Document Number:
2021-15511
Dates:
This rule is effective October 4, 2021.
Pages:
42710-42715 (6 pages)
Docket Numbers:
Docket No. RM20-21-000, Order No. 877
Topics:
Administrative practice and procedure, Electric power, Reporting and recordkeeping requirements
PDF File:
2021-15511.pdf
CFR: (9)
18 CFR 4.32
18 CFR 4.40
18 CFR 4.50
18 CFR 4.60
18 CFR 4.61
More ...