2024-16412. Takes of Marine Mammals Incidental to Specified Activities; Taking Marine Mammals Incidental to U.S. Coast Guard Fast Response Cutter Homeporting in Seward and Sitka, Alaska
Table 1—Pile Removal Methods and Durations at USCG Moorings Seward
Removal method and pile type Number of piles Duration per pile Piles removed per day Estimated duration (days) Vibratory extraction of 14-in steel piles 10 30 min 5 2 Note: A total of 10 steel piles will be removed over a total of 2 days (rate 5 piles/day). Pile cutting and diamond wire sawing may also be used but these methods are not expected to cause take of marine mammals.