E6-10838. Defense Federal Acquisition Regulation Supplement; Types of Contracts  

  • Start Preamble

    AGENCY:

    Defense Acquisition Regulations System, Department of Defense (DoD).

    ACTION:

    Final rule.

    SUMMARY:

    DoD has issued a final rule amending the Defense Federal Acquisition Regulation Supplement (DFARS) to update text on the selection and use of contract types. This rule is a result of a transformation initiative undertaken by DoD to dramatically change the purpose and content of the DFARS.

    EFFECTIVE DATE:

    July 11, 2006.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Ms. Robin Schulze, Defense Acquisition Regulations System, OUSD (AT&L) DPAP (DARS), IMD 3C132, 3062 Defense Pentagon, Washington, DC 20301-3062. Telephone (703) 602-0326; facsimile (703) 602-0350. Please cite DFARS Case 2003-D078.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    A. Background

    DFARS Transformation is a major DoD initiative to dramatically change the purpose and content of the DFARS. The objective is to improve the efficiency and effectiveness of the acquisition process, while allowing the acquisition workforce the flexibility to innovate. The transformed DFARS will contain only requirements of law, DoD-wide policies, delegations of FAR authorities, deviations from FAR requirements, and policies/procedures that have a significant effect beyond the internal operating procedures of DoD or a significant cost or administrative impact on contractors or offerors. Additional information on the DFARS Transformation initiative is available at http://www.acq.osd.mil/​dpap/​dars/​dfars/​transformation/​index.htm.

    This final rule is a result of the DFARS Transformation initiative. The DFARS changes—

    • Streamline text on the use of economic price adjustment clauses;
    • Increase, from 3 to 5 years, the standard maximum ordering period under basic ordering agreements;
    • Delete obsolete text on the use of cost-plus-fixed-fee contracts for environmental restoration; Start Printed Page 39007
    • Delete unnecessary text on design stability and use of incentive provisions; and
    • Delete procedures for selecting contract type and for use of special economic price adjustment clauses, incentive contracts, and basic ordering agreements. Text on these subjects has been relocated to the DFARS companion resource, Procedures, Guidance, and Information (PGI), available at http://www.acq.osd.mil/​dpap/​dars/​pgi.

    DoD published a proposed rule at 70 FR 54694 on September 16, 2005. DoD received no comments on the proposed rule. Therefore, DoD has adopted the proposed rule as a final rule without change.

    This rule was not subject to Office of Management and Budget review under Executive Order 12866, dated September 30, 1993.

    B. Regulatory Flexibility Act

    DoD certifies that this final rule will not have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq., because the rule updates and streamlines DFARS text, but makes no significant change to DoD contracting policy.

    C. Paperwork Reduction Act

    The Paperwork Reduction Act does not apply, because the rule does not impose any information collection requirements that require the approval of the Office of Management and Budget under 44 U.S.C. 3501, et seq.

    Start List of Subjects

    List of Subjects in 48 CFR Part 216

    • Government procurement
    End List of Subjects Start Signature

    Michele P. Peterson,

    Editor, Defense Acquisition Regulations System.

    End Signature Start Amendment Part

    Therefore, 48 CFR part 216 is amended as follows:

    End Amendment Part Start Part

    PART 216—TYPES OF CONTRACTS

    End Part Start Amendment Part

    1. The authority citation for 48 CFR part 216 continues to read as follows:

    End Amendment Part Start Authority

    Authority: 41 U.S.C. 421 and 48 CFR Chapter 1.

    End Authority
    [Removed]
    Start Amendment Part

    2. Section 216.104 is removed.

    End Amendment Part Start Amendment Part

    3. Section 216.104-70 is revised to read as follows:

    End Amendment Part
    Research and development.

    Follow the procedures at PGI 216.104-70 for selecting the appropriate research and development contract type.

    Start Amendment Part

    4. Section 216.203-4 is revised to read as follows:

    End Amendment Part
    Contract clauses.

    (1) Generally, use the clauses at FAR 52.216-2, Economic Price Adjustment—Standard Supplies, FAR 52.216-3, Economic Price Adjustment—Semistandard Supplies, and FAR 52.216-4, Economic Price Adjustment—Labor and Material, only when—

    (i) The total contract price exceeds the simplified acquisition threshold; and

    (ii) Delivery or performance will not be completed within 6 months after contract award.

    (2) Follow the procedures at PGI 216.203-4 when using an economic price adjustment clause based on cost indexes of labor or material.

    Start Amendment Part

    5. Section 216.306 is amended by revising paragraph (c)(ii) to read as follows:

    End Amendment Part
    Cost-plus-fixed-fee contracts.

    (c) * * *

    (ii) The prohibition in paragraph (c)(i) of this section does not apply to contracts specifically approved in writing, setting forth the reasons therefor, in accordance with the following:

    (A) The Secretaries of the military departments are authorized to approve such contracts that are for environmental work only, provided the environmental work is not classified as construction, as defined by 10 U.S.C. 2801.

    (B) The Secretary of Defense or designee must approve such contracts that are not for environmental work only or are for environmental work classified as construction.

    Start Amendment Part

    6. Sections 216.402-2 through 216.403-2 are revised to read as follows:

    End Amendment Part
    Technical performance incentives.

    See PGI 216.402-2 for guidance on establishing performance incentives.

    Fixed-price incentive contracts.
    Fixed-price incentive (successive targets) contracts.

    See PGI 216.403-2 for guidance on the use of fixed-price incentive (successive targets) contracts.

    [Removed]
    Start Amendment Part

    7. Section 216.404 is removed.

    End Amendment Part Start Amendment Part

    8. Section 216.405-1 is revised to read as follows:

    End Amendment Part
    Cost-plus-incentive-fee contracts.

    See PGI 216.405-1 for guidance on the use of cost-plus-incentive-fee contracts.

    Start Amendment Part

    9. Section 216.405-2 is revised to read as follows:

    End Amendment Part
    Cost-plus-award-fee contracts.

    (b) Application. The cost-plus-award-fee (CPAF) contract may include provisional award fee payments. A provisional award fee payment is a payment made within an evaluation period prior to a final evaluation for that period. The contracting officer may include provisional award fee payments in a CPAF contract on a case-by-case basis, provided those payments—

    (i) Are made no more frequently than monthly;

    (ii) Are limited to no more than—

    (A) For the initial award fee evaluation period, 50 percent of the award fee available for that period; and

    (B) For subsequent award fee evaluation periods, 80 percent of the evaluation score for the prior evaluation period times the award fee available for the current period, e.g., if the contractor received 90 percent of the award fee available for the prior evaluation period, provisional payments for the current period shall not exceed 72 percent (90 percent x 80 percent) of the award fee available for the current period;

    (iii) Are superseded by an interim or final award fee evaluation for the applicable evaluation period. If provisional payments have exceeded the payment determined by the evaluation score for the applicable period, the contracting officer shall collect the debt in accordance with FAR 32.606; and

    (iv) May be discontinued, or reduced in such amounts deemed appropriate by the contracting officer, when the contracting officer determines that the contractor will not achieve a level of performance commensurate with the provisional payment. The contracting officer shall notify the contractor in writing of any discontinuance or reduction in provisional award fee payments.

    (c) Limitations.

    (i) The CPAF contract shall not be used—

    (A) To avoid—

    (1) Establishing cost-plus-fixed-fee contracts when the criteria for cost-plus-fixed-fee contracts apply; or

    (2) Developing objective targets so a cost-plus-incentive-fee contract can be used; or

    (B) For either engineering development or operational system development acquisitions that have specifications suitable for simultaneous research and development and production, except a CPAF contract may be used for individual engineering development or operational system development acquisitions ancillary to the development of a major weapon system or equipment, where—

    (1) It is more advantageous; and Start Printed Page 39008

    (2) The purpose of the acquisition is clearly to determine or solve specific problems associated with the major weapon system or equipment.

    (ii) Do not apply the weighted guidelines method to CPAF contracts for either the base (fixed) fee or the award fee.

    (iii) The base fee shall not exceed 3 percent of the estimated cost of the contract exclusive of the fee.

    (S-70) See PGI 216.405-2 for guidance on the use of CPAF contracts.

    Start Amendment Part

    10. Section 216.470 is revised to read as follows:

    End Amendment Part
    Other applications of award fees.

    See PGI 216.470 for guidance on other applications of award fees.

    Start Amendment Part

    11. Section 216.703 is revised to read as follows:

    End Amendment Part
    Basic ordering agreements.

    (c) Limitations. The period during which orders may be placed against a basic ordering agreement may not exceed 5 years.

    (d) Orders. Follow the procedures at PGI 216.703(d) for issuing orders under basic ordering agreements.

    End Supplemental Information

    [FR Doc. E6-10838 Filed 7-10-06; 8:45 am]

    BILLING CODE 5001-08-P

Document Information

Comments Received:
0 Comments
Effective Date:
7/11/2006
Published:
07/11/2006
Department:
Defense Acquisition Regulations System
Entry Type:
Rule
Action:
Final rule.
Document Number:
E6-10838
Dates:
July 11, 2006.
Pages:
39006-39008 (3 pages)
Docket Numbers:
DFARS Case 2003-D078
Topics:
Government procurement
PDF File:
e6-10838.pdf
CFR: (12)
48 CFR 216.104
48 CFR 216.306
48 CFR 216.403
48 CFR 216.404
48 CFR 216.470
More ...