E7-13871. Texas Eastern Transmission, LP; Notice of Application  

  • Start Preamble July 11, 2007.

    Take notice that on June 29, 2007, Texas Eastern Transmission, LP (Texas Eastern), P.O. Box 1642, Houston, Texas 77251-1642, filed in Docket No. CP07-411-000, an application pursuant to section 7of the Natural Gas Act (NGA) and part 157 of the Commission's Regulations, seeking (1) authorization to install, construct, own, operate and maintain certain pipeline facilities, consisting primarily of the installation of approximately 3.79 miles of 20-inch diameter pipeline and a meter and regulating station (the Cedar Bayou Lateral Project), and (2) an initial rate for firm service on the Cedar Bayou Lateral under Rate Schedule MLS-1, all as more fully set forth in the application which is on file with the Commission Start Printed Page 39396and open to public inspection. This filing is accessible online at http://www.ferc.gov,, using the “eLibrary” link and is available for review in the Commission's Public Reference Room in Washington, DC. There is an “eSubscription” link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For TTY, call (202) 502-8659.

    Specifically, Texas Eastern states that the facilities are required to enable Texas Eastern to provide up to 360,000 Dth/d of Rate Schedule MLS-1 firm transportation service to the Cedar Bayou Power plant owned by NRG Energy, Inc. (NRG). Texas Eastern states that although a project of this scope would otherwise qualify for construction under the blanket certificate procedures, proposing an initial rate under Rate Schedule MLS-1 requires a section 7(c) application. Texas Eastern states that the capital cost used to calculate the Cedar Bayou Lateral Project cost of service is $16,514,000.

    Any questions regarding this application should be directed to Garth Johnson, Director, Certificates & Reporting, Texas Eastern Transmission, LP, P.O. Box 1642, Houston, Texas 77251-1642, at (713) 627-5415.

    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission's public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff's issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission's public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify Federal and State agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all Federal authorizations within 90 days of the date of issuance of the Commission staff's FEIS or EA.

    There are two ways to become involved in the Commission's review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below, file with the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 14 copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding.

    However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission's rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest.

    Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission's environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission's environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission's final order.

    Comments, protests and interventions may be filed electronically via the Internet in lieu of paper. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site under the “e-Filing” link at http://www.ferc.gov. The Commission strongly encourages intervenors to file electronically. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426.

    Comment Date: 5 p.m. Eastern Time on August 1, 2007.

    Start Signature

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    [FR Doc. E7-13871 Filed 7-17-07; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Comments Received:
0 Comments
Published:
07/18/2007
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
E7-13871
Dates:
5 p.m. Eastern Time on August 1, 2007.
Pages:
39395-39396 (2 pages)
Docket Numbers:
Docket No. CP07-411-000
EOCitation:
of 2007-07-11
PDF File:
e7-13871.pdf