PLEASE SEE THE TWO QUESTIONS BELOW - CLARIFICATION NEEDS TO TAKE PLACE
CONCERNING § 250.420 What well casing and cementing
requirements must I meet?
(b) * * *
(3) For the final casing string (or liner
if it is your final string), you must install
dual mechanical barriers in addition to
cement, to prevent flow in the event of
a failure in the cement. These may
include dual float valves, or one float
valve and a mechanical barrier. You
must submit documentation to BOEMRE
30 days after installation of the dual
mechanical barriers.
Question :
Does the dual mechanical barrier requirement apply to just the inside of the casing or to both the inside and annulus flow paths ? We believe you are meaning the inside only.
CONCERNINIG § 250.423 What are the requirements for
pressure testing casing?
(c) You must perform a negative
pressure test on all wells to ensure
proper casing installation. You must
perform this test for the intermediate
and production casing strings.
Question :
What is the definition of intermediate casing? The rule states a negative pressure test is required for intermediate and production casing. If drilling liners are set below intermediate casing is additional negative testing required ?
Comment from DEAN SWANZY, PETROBRAS AMERICA
This is comment on Rule
Oil and Gas and Sulphur Operations in Outer Continental Shelf: Increased Safety Measures for Energy Development on Outer Continental Shelf
View Comment
Related Comments
View AllPublic Submission Posted: 10/19/2010 ID: BOEM-2010-0034-0005
Dec 13,2010 11:59 PM ET
Public Submission Posted: 11/02/2010 ID: BOEM-2010-0034-0006
Dec 13,2010 11:59 PM ET
Public Submission Posted: 11/05/2010 ID: BOEM-2010-0034-0007
Dec 13,2010 11:59 PM ET
Public Submission Posted: 11/08/2010 ID: BOEM-2010-0034-0008
Dec 13,2010 11:59 PM ET
Public Submission Posted: 11/10/2010 ID: BOEM-2010-0034-0009
Dec 13,2010 11:59 PM ET