GSA needs to remind Contracting Officers (COs) under 516.2 that, in order for a
contract to be procured on a firm-fixed price basis, the solicitation must be based
on “reasonably definite functional or detailed specifications...when the contracting
officer can establish fair and reasonable prices at the outset.” Conversely, “when
it is not possible at the time of placing the contract to estimate accurately the
extent or duration of the work or to anticipate costs with any reasonable degree of
confidence”, COs should use a time-and-materials/labor-hour contract, which
includes a “ceiling price” based on “fixed hourly rates,” if the required
determination and findings is approved per FAR 16.601(d). In other words, GSA
should require COs to include the fixed basis for the requirements (e.g.
performance period, man-hours), in a solicitation/RFQ if it is to be awarded and
reported as a fixed price contract. If COs can not include these definitive
requirements in the solicitation or RFQ, expects to award the contract in a not-to-
exceed/ceiling price amount, or expects offerors to ‘propose’ the number of hours,
etc., the GSAM should forbid COs from procuring or reporting the action as
a “fixed price” contract award.
GSAM should also prohibit GSA COs from unilaterally reducing any hours or
contract price on these 516.6 not-to-exceed contracts, or ‘deobligating’ awarded
funds without a bilateral supplemental agreement. The GSAM should remind
GSA COs that unilateral “administrative” modifications are appropriate only for
actions that do not affect contract price/cost. Even a unilateral Change Order
mod must be followed by a bilateral supplemental agreement mod to reflect the
equitable adjustment amount pursuant to FAR 43.204(a). [It may be more
appropriate to address this in GSAM 543, but the violations seem to occur only on
not-to-exceed (labor hour/time-and-materials) contracts (that are being awarded
and reported by GSA COs as fixed price contracts).]
I would also like to recommend that GSA consider adding the word "Additional" at
the beginning of the 516.603-70 title, "Limitations on the use of letter contracts for
architect-engineer (A-E) services." This could serve as a simple reminder that
there are other 'Limitations' that must be considered in accordance with FAR
16.603-3. In particular, based on my experience, the vast majority of COs fail to
obtain the written Determination from the HCA, or designee,
that "no other contract is suitable."
I'd also like to question the restriction GSA has placed on contractors to submit
a "price proposal…before the award" of a letter contract. FAR 16.603-3(c)
requires COs to include in the mandated FAR 52.216-25 clause a 'definitization
schedule' including "(1) dates for submission of the contractor’s price proposal…"
Similarly, the FAR 52.216-25 clause itself includes notes to the CO to
insert "dates for submission of proposal". So isn't this requirement inconsistent
with the flexibilities demanded throughout FAR, especially in FAR part 1, in
addition to the FAR 16.6 regulations?
Ditto this concern with the prohibition placed on COs to "not authorize the A-E to
begin the design effort before the letter contract is definitized." Doesn't this defeat
the whole purpose of a letter contract which, according to FAR 16.603-1, is to
authorize "the contractor to begin immediately … performing services"? If yes,
then the Determination should support any decision to not award a letter contract
if COs comply with FAR 16.603-3.
Therefore, my recommendation would be for GSA to delete 516.703-70 in its
entirety from the GSAM/GSAR. In the alternative, GSA should consider
incorporating oversight requirements into this section to review all Determinations
that authorize letter contracts to ensure decisions are being made appropriately.
GSA should also consider auditing all unilateral/admin mods that involve any
change in funding/costs.
However, if GSA agrees to delete 516.703-70, GSA may still need to cross
reference comment from above, regarding 516.2, to remind COs that any contract
that is procured and awarded with a not-to-exceed/ceiling price falls under the
prescription, and limitations, of FAR 16.6. Contracts awarded with a not-to-
exceed/ceiling price can not be procured and/or reported as “fixed price” even
though they are based on "fixed hourly rates".
GSAR Case 2006-504; Rewrite of GSAR Part 516; Types of Contracts (Comment #2)
This is comment on Proposed Rule
GSAR Case 2006-G504; Rewrite of GSAR Part 516; Types of Contracts
View Comment
Related Comments
Public Submission Posted: 09/09/2008 ID: GSA-GSAR-2008-0007-0031
Sep 08,2008 11:59 PM ET
Public Submission Posted: 09/09/2008 ID: GSA-GSAR-2008-0007-0032
Sep 08,2008 11:59 PM ET
Public Submission Posted: 09/09/2008 ID: GSA-GSAR-2008-0007-0033
Sep 08,2008 11:59 PM ET
Public Submission Posted: 09/09/2008 ID: GSA-GSAR-2008-0007-0034
Sep 08,2008 11:59 PM ET
Public Submission Posted: 09/09/2008 ID: GSA-GSAR-2008-0007-0035
Sep 08,2008 11:59 PM ET