I offer the following comments in response to GSAR Case 2006-G504; Rewrite of
GSAR Part 516; Types of Contracts.
The GSAM should remind Contracting Officers (COs) under 516.2 that, in order for
a contract to be procured on a firm-fixed price basis, the solicitation must be
based on “reasonably definite functional or detailed specifications...when the
contracting officer can establish fair and reasonable prices at the outset.”
Conversely, “when it is not possible at the time of placing the contract to estimate
accurately the extent or duration of the work or to anticipate costs with any
reasonable degree of confidence”, COs should use a time-and-materials/labor-hour
contract, which includes a “ceiling price” based on “fixed hourly rates,” if the
required determination and findings is approved per FAR 16.601(d). In other
words, GSA should require COs to include the fixed basis for the requirements
(e.g. performance period, man-hours), in a solicitation/RFQ if it is to be awarded
and reported as a fixed price contract. If COs can not include these definitive
requirements in the solicitation or RFQ, expects to award the contract in a not-to-
exceed/ceiling price amount, or expects offerors to ‘propose’ the number of hours,
etc., the GSAM should forbid COs from procuring or reporting the action as
a “fixed price” contract award. Conversely, any award of a contract as fixed price,
based on indefinite requirements, could result in unnecessary or excessive costs
to the Government.
GSAM should also prohibit GSA COs from unilaterally reducing any hours or
contract price on these not-to-exceed contracts, or ‘deobligating’ awarded funds
as an administrative modification. The GSAM should remind GSA COs that
unilateral “administrative” modifications are appropriate only for actions that do not
affect contract price/cost. Even a unilateral Change Order mod must be followed
by a bilateral supplemental agreement mod to reflect the equitable adjustment
amount pursuant to FAR 43.204(a). [It may be more appropriate to address this
in GSAM 543, but the violations seem to occur primarily on not-to-exceed (labor
hour/time-and-materials) contracts (that are being awarded and reported by GSA
COs as fixed price contracts).] GSA should consider conducting an audit/review
of all ‘administrative’ mods that involve any changes in funds/costs to ensure
compliance with the FAR 43.103.
I would also like to recommend that GSA consider adding the word "Additional" at
the beginning of the 516.603-70 title, "Limitations on the use of letter contracts for
architect-engineer (A-E) services." This could serve as a simple reminder that
there are other 'Limitations' that must be considered in accordance with FAR
16.603-3. In particular, based on my experience, the vast majority of COs fail to
obtain the written Determination from the HCA, or designee, that "no other
contract is suitable."
I'd also like to question the restriction GSA has placed on contractors to submit
a "price proposal…before the award" of a letter contract. FAR 16.603-3(c)
requires COs to include in the mandated FAR 52.216-25 clause a 'definitization
schedule' including "(1) dates for submission of the contractor’s price proposal…"
Similarly, the FAR 52.216-25 clause itself includes notes to the CO to
insert "dates for submission of proposal". So isn't this requirement inconsistent
with the flexibilities demanded throughout FAR, especially in FAR part 1, in
addition to the FAR 16 regulations?
Ditto this concern with the prohibition placed on COs to "not authorize the A-E to
begin the design effort before the letter contract is definitized." Doesn't this defeat
the whole purpose of a letter contract which, according to FAR 16.603-1, is to
authorize "the contractor to begin immediately … performing services"? If yes,
then the Determination should support the decision to not award a letter contract if
COs comply with FAR 16.603-3.
Therefore, my recommendation would be for GSA to delete 516.703-70 in its
entirety from the GSAM/GSAR. In the alternative, GSA should consider
incorporating oversight requirements into this section to review all Determinations
that authorize letter contracts to ensure decisions are being made appropriately.
However, even if GSA decides to delete 516.703-70, it may still need to cross
reference comment from above, regarding 516.2, to remind COs that any contract
that is procured and awarded with a not-to-exceed/ceiling price falls under the
prescription, and limitations, of FAR 16.6. Contracts awarded with a not-to-
exceed/ceiling price can not be procured and/or reported as “fixed price” even
though they are based on fixed hourly rates.
Thank you for this opportunity to community.
GSAR Case 2006-504; Rewrite of GSAR Part 516; Types of Contracts (Comment #3)
This is comment on Proposed Rule
GSAR Case 2006-G504; Rewrite of GSAR Part 516; Types of Contracts
View Comment
Related Comments
Public Submission Posted: 09/09/2008 ID: GSA-GSAR-2008-0007-0031
Sep 08,2008 11:59 PM ET
Public Submission Posted: 09/09/2008 ID: GSA-GSAR-2008-0007-0032
Sep 08,2008 11:59 PM ET
Public Submission Posted: 09/09/2008 ID: GSA-GSAR-2008-0007-0033
Sep 08,2008 11:59 PM ET
Public Submission Posted: 09/09/2008 ID: GSA-GSAR-2008-0007-0034
Sep 08,2008 11:59 PM ET
Public Submission Posted: 09/09/2008 ID: GSA-GSAR-2008-0007-0035
Sep 08,2008 11:59 PM ET