The following comments are respectfully submitted in response to the GSAR
Case 532 publication.
GSA’s 1142 Release of Claim form contains no OMB control number indicating it
has been approved for the collection of information. Additionally, there is no
indication that a Regulatory Flexibility Analysis was ever performed to reflect the
burden or impact on contractors, including small businesses, especially the
requirements for a ‘witness’ and a ‘seal’. Additionally the form fails to advise
contractors, especially small businesses that, by signing the form, they are likely
waiving their rights to submit claims permitted under the Disputes Act. It is
improper for the government to require an unconditional release from contractors
as a prerequisite for final payment. Therefore, it is recommended that the form be
revised to recognize a contractor’s right to submit claims “within 6 years following
the release date or notice of final payment date, whichever is earlier” as set forth
in FAR 52.216-7(h)(2)(ii), and FAR 33.206, when a claim was unknown at the time
of executing the form. Similarly the form should allow contractors the ability to
cite ‘estimated amounts when the exact amounts are not known” as permitted
under the same FAR clause.
Furthermore, since releases of claims are cited in FAR [52.232-7(g) for Time &
Material/Labor Hour contracts, and in paren as an example(‘e.g.’) under 52.232-26
and -27 for A-E and construction contracts, respectively], it would seem more
appropriate for the FAR Council to develop a Standard Form (SF) to be used by all
agencies in accordance with FAR 1.304(c) since it is not just pertinent to GSA.
And since releases apply to “final payments”, it is highly recommended that GSA
and/or the FAR Council consider allowing contractors to submit the release jointly
along with the electronic submission of a final invoice request.
There is a major concern about GSA’s allowance for Contracting Officers (COs) to
make “repeated attempts” to obtain a release of claims from contractors under
GSAM 532.904 as this could be construed as coercion penalizing contractors by
withholding funds “without cause”. GSAM should justify the reasonableness of
withholding any funds from contractors beyond the 30 days authorized by FAR for
final payments. Any ”unreasonable delay” in payment could, by law, convert
invoices into a claim. Recommendation is made for GSA to consider establishing
a limit to the number of “repeated attempts” and a maximum number of days for
GSA COs to withhold final payment from the date when the invoice is officially
received.
The GSAM needs to provide some guidance for any authority of COs to initiate an
action for A-E design services in advance of approved appropriations. Many find
nothing in the FAR that precludes COs from selecting an A-E using Brooks Act
procedures through the solicitation and negotiation phase up to award when the
appropriation request is included in the President's Budget. Others wait until after
the budget has actually been approved and still others wait until the funds have
actually been received in their organizational office before they publish the
synopsis notice. Consistency should be established based on what is in the best
interest of the Government and what is appropriate.
Electronic Invoices
Contractors experience numerous problems attempting to submit invoices
electronically to GSA for payment. Frequently GSA has failed to enter obligations
into Pegasys which, in turn, prohibits contractors from being able to submit a pay
request and establish a ‘receipt date’ for purposes of computing interest which
appears to be in direct violation of FAR 32.907(f). GSA’s Pegasys system should
permit contractors to submit an invoice and date it as ‘received’ for interest
purposes regardless of whether or not GSA has entered the obligations. If the
invoice was submitted in error or ‘improper’ in any way, there are mechanisms
permitted under FAR for rejecting the invoice. But contractors, esp. small and
disadvantage, including 8(a) firms, should not be penalized for GSA’s failure to
enter obligations into the system in a timely manner. Nor should GSA be
permitted to escape its responsibility to pay interest and/or penalties for late
payment. As an added protection for contractors, it is also recommended that
GSA include a notice on its invoicing system to cite FAR 32.909(b)’s suggestion
to contact GSA’s small business specialist or representative from the Office of
Small and Disadvantaged Business Utilization to obtain additional assistance
related to payment issues, late payment interest penalties, and information on the
Prompt Payment Act.” If satisfaction is not achieved from GSA’s designated
representative, small businesses should be encouraged to seek assistance from
SBA’s Advocacy office.
Construction
To eliminate confusion and ensure consistency, all GSA contractors should be
permitted to submit invoices electronically including those for construction
contracts awarded on an SF1442. It should be noted that invoices for
construction contracts awarded on a GSA 300 as a task order against an IDIQ are
permitted to be submitted electronically. All construction payments, whether
awarded on an SF 1442 or a GSA 300, are 14-day pay. To ensure “prompt
payment”, GSA should also consider allowing contractors to submit
the “substantiation” information electronically with their invoice.
Additionally there is currently no requirement in FAR for construction contractors
to attend “progress payment meetings” and/or submit preliminary invoices to the
Government for ’approval’ prior to formally submitting them to the CO. Any
requirement for contractors to attend a progress meeting and/or submit
preliminary invoices for approval, as a condition for a “proper invoice", would
appear to require a deviation to FAR 32.904. In fact, FAR 52.232-5(b) states, “The
Government shall make progress payments monthly as the work proceeds, or at
more frequent intervals as determined by the Contracting Officer, on estimates of
work accomplished which meets the standards of quality established under the
contract, as approved by the Contracting Officer.” Therefore it is recommended
that GSA develop a clause for incorporation into GSAM to address the PBS
requirement for preliminary approval and/or progress payment meetings as a
prerequisite for invoice approval if deemed appropriate. If not appropriate, the
GSAM should prohibit this practice.
Per FAR 32.103, “Retainage should not be used as a substitute for good contract
management, and the CO should not withhold funds without cause.
Determinations…will be based on the contracting officer’s assessment of past
performance and the likelihood that such performance will continue.” More
importantly, the percentage should “recognize better than expected performance,
the ability to rely on alternative safeguards, and other factors” such as the
allowance and responsibility of COs to approve a lesser amount for payment than
than contractor has indicated in the invoice if estimated progress is not accurate.
Furthermore, para. (e) of the construction payment clause states that :”the
Contracting Officer shall authorize payment to be made in full” when “satisfactory
progress was achieved during any period for which a progress payment is to be
made.” And even “if satisfactory progress has not been made”, the CO is limited
to “retaining a maximum of 10 percent of the amount of the payment until
satisfactory progress is achieved.” COs are not permitted to withhold 10% of the
total contract price, only the payment amount, and retainage is not permitted
when progress is satisfactory. Therefore, it is recommended that GSAM remind
COs of the FAR 32.103 requirement to execute a written ‘determination’ to
withhold any funds including retainage. It is further suggested that GSA consider
adding a requirement for approval of any withholding of funds at a level above the
CO to ensure compliance.
Just like the Release of Claims form, it would seem more appropriate for the FAR
Council to develop a Standard Form (SF) to be used by all agencies in
accordance with FAR 1.304(c) in lieu of GSA’s Certification of Progress Payment
Form 2419 since the requirement is set forth for all construction contracts under
FAR 32.904(d)(1)(i)(C) and not specific to GSA. And since this certification
requirement applies to all construction invoices, it is highly recommended that
GSA and/or the FAR Council consider allowing contractors to submit the
certification jointly along with any electronic submission of an invoice. In the
alternative, COs should recognize the fact that most invoices, including AIA's
application for payment, already have a built-in certification. So use of the GSA
2419 form is often unnecessary duplication.
Rejection of Invoices
Any rejection of invoices should cite the specific section of FAR 32.905(b)(1) that
is in non-compliance and also advise contractors of their rights under the Disputes
clause. Avoidance of interest or penalties should not be a sufficient reason for
GSA COs to reject an invoice. In particular, if the reason is failure to comply with
a contract requirement, the rejection should cite the specific term or condition.
GSA COs should be reminded also that a disagreement in payment amounts
does not require rejection since a lesser amount can be authorized if appropriate.
In fact, GSA should provide contractors with the information cited under FAR
32.906(b)(4) which says, “When it is determined that the designated billing office
erroneously rejected a proper invoice and upon resubmission of the invoice, will
enter in the payment system the original date the invoice was received by the
designated billing office for the purpose of calculating the correct payment due
date and any interest penalties that may be due.”
EFT
Lastly, GSA has from time-to-time collected EFT information from contractors
using a form that has not been approved by OMB for this collection of information.
More importantly there is no indication that GSA is ensuring the financial
information collected is protected as privileged and confidential in accordance with
FAR 32.1104. Therefore a recommendation is made to review any form used by
GSA to collect EFT information from contractors, that are not required to be
registered in CCR (i.e. where FAR 52.232-34 applies), and perform a proper
analysis as required by the Paperwork Reduction Act to ensure compliance with
FAR.
Thank you for the opportunity to comment on this case.
Regards,
Debbie Loftin
GSAR Case 2006-G515; Rewrite of Part 532, Contract Financing (Comment #1)
This is comment on Proposed Rule
GSAR Case 2006-G515; Rewrite of Part 532, Contract Financing
View Comment
Related Comments
Public Submission Posted: 11/07/2008 ID: GSA-GSAR-2008-0007-0046
Nov 06,2008 11:59 PM ET
Public Submission Posted: 11/07/2008 ID: GSA-GSAR-2008-0007-0047
Nov 06,2008 11:59 PM ET
Public Submission Posted: 11/07/2008 ID: GSA-GSAR-2008-0007-0048
Nov 06,2008 11:59 PM ET