Code of Federal Regulations (Last Updated: November 8, 2024) |
Title 10 - Energy |
Chapter III—Department of Energy |
Part 900 - Coordination of Federal Authorizations for Electric Transmission Facilities |
§ 900.3 - Applicability to other projects.
-
§ 900.3 Definitions.
As used in this part:
Affected landowner means an owner of real property interests who is usually referenced in the most recent county or city tax records, and whose real property:
(1) Is located within either 0.25 miles of a proposed study corridor or route of a qualifying project or at a minimum distance specified by state law, whichever is greater; or
(2) Contains a residence within 3000 feet of a proposed construction work area for a qualifying project.
DOE means the United States Department of Energy.
Early identification of project issues refers to an early and open stakeholder participation process carried out by a project proponent as a part of its project development activities to identify potential environmental issues Federal and Non-Federal entities' may consider for further study, issues of concern to the affected public and stakeholders, and potential project alternatives.
Federal entity means any Federal agency with jurisdictional interests that may have an effect on a proposed qualifying project, that is responsible for issuing a Federal authorization for the proposed qualifying project or attendant facilities, has relevant expertise with respect to environmental and other issues pertinent to or that are potentially affected by the proposed qualifying project or its attendant facilities, or provides funding for the proposed qualifying project or its attendant facilities. Federal entities include those with either permitting or non-permitting authority; for example, those entities with which consultation or review must be completed before a project may commence, such as the Department of Defense for an examination of military test, training or operational impacts.
FPA means the Federal Power Act (16 U.S.C. 791 through 828c).
IIP process administrative file means the information assembled and maintained by DOE as the Lead section 216(h) Agency. The IIP Process Administrative File will include the IIP Initiation Request, which includes a Summary of Qualifying Project, Affected Environmental Resources and Impacts Summary, associated Maps, Geospatial Information and Data (provided in electronic format), and a Summary of Early Identification of Project Issues. The IIP Process Administrative File will also include IIP Meeting Summaries, an IIP Resources Report, and other documents, including but not limited to maps, publicly-available data, and other supporting documentation submitted by the project proponent as part of the IIP Process that inform the Federal entities.
IIP resources report means the resource summary information provided by the project proponent as a part of the IIP Process that meets the content requirements pursuant to § 900.4 of this part. The IIP Resource Report contains the environmental information used by a project proponent to plan a qualifying project.
Indian tribe has the same meaning as provided for in 25 U.S.C. 450b(e).
Lead 216(h) agency means the Department of Energy, which section 216(h) of the FPA (16 U.S.C. 824p(h)) makes responsible for timely coordination of Federal authorization requests for proposed electric transmission facilities.
MOU principals means the heads of each of the MOU signatory agencies.
MOU signatory agency means a signatory of the Interagency MOU executed on October 23, 2009, entitled, “Memorandum of Understanding among the United States (U.S.) Department of Agriculture (USDA), the Department of Commerce, Department of Defense (DoD), Department of Energy (DOE), Environmental Protection Agency (EPA), the Council on Environmental Quality (CEQ), the Federal Energy Regulatory Commission (FERC), the Advisory Council on Historic Preservation (ACHP), and Department of the Interior (DOI), regarding Coordination in Federal Agency Review of Electric Transmission Facilities on Federal Lands.”
NEPA means the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.)
NEPA lead agency means the Federal agency or agencies preparing or having primary responsibility for preparing an environmental impact statement or environmental assessment as defined in 40 CFR 1508.16 and in accordance with 40 CFR 1501.5(c).
Non-federal entity means an Indian Tribe, multistate governmental entity, or state and local government agency with relevant expertise and/or jurisdiction within the project area, that is responsible for conducting permitting and environmental reviews of the proposed qualifying project or its attendant facilities, that has special expertise with respect to environmental and other issues pertinent to or that are potentially affected by the proposed qualifying project or its attendant facilities, or provides funding for the proposed qualifying project or its attendant facilities. Non-Federal entities may include those with either permitting or non-permitting authority, e.g., entities such as State Historic Preservation Offices, with whom consultation must be completed in accordance with section 106 of the National Historic Preservation Act, 54 U.S.C. 306108, before a project can commence.
OE-1 means the Assistant Secretary for DOE's Office of Electricity Delivery and Energy Reliability.
Other projects mean electric transmission facilities that are not qualifying projects. Other Projects may include facilities for the transmission of electric energy in interstate commerce for the sale of electric energy at wholesale that do not meet the 230 kV or above qualification, or are not otherwise identified as regionally or nationally significant with attendant facilities, in which all or part of a proposed transmission line—
(1) Crosses jurisdictions administered by more than one Federal entity; or
(2) Crosses jurisdictions administered by a Federal entity and is considered for Federal financial assistance from a Federal entity.
Project area means the geographic area considered when the project proponent develops study corridors and then potential routes for environmental review and potential project siting as a part of the project proponent's planning process for a qualifying project. It is an area located between the two end points of the project (e.g., substations), including their immediate surroundings within at least one-mile of that area, as well as any proposed intermediate substations. The size of the project area should be sufficient to allow for the evaluation of various potential alternative routes with differing environmental, engineering, and regulatory constraints. The project area does not necessarily coincide with “permit area,” “area of potential effect,” “action area,” or other defined terms of art that are specific to types of regulatory review.
Project proponent means a person or entity who initiates the IIP Process in anticipation of seeking Federal authorizations for a qualifying project or Other Project.
Qualifying project means a non-marine high voltage electric transmission line (230 kV or above) and its attendant facilities, or other regionally or nationally significant non-marine electric transmission line and its attendant facilities, in which:
(1) All or part of the proposed electric transmission line is used for the transmission of electric energy in interstate commerce for sale at wholesale, and
(2) All or part of the proposed electric transmission line crosses jurisdictions administered by more than one Federal entity or crosses jurisdictions administered by a Federal entity and is considered for Federal financial assistance from a Federal entity. qualifying projects do not include those for which a project proponent seeks a construction or modification permit from the FERC for electric transmission facilities in a DOE-designated National Interest Electric Transmission Corridor under section 216(b) of the FPA (16 U.S.C. 824p(b)).
Regional mitigation approach means an approach that applies the mitigation hierarchy (first seeking to avoid, then minimize impacts, then, when necessary, compensate for residual impacts) when developing mitigation measures for impacts to resources from qualifying projects at scales relevant to the resource, however narrow or broad, necessary to sustain, or otherwise achieve established goals for those resources. The approach identifies the needs and baseline conditions of targeted resources, potential impacts from the qualifying projects, cumulative impacts of past and likely projected disturbance to those resources, and future disturbance trends. The approach then uses such information to identify priorities for avoidance, minimization, and compensatory mitigation measures across that relevant area to provide the maximum benefit to the impacted resources.
Regional mitigation strategies or plans mean documents developed through or external to the NEPA process that apply a Regional Mitigation Approach to identify appropriate mitigation measures in advance of potential impacts to resources from qualifying projects.
Route means a linear area within which a qualifying project could be sited. It should be wide enough to allow minor adjustments in the alignment of the qualifying project so as to avoid sensitive features or to accommodate potential engineering constraints but narrow enough to allow detailed study.
Study corridor means a contiguous area (but not to exceed one-mile) in width within the project area where alternative routes may be considered for further studyStakeholder means any Non-Federal entity, any non-governmental organization, Affected Landowner, or other person potentially affected by a proposed qualifying project.
Applicability to other projects.
(a) Following the procedures set out in this section, the Director may determine that a proposed electric transmission facility that does not meet the description of a qualifying project under paragraph (1) of the definition in § 900.2 is a qualifying project under paragraph (2) of the definition.
(b) A requestor seeking DOE assistance under this part for a proposed electric transmission facility that does not meet the description of a qualifying project under paragraph (1) of the definition in § 900.2 must file a request for coordination with the Director. The request must contain:
(1) The legal name of the requester; its principal place of business; and the name, title, and mailing address of the person or persons to whom communications concerning the request for coordination are to be addressed;
(2) A concise description of the proposed facility sufficient to explain its scope and purpose;
(3) A list of anticipated relevant Federal entities involved in the proposed facility; and
(4) A list of anticipated relevant non-Federal entities involved in the proposed facility, including any agency serial or docket numbers for pending applications.
(c) Not later than 30 calendar days after the date that the Director receives a request under this section, the Director, in consultation with the relevant Federal entities, will determine if the proposed electric transmission facility is a qualifying project under this part and will notify the project proponent in writing of one of the following:
(1) If accepted, that the proposed facility is a qualifying project and the project proponent must submit an initiation request as set forth under § 900.5; or
(2) If not accepted, that the proposed facility is not a qualifying project, a justification of that determination, and an indication that the project proponent must follow the procedures of each relevant Federal entity that has jurisdiction over the proposed facility without DOE performing a coordinating function.
(d) In making the determination whether a proposed electric transmission facility is a qualifying project, the Director may consider:
(1) Whether the proposed facility would benefit from CITAP Program coordination;
(2) Whether the proposed facility would result in reduced congestion costs for generating and delivering energy;
(3) Whether the proposed facility would result in mitigation of weather and variable generation uncertainty;
(4) Whether the proposed facility would result in an enhanced diversity of supply; and
(5) Any other relevant factors, as determined by the Director.
(e) For a proposed facility that is seeking a construction or modification permit pursuant to section 216(b) of the Federal Power Act, DOE may only consider a request for assistance under this section if the request under paragraph (b) of this section is consistent with Delegation Order No. S1-DEL-FERC-2006 or any similar, subsequent delegation that the Secretary may order.
(f) At the discretion of the MOU signatory agencies, this section may be applied to a proposed electric transmission facility proposed for authorization under section 8(p) of the Outer Continental Shelf Lands Act, if the proposed authorization is independent of any generation project.
(g) This section does not apply to:
(1) A proposed electric transmission facility proposed to be authorized under section 8(p) of the Outer Continental Shelf Lands Act in conjunction with a generation project; or
(2) A proposed electric transmission facility wholly located within the Electric Reliability Council of Texas interconnection.