§ 200.308 - Revision of budget and program plans.  


Latest version.
  • § 200.308 Revision of budget and program plans.

    (a) Approved budget in general. The approved budget for the Federal award summarizes the financial aspects of the project or program as approved during the Federal award process. It may include either the Federal share and non-Federal share (see definition for Federal share in § 200.1) or only the Federal share, depending upon Federal awarding agency requirements. The budget and program plans include considerations for performance and program evaluation purposes whenever required in accordance with the terms and conditions of the award.

    (b) Recipients are required to report deviations from budget or project scope or objective, and request prior approvals from Federal awarding agencies

    as determined by the Federal agency or pass-through entity.

    (b) Deviations from approved budget. The recipient or subrecipient must report deviations from the approved budget, project or program scope, or objective(s) in accordance with § 200.329. The recipient or subrecipient must request prior approvals from the Federal agency or pass-through entity for budget and program plan revisions , in accordance with this section.

    (c) For non-construction Federal awards, recipients must request prior approvals from Federal awarding agencies for the following program or Requesting approval for budget revisions. When requesting approval for budget revisions, the recipient or subrecipient must use the same format for budget information that was used in their application, except if the Federal agency has approved an alternative format. Alternative formats may include the use of electronic systems, email, or other agency-approved mechanisms that document the request.

    (d) Federal agency or pass-through entity review. The Federal agency or pass-through entity must review the request for budget or program plan revision and should notify the recipient or subrecipient whether the revisions have been approved within 30 days of receipt of the request. The Federal agency or pass-through entity must inform the recipient or subrecipient in writing when a decision can be expected if more than 30 days is required for a review.

    (e) Limitation on other prior approval requirements. Unless specified in this guidance, the Federal agency must not impose additional prior approval requirements without OMB approval. See also §§ 200.102 and 200.407.

    (f) Revisions Requiring Prior Approval. A recipient or subrecipient must request prior written approval from the Federal agency or pass-through entity for the following program and budget-related reasons:

    (1) Change in the scope or the objective of the project or program (even if there is no associated budget revision requiring prior written approval).

    (2) Change in

    a key person specified in the application or the

    key personnel (including employees and contractors) that are identified by name or position in the Federal award.

    (3) The disengagement from

    the

    a project for more than three months, or a 25 percent reduction in time and effort devoted to the

    project

    Federal award over the course of the period of performance, by the approved project director or principal investigator.

    (4) The inclusion, unless waived by the Federal

    awarding

    agency, of costs that require prior approval in accordance with subpart E

    of this part

    as applicable.

    (5) The transfer of funds budgeted for participant support costs to other budget categories

    of expense

    .

    (6)

    Unless described

    Subaward activities not proposed in the application and

    funded

    approved in the

    approved Federal awards, the subawarding, transferring or contracting out of any work under a Federal award, including fixed amount subawards as described in § 200.333. This provision does not apply to the acquisition of supplies, material, equipment or general support

    Federal award. A change of subrecipient only requires prior approval if the Federal agency or pass-through entity includes the requirement in the terms and conditions of the Federal award. In general, a Federal agency or pass-through entity should not require prior approval of a change of subrecipient unless the inclusion was a determining factor in the merit review or eligibility process. This requirement does not apply to procurement transactions for goods and services.

    (7) Changes in the total approved cost-sharing

    or matching provided by the non-Federal entity

    amount.

    (8) The need arises for additional Federal funds to complete the project.

    (d) No other prior approval requirements for specific items may be imposed unless an exception has been approved by OMB. See also §§ 200.102 and 200.407.

    (e) Except for requirements listed in paragraphs (c

    Before providing approval, the Federal agency must ensure that adequate funds are available to avoid a violation of the Antideficiency Act.

    (9) Transferring funds between the construction and non-construction work under a Federal award.

    (10) A no-cost extension (meaning, an extension of time that does not require the obligation of additional Federal funds) of the period of performance, other than any one-time extension authorized by the Federal agency in accordance with paragraph (g)(2). All requests for no-cost extensions should be submitted at least 10 calendar days before the conclusion of the period of performance. The Federal agency may approve multiple no-cost extensions under a Federal award if not prohibited by Federal statute or regulation.

    (g) Waiver of certain prior approvals. Except for the requirements listed in paragraphs (f)(1) through (

    8

    10)

    of this section

    , the Federal

    awarding

    agency is authorized

    , at its option,

    to waive other cost-related and administrative prior written

    approvals

    approval requirements contained in subparts D and E

    of this part

    . Such waivers may include authorizing recipients to do

    any

    one or more of the following:

    (1) Pre-award costs. Incur project costs 90 calendar days before the Federal

    awarding agency makes the Federal

    award date. Expenses incurred more than 90 calendar days

    pre-

    before the Federal award date require prior approval of the Federal

    awarding

    agency. All costs incurred before the Federal

    awarding agency makes the Federal

    award date are at the recipient's own risk (

    i.e.

    for example, the Federal

    awarding

    agency is not required to reimburse such costs if

    for any reason

    the recipient does not receive

    a

    the Federal award or if the Federal award is less than anticipated and inadequate to cover such costs). Pre-award costs must be charged to the initial budget period of the Federal award unless otherwise specified by the Federal agency. See also § 200.458.

    (2) One-time extensions. Initiate a one-time extension of the period of performance by up to 12 months unless one or more of the conditions outlined in paragraphs (

    e

    g)(2)(i) through (iii) of this section apply.

    For

    Prior approval is not required if a recipient is authorized in the terms and conditions of the Federal award to initiate a one-time

    extensions

    extension. However, the recipient must notify the Federal

    awarding

    agency in writing with the supporting

    reasons

    justification and a revised period of performance at least 10 calendar days before the

    end

    conclusion of the period of performance

    specified in the Federal award

    .

    This

    A one-time extension

    must

    may not be exercised

    merely

    for the sole purpose of using unobligated balances.

    Extensions require explicit prior Federal awarding agency approval

    This paragraph does not preclude the Federal agency from approving further no-cost extensions to the Federal award. One-time extensions require prior approval from the Federal agency when:

    (i) The terms and conditions of the Federal award prohibit the extension

    .

    ;

    (ii) The extension requires additional Federal funds

    .

    ; or

    (iii) The extension involves any change in the approved

    objectives or

    scope of the project.

    (3) Unobligated Balances. Carry forward unobligated balances to subsequent budget periods.

    (

    4) For

    h) Prior approvals for research awards. The prior approval requirements for the actions described in paragraph (g) of this section are automatically waived for Federal awards that support research

    ,

    unless stipulated in the Federal

    awarding agency provides otherwise in

    agency's regulations or terms and conditions of the Federal award

    or in

    . However, one-time extensions require the Federal

    awarding

    agency's

    regulations, the prior approval requirements described in this paragraph (e) are automatically waived (i.e., recipients need not obtain such prior approvals) unless

    prior approval when one of the conditions

    included e

    g)(2) of this section applies.

    (

    f) The Federal awarding agency may, at its option, restrict the transfer of funds among direct cost categories or programs, functions and activities for Federal awards in which the Federal share of the project exceeds the simplified acquisition threshold and the cumulative amount of such transfers exceeds or is expected to exceed 10 percent of the total budget as last approved by the Federal awarding agency. The Federal awarding agency cannot permit a transfer

    i) Transfer of funds. The Federal agency must not permit a transfer of funds that would cause any Federal appropriation to be used for purposes other than those consistent with the appropriation.

    (g) All other changes to non-construction budgets, except for the changes described in paragraph (c) of this section, do not require prior approval (see also § 200.407).

    (h) For construction Federal awards, the recipient must request prior written approval promptly from the Federal awarding agency for budget revisions whenever paragraph (h)(1), (2), or (3) of this section applies:

    (1) The revision results from changes in the scope or the objective of the project or program.

    (2) The need arises for additional Federal funds to complete the project.

    (3) A revision is desired which involves specific costs for which prior written approval requirements may be imposed consistent with applicable OMB cost principles listed in subpart E.

    (4) No other prior approval requirements for budget revisions may be imposed unless an exception has been approved by OMB.

    (5) When a Federal awarding agency makes a Federal award that provides support for construction and non-construction work, the Federal awarding agency may require the recipient to obtain prior approval from the Federal awarding agency before making any fund or budget transfers between the two types of work supported.

    (i) When requesting approval for budget revisions, the recipient must use the same format for budget information that was used in the application, unless the Federal awarding agency indicates a letter of request suffices.

    (j) Within 30 calendar days from the date of receipt of the request for budget revisions, the Federal awarding agency must review the request and notify the recipient whether the budget revisions have been approved. If the revision is still under consideration at the end of 30 calendar days, the Federal awarding agency must inform the recipient in writing of the date when the recipient may expect the decision

    The Federal agency may also, at its option, restrict the transfer of funds among direct cost categories (for example, personnel, travel, and supplies) or programs, functions, and activities when:

    (1) The Federal share of the Federal award exceeds the simplified acquisition threshold; and

    (2) The cumulative amount of a transfer exceeds or is expected to exceed 10 percent of the total budget, including cost share, as last approved by the Federal agency.