§ 84.86 - Termination and enforcement.  


Latest version.
  • (a) Termination. (1) Awards may be terminated in whole or in part only if paragraphs (a)(1)(i), (a)(1)(ii), or (a)(1)(iii) of this section apply.

    (i) By HUD, if a recipient materially fails to comply with the terms and conditions of an award.

    (ii) By HUD with the consent of the recipient, in which case the two parties shall agree upon the termination conditions, including the effective date and, in the case of partial termination, the portion to be terminated.

    (iii) By the recipient upon sending to HUD written notification setting forth the reasons for such termination, the effective date, and, in the case of partial termination, the portion to be terminated. However, if HUD determines in the case of partial termination that the reduced or modified portion of the grant will not accomplish the purposes for which the grant was made, it may terminate the grant in its entirety under either paragraphs (a)(1)(i) or (a)(1)(ii) of this section.

    (2) If costs are allowed under an award, the responsibilities of the recipient referred to in §84.87(a)(1), including those for property management as applicable, shall be considered in the termination of the award, and provision shall be made for continuing responsibilities of the recipient after termination, as appropriate.

    (3) If costs are allowed, the cost principles in §84.27 apply, even though the award was made on a lump-sum basis. Alternatively, a termination settlement may be reached by prorating the grant amount against the percentage of completion or by some other method as determined by the Grant Officer, as long as the method used results in an equitable settlement to both parties.

    (b) Enforcement—(1) Remedies for noncompliance. If a recipient materially fails to comply with the terms and conditions of an award, whether stated in a Federal statute, regulation, assurance, application, or notice of award, HUD may, in addition to imposing any of the special conditions outlined in §84.14, take one or more of the following actions, as appropriate in the circumstances.

    (i) Temporarily withhold cash payments pending correction of the deficiency by the recipient or more severe enforcement action by HUD.

    (ii) Wholly or partly suspend or terminate the current award.

    (iii) Withhold further awards for the project or program.

    (iv) Take other remedies that may be legally available.

    (2) Hearings and appeals. In taking an enforcement action, HUD shall provide the recipient an opportunity for hearing, appeal, or other administrative proceeding to which the recipient is entitled under any statute or regulation applicable to the action involved.

    (3) Effects of suspension and termination. Costs of a recipient resulting from obligations incurred by the recipient during a suspension or after termination of an award are not allowable unless HUD expressly authorizes them in the notice of suspension or termination or subsequently. Other recipient costs during suspension or after termination which are necessary and not reasonably avoidable are allowable if paragraphs (b)(3)(i) and (b)(3)(ii) of this section apply.

    (i) The costs result from obligations which were properly incurred by the recipient before the effective date of suspension or termination, are not in anticipation of it, and in the case of a termination, are noncancellable.

    (ii) The costs would be allowable if the award were not suspended or expired normally at the end of the funding period in which the termination takes effect.

    (4) Relationship to debarment and suspension. The enforcement remedies identified in this section, including suspension and termination, do not preclude a recipient from being subject to debarment and suspension under HUD's regulations at 2 CFR part 2424 (see §84.13).

    [59 FR 47011, Sept. 13, 1994, as amended at 72 FR 73492, Dec. 27, 2007]