§ 950.604 - Allocation of funds under section 14.  


Latest version.
  • (a) General. This section describes the process for allocating modernization funds to the aggregate of IHAs and PHAs participating in the CIAP (i.e., agencies that own or operate fewer than 250 units), and to individual IHAs and PHAs participating in the CGP (i.e., agencies that own or operate 250 or more units). The program requirements governing PHA participation in the CIAP and CGP are contained in 24 CFR part 968.

    (b) Set-aside for emergencies and disasters. For each FFY, HUD shall reserve from amounts approved in the appropriation act for grants under this part and part 968 of this title, an amount not to exceed $75 million (which shall include unused reserve amounts carried over from previous FFYs), which shall be made available to IHAs and PHAs for modernization needs resulting from natural and other disasters, and from emergencies. HUD shall replenish this reserve at the beginning of each FFY. Any unused funds from previous years may remain in the reserve until allocated. The requirements governing the reserve for disasters and emergencies and the procedures by which an IHA may request such funds are set forth in § 950.606.

    (c) Set-aside for credits for mod troubled PHAs under 24 CFR part 968, subpart C. (1) General. After deducting amounts for the reserve for natural and other disasters and for emergencies under paragraph (b) of this section, HUD shall set aside no more than five percent of the remaining amount for the purpose of providing credits to PHAs under 24 CFR part 968, subpart C that were formerly designated as mod troubled agencies under the Public Housing Management Assessment Program (PHMAP) at 24 CFR part 901. The purpose of this set-aside is to compensate such PHAs for amounts previously withheld by HUD because of their prior designation as a mod troubled agency.

    (2) Nonapplicability to IHAs. Since the PHMAP performance indicators under 24 CFR part 901 do not apply to IHAs, these agencies cannot be deemed mod troubled for purposes of the CGP. Hence, IHAs are not subject to any reduction in funding under section 14(k)(5)(a) of the Act, nor do they participate in the set-aside of credits established under paragraph (c)(1) of this section.

    (d) Formula allocation based on relative needs. After determining the amounts to be reserved under paragraphs (b) and (c) of this section, HUD shall allocate the amount remaining pursuant to the formula set forth in paragraphs (e) and (f) of this section, which are designed to measure the relative backlog and accrual needs of IHAs and PHAs.

    (e) Allocation for backlog needs. HUD shall allocate half of the formula amount under paragraph (d) of this section based on the relative backlog needs of IHAs and PHAs, as follows:

    (1) Determination of backlog need. (i) Statistically reliable data. Where HUD determines that the data concerning the categories of backlog need identified under paragraph (e)(4) of this section are statistically reliable for individual IHAs and PHAs with 250 or more units, or the aggregate of IHAs and PHAs with fewer than 250 units not participating in the formula funding portion of the modernization program, it will base its allocation on direct estimates of the statutory categories of backlog need, based on the most recently available, statistically reliable data.

    (ii) Statistically reliable data are unavailable. Where HUD determines that statistically reliable data concerning the categories of backlog need identified under paragraph (e)(4) of this section are not available for individual IHAs and PHAs with 250 or more units, it will base its allocation of funds under this section on estimates of the categories of backlog need using:

    (A) The most recently available data on the categories of backlog need under paragraph (e)(4) of this section;

    (B) Objectively measurable data concerning the following IHA or PHA, community, and development characteristics:

    (1) The average number of bedrooms in the units in a development (Weighted at 2858.7);

    (2) The proportion of units in a development available for occupancy by very large families (Weighted at 7295.7);

    (3) The extent to which units for families are in high-rise elevator developments (Weighted at 5555.8);

    (4) The age of the developments, as determined by the DOFA date (date of full availability). In the case of acquired developments, HUD will use the DOFA date unless the IHA provides HUD with the actual date of construction, in which case HUD will use the age of the development (or for scattered sites, the average age of all the buildings), subject to a 50 year cap. (Weighted at 206.5);

    (5) In the case of a large agency, the number of units with 2 or more bedrooms (Weighted at .433);

    (6) The cost of rehabilitating property in the area (Weighted at 27544.3);

    (7) For family developments, the extent of population decline in the unit of general local government determined on the basis of the 1970 and 1980 censuses (Weighted at 759.5); and

    (C) An equation constant of 1412.9.

    (2) Calibration of backlog need for developments constructed prior to 1985. The estimated backlog need, as determined under either paragraphs (e)(1)(i) or (e)(1)(ii) of this section, shall be adjusted upward for developments constructed prior to 1985 by a constant ratio of 1.5 to more accurately reflect the costs of modernizing the categories of backlog need under paragraph (e)(4) of this section, for the Indian housing stock as of 1991.

    (3) Deduction for prior modernization. HUD shall deduct from the estimated backlog need, as determined under either paragraphs (e)(1)(i) or (e)(1)(ii) of this section, amounts previously provided to an IHA or PHA for modernization, using one of the following methods:

    (i) Standard deduction for prior CIAP and MROP. HUD shall deduct 60 percent of the CIAP funds made available on an IHA-wide or PHA-wide basis from FFY 1984 to 1991, and 40 percent of the funds made available on a development-specific basis for the Major Reconstruction of Obsolete Projects (MROP) (not to exceed the estimated formula need for the development), subject to a maximum 50 percent deduction of an IHA's or PHA's total need for backlog funding;

    (ii) Newly constructed units. Units with a DOFA date of October 1, 1991 or thereafter will be considered to have a zero backlog; or

    (iii) Acquired developments. Developments acquired by an IHA with major rehabilitation, with a DOFA date of October 1, 1991 or thereafter, will be considered to have a zero backlog.

    (4) Categories of backlog need. The most recently available data to be used under either paragraphs (e)(1)(i) or (e)(1)(ii) of this section shall pertain to the following categories of backlog need:

    (i) Backlog of needed repairs and replacements of existing physical systems in Indian housing developments;

    (ii) Items that shall be added to developments to meet HUD's modernization standards under § 950.610, and State, local and tribal codes; and

    (iii) Items that are necessary or highly desirable for the long-term viability of a development, in accordance with HUD's modernization standards.

    (f) Allocation for accrual needs. HUD shall allocate the other half remaining under the formula allocation under paragraph (d) of this section based upon the relative accrual needs of IHAs and PHAs, determined as follows:

    (1) Statistically reliable data. If HUD determines that statistically reliable data are available concerning the categories of need identified under paragraph (f)(3) of this section for individual IHAs and PHAs with 250 or more units and for the aggregate of IHAs and PHAs with fewer than 250 units, it shall base its allocation of assistance under this section on the needs that are estimated to have accrued since the date of the last objective measurement of backlog needs under paragraph (e)(1)(i) of this section; or

    (2) Statistically reliable data are unavailable. If HUD determines that statistically reliable data concerning the categories of need identified under paragraph (f)(3) of this section are not available for individual IHAs and PHAs with 250 or more units, it shall base its allocation of assistance under this section on estimates of accrued need using:

    (i) The most recently available data on the categories of backlog need under paragraph (f)(3) of this section;

    (ii) Objectively measurable data concerning the following IHA or PHA, community, and development characteristics:

    (A) The average number of bedrooms in the units in a development (Weighted at 100.1);

    (B) The proportion of units in a development available for occupancy by very large families (Weighted at 356.7);

    (C) The age of the developments (Weighted at 10.4);

    (D) The extent to which the buildings in developments of an agency average fewer than 5 units (Weighted at 87.1.);

    (E) The cost of rehabilitating property in the area (Weighted at 679.1);

    (F) The total number of units of each IHA or PHA that owns or operates 250 or more units (Weighted at .0144); and

    (iii) An equation constant of 602.1.

    (3) Categories of need. The data to be provided under either paragraph (f)(1) or (f)(2) of this section shall pertain to the following categories of need:

    (i) Backlog of needed repairs and replacements of existing physical systems in Indian housing developments; and

    (ii) Items that shall be added to developments to meet HUD's modernization standards under § 950.610, and State, local, and tribal codes.

    (g) Allocation for CIAP. The formula amount determined under paragraphs (e) and (f) of this section for IHAs and PHAs with fewer than 250 units shall be allocated to IHAs in accordance with the requirements under the undesignated heading of this subpart “Comprehensive Improvement Assistance Program” (CIAP) and to PHAs in accordance with the requirements of 24 CFR part 968, subpart B.

    (h) Allocation for CGP. The formula amount determined under paragraphs (e) and (f) of this section for IHAs with 250 or more units shall be allocated in accordance with the requirements under the undesignated heading of this subpart “Comprehensive Grant Program,” and for PHAs in accordance with the requirements of 24 CFR part 968, subpart C. An IHA that is eligible to receive a grant under the CGP may appeal the amount of its formula allocation under this section in accordance with the requirements set forth in § 950.650. An IHA that is eligible to receive modernization funds under the CGP because it owns or operates 250 or more units, is disqualified from receiving assistance under the CIAP under this part.

    (i) Use of formula allocation. Any amounts allocated to an IHA under paragraphs (e) and (f) of this section may be used for any eligible activity under this subpart, notwithstanding that the allocation amount is determined by allocating half based on the relative backlog needs and half based on the relative accrual needs of IHAs and PHAs.

    (j) Calculation of number of units. For purposes of determining under this section the number of units owned or operated by an IHA or PHA, and the relative modernization needs of IHAs and PHAs, HUD shall count as one unit each existing rental, Mutual Help, and section 23 Bond-Financed unit under the ACC, except that it shall count as one-fourth of a unit each existing unit under the Turnkey III program. New development units that are added to an IHA's or PHA's inventory will be added to the overall unit count so long as they are under ACC amendment and have reached DOFA by the first day in the FFY in which the formula is being run. Any increase in units (reaching DOFA and under ACC amendment) as of the beginning of the FFY shall result in an adjustment upwards in the number of units under the formula. New units reaching DOFA after this date will be counted for formula purposes as of the following FFY.

    (k) Demolition, disposition, and conversion of units. (1) General. Where an existing unit under an ACC is demolished, disposed of, or converted into a larger or smaller unit, HUD shall not adjust the amount the IHA or PHA receives under the formula, unless more than one percent of the units are affected on a cumulative basis. Where more than one percent of the existing units are demolished, disposed of, or converted, HUD shall reduce the formula amount for the IHA or PHA over a 3-year period to reflect removal of the units from the ACC.

    (2) Determination of one percent cap. In determining whether more than one percent of the units are affected on a cumulative basis, HUD will compare the units eligible for funding in the initial year under formula funding with the number of units eligible for funding for the current year under formula funding, and shall base its calculations on the following:

    (i) Increases in the number of units resulting from the conversion of existing units will be added to the overall unit count so long as they are under ACC amendment by the first day in the FFY in which the formula is being run;

    (ii) Units that are lost as a result of demolition, disposition, or conversion shall not be offset against units subsequently added to an IHA's or PHA's inventory;

    (iii) For purposes of calculating the number of converted units, HUD shall regard the converted size of the unit as the appropriate unit count (e.g., a unit that originally was counted as one unit under paragraph (j) of this section, but which later was converted into two units, shall be counted as two units under the ACC).

    (3) Phased-in reduction of units. (i) Reduction less than one percent. If HUD determines that the reduction in units under paragraph (k)(2) of this section is less than one percent, the IHA or PHA will be funded as though no change had occurred.

    (ii) Reduction greater than one percent. If HUD determines that the reduction in units under paragraph (k)(2) of this section is greater than one percent, the number of units on which formula funding is based will be the number of units reported as eligible for funding for the current program, plus two-thirds of the difference between the initial year and the current year in the first year, plus one-third of the difference in the second year, and at the level of the current year in the third year.

    (iii) Exception. A unit that is conveyed under the Mutual Help or Turnkey III programs will result in an automatic (rather than a phased-in) reduction in the unit count. Paid-off Mutual Help or Turnkey III units continue to be counted until they are conveyed.

    (4) Subsequent reductions in unit count. (i) Once an IHA's or PHA's unit count has been fully reduced under paragraph (k)(3)(ii) of this section to reflect the new number of units under the ACC, this new number of units will serve as the base for purposes of calculating whether there has been a one percent reduction in units on a cumulative basis.