Deepwater Operations Plan (DWOP) |
§ 250.288 - When and how must I submit the Conceptual Plan?
Latest version.
-
§ 250.288 When and how must I submit the Conceptual Plan?
You must submit four copies, or one hard copy and one electronic version, of the Conceptual Plan to the Regional Director after you have decided on the general concept(s) for development and before you begin engineering design of the well safety control system or subsea production systems to be used after well completion.