Code of Federal Regulations (Last Updated: July 5, 2024) |
Title 30 - Mineral Resources |
Chapter II - Bureau of Safety and Environmental Enforcement, Department of the Interior |
SubChapter B - Offshore |
Part 285 - [Reserved] |
Subpart F - Plans and Information Requirements |
Activities Under an Approved COP |
§ 285.632 - What documents must I submit before I may construct and install facilities under my approved COP?
Latest version.
-
§ 285.632 What documents must I submit before I may construct and install facilities under my approved COP?
(a) You must submit to BSEE the documents listed in the following table:
Document: Requirements are found in: (1) Facility Design Report § 285.701 (2) Fabrication and Installation Report § 285.702 (b) You must submit your safety management system, as required by § 285.810.
(c) These activities must fall within the scope of your approved COP. If they do not fall within the scope of your approved COP, you will be required to submit a revision to your COP, under 30 CFR 585.634, for BOEM approval before commencing the activity.