§ 585.631 - When must I initiate activities under an approved COP?
Latest version.
-
§ 585.631 When must I initiate activities under an approved COP?
After your COP is approved, you must commence construction by the date given in the construction schedule required by § 585.626(b)(21), and included as a part of your approved COP, unless BOEM approves a deviation from your schedule.