Code of Federal Regulations (Last Updated: November 8, 2024) |
Title 40 - Protection of Environment |
Chapter I—Environmental Protection Agency |
SubChapter C—Air Programs |
Part 63 - National Emission Standards for Hazardous Air Pollutants for Source Categories |
Subpart AAAAA - National Emission Standards for Hazardous Air Pollutants for Lime Manufacturing Plants |
Table 10 to Subpart AAAAA of Part 63 - —Applicability of General Provisions to Subpart AAAAA
Latest version.
-
Table 10 to Subpart AAAAA of Part 63—XXX
Link to an amendment published atCross Reference
63—Applicability of General Provisions to Subpart AAAAA
[As required in § 63.7140, you must comply with the applicable General Provisions requirements according to the following table.]
Citation Summary of
requirementAm I subject to this requirement? Explanations § 63.1(a)(1) through (4) Applicability Yes § 63.1(a)(5) No § 63.1(a)(6) Applicability Yes § 63.1(a)(7) through (9) No § 63.1(a)(10) through (14) Applicability Yes § 63.1(b)(1) Initial Applicability Determination Yes §§ 63.7081 and 63.7142 specify additional applicability determination requirements. § 63.1(b)(2) No § 63.1(b)(3) Initial Applicability Determination Yes § 63.1(c)(1) Applicability After Standard Established Yes § 63.1(c)(2) Permit Requirements No Area sources not subject to this subpart, except all sources must make initial applicability determination. § 63.1(c)(3) and (4) No § 63.1(c)(5) Area Source Becomes Major Yes § 63.1(c)(6) Reclassification Yes § 63.1(d) No § 63.1(e) Applicability of Permit Program Yes § 63.2 Definitions Yes Additional definitions in § 63.7143. § 63.3(a) through (c) Units and Abbreviations Yes § 63.4(a)(1) and (2) Prohibited Activities Yes § 63.4(a)(3) through (5) No § 63.4(b) and (c) Circumvention, Severability Yes § 63.5(a)(1) and (2) Construction/Reconstruction Yes § 63.5(b)(1) Compliance Dates Yes § 63.5(b)(2) No § 63.5(b)(3) and (4) Construction Approval, Applicability Yes § 63.5(b)(5) No § 63.5(b)(6) Applicability Yes § 63.5(c) No § 63.5(d)(1) through (4) Approval of Construction/Reconstruction Yes § 63.5(e) Approval of Construction/Reconstruction Yes § 63.5(f)(1) and (2) Approval of Construction/Reconstruction Yes § 63.6(a) Compliance for Standards and Maintenance Yes § 63.6(b)(1) through (5) Compliance Dates Yes § 63.6(b)(6) No § 63.6(b)(7) Compliance Dates Yes § 63.6(c)(1) and (2) Compliance Dates Yes § 63.6(c)(3) and (4) No § 63.6(c)(5) Compliance Dates Yes § 63.6(d) No § 63.6(e)(1)(i) General Duty to Minimize Emissions Yes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)On and after the relevant compliance date for your source as specified in § 63.7083(e), see § 63.7100 for general duty requirement. § 63.6(e)(1)(ii) Requirement to Correct Malfunctions ASAP Yes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)§ 63.6(e)(1)(iii) Operation and Maintenance Requirements Yes § 63.6(e)(2) No [Reserved]. § 63.6(e)(3) Startup, Shutdown Malfunction Plan Yes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)On and after the relevant compliance date for your source as specified in § 63.7083(e), the OM&M plan must address periods of startup and shutdown. See § 63.7100(d). § 63.6(f)(1) SSM exemption No See § 63.7100. For periods of startup and shutdown, see § 63.7090(c). § 63.6(f)(2) and (3) Methods for Determining Compliance Yes § 63.6(g)(1) through (3) Alternative Standard Yes § 63.6(h)(1) SSM exemption No See § 63.7100. For periods of startup and shutdown, see § 63.7090(c). § 63.6(h)(2) Methods for Determining Compliance Yes § 63.6(h)(3) No § 63.6(h)(4) through (h)(5)(i) Opacity/VE Standards Yes This requirement only applies to opacity and VE performance checks required in table 5 to this subpart. § 63.6(h)(5)(ii) and (iii) Opacity/VE Standards No Test durations are specified in this subpart; this subpart takes precedence. § 63.6(h)(5)(iv) Opacity/VE Standards No § 63.6(h)(5)(v) Opacity/VE Standards Yes § 63.6(h)(6) Opacity/VE Standards Yes § 63.6(h)(7) COM Use Yes § 63.6(h)(8) Compliance with Opacity and VE Yes § 63.6(h)(9) Adjustment of Opacity Limit Yes § 63.6(i)(1) through (14) Extension of Compliance Yes § 63.6(i)(15) No § 63.6(i)(16) Extension of Compliance Yes § 63.6(j) Exemption from Compliance Yes § 63.7(a)(1) through (3) Performance Testing Requirements Yes § 63.7110 specifies deadlines; § 63.7112 has additional specific requirements. § 63.7(b) Notification Yes § 63.7(c) Quality Assurance/Test Plan Yes § 63.7(d) Testing Facilities Yes § 63.7(e)(1) Conduct of Tests Yes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)On and after the relevant compliance date for your source as specified in § 63.7083(e), see § 63.7112(b). § 63.7(e)(2) through (4) Conduct of Tests Yes § 63.7(f) Alternative Test Method Yes § 63.7(g) Data Analysis Yes § 63.7(h) Waiver of Tests Yes § 63.8(a)(1) Monitoring Requirements Yes See § 63.7113. § 63.8(a)(2) Monitoring Yes § 63.8(a)(3) No § 63.8(a)(4) Monitoring No Flares not applicable. § 63.8(b)(1) through (3) Conduct of Monitoring Yes § 63.8(c)(1)(i) CMS Operation/Maintenance Yes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)On and after the relevant compliance date for your source as specified in § 63.7083(e), see § 63.7100 for OM&M requirements. § 63.8(c)(1)(ii) CMS Spare Parts Yes § 63.8(c)(1)(iii) Requirement to Develop SSM Plan for CMS Yes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)On and after the relevant compliance date for your source as specified in § 63.7083(e), no longer required. § 63.8(c)(2) and (3) CMS Operation/Maintenance Yes § 63.8(c)(4) CMS Requirements No See § 63.7121. § 63.8(c)(4)(i) and (ii) Cycle Time for COM and CEMS Yes No CEMS are required under this subpart; see § 63.7113 for CPMS requirements. § 63.8(c)(5) Minimum COM procedures Yes COM not required. § 63.8(c)(6) CMS Requirements No See § 63.7113. § 63.8(c)(7) and (8) CMS Requirements Yes § 63.8(d)(1) and (2) Quality Control Yes See also § 63.7113. § 63.8(d)(3) Quality Control Yes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)§ 63.8(e) Performance Evaluation for CMS Yes See also § 63.7113. § 63.8(f)(1) through (5) Alternative Monitoring Method Yes § 63.8(f)(6) Alternative to Relative Accuracy Test for CEMS No No CEMS required in this subpart. § 63.8(g)(1) through (5) Data Reduction; Data That Cannot Be Used No See data reduction requirements in §§ 63.7120 and 63.7121. § 63.9(a) Notification Requirements Yes See § 63.7130. § 63.9(b) Initial Notifications Yes § 63.9(c) Request for Compliance Extension Yes § 63.9(d) New Source Notification for Special Compliance Requirements Yes § 63.9(e) Notification of Performance Test Yes § 63.9(f) Notification of VE/Opacity Test Yes This requirement only applies to opacity and VE performance tests required in table 5 to this subpart. Notification not required for VE/opacity test under table 7 to this subpart. § 63.9(g) Additional CMS Notifications No Not required for operating parameter monitoring. § 63.9(h)(1) through (3) Notification of Compliance Status Yes § 63.9(h)(4) No § 63.9(h)(5) and (6) Notification of Compliance Status Yes § 63.9(i) Adjustment of Deadlines Yes § 63.9(j) Change in Previous Information Yes § 63.9(k) Electronic reporting procedures Yes Only as specified in § 63.9(j). § 63.10(a) Recordkeeping/Reporting General Requirements Yes See §§ 63.7131 through 63.7133. § 63.10(b)(1) Records Yes § 63.10(b)(2)(i) Recordkeeping of Occurrence and Duration of Startups and Shutdowns Yes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)§ 63.10(b)(2)(ii) Recordkeeping of Failures to Meet a Standard Yes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)On and after the relevant compliance date for your source as specified in § 63.7083(e), see § 63.7132 for recordkeeping of (1) date, time and duration; (2) listing of affected source or equipment, and an estimate of the quantity of each regulated pollutant emitted over the standard; and (3) actions to minimize emissions and correct the failure. § 63.10(b)(2)(iii) Maintenance Records Yes § 63.10(b)(2)(iv) and (v) Actions Taken to Minimize Emissions During SSM Yes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)On and after the relevant compliance date for your source as specified in § 63.7083(e), see § 63.7100 for OM&M requirements. § 63.10(b)(2)(vi) through (xii) Recordkeeping for CMS Yes § 63.10(b)(2)(xiii) Records for Relative Accuracy Test No § 63.10(b)(2)(xiv) Records for Notification Yes § 63.10(b)(3) Applicability Determinations Yes § 63.10(c) Additional CMS Recordkeeping No See § 63.7132. § 63.10(d)(1) General Reporting Requirements Yes § 63.10(d)(2) Performance Test Results Yes § 63.10(d)(3) Opacity or VE Observations Yes For the periodic monitoring requirements in table 7 to this subpart, report according to § 63.10(d)(3) only if VE observed and subsequent visual opacity test is required. § 63.10(d)(4) Progress Reports Yes § 63.10(d)(5)(i) Periodic Startup, Shutdown, Malfunction Reports Yes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)On and after the relevant compliance date for your source as specified in § 63.7083(e), see § 63.7131 for malfunction reporting requirements. § 63.10(d)(5)(ii) Immediate Startup, Shutdown, Malfunction Reports Yes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)§ 63.10(e) Additional CMS Reports No See specific requirements in this subpart, see § 63.7131. § 63.10(f) Waiver for Recordkeeping/Reporting Yes § 63.11(a) and (b) Control Device and Work Practice Requirements No Flares not applicable. § 63.12(a) through (c) State Authority and Delegations Yes § 63.13(a) through (c) State/Regional Addresses Yes § 63.14(a) and (b) Incorporation by Reference No § 63.15(a) and (b) Availability of Information and Confidentiality Yes § 63.16 Performance Track Provisions Yes [89 FR 57766, July 16, 2024
.]