Table 1 to Subpart EEEEEE of Part 63 - —Applicability of General Provisions to This Subpart


Latest version.
  • Table 1 to Subpart EEEEEE of Part 63—Applicability of General Provisions to Subpart EEEEEE This Subpart

    As required in § 63.11150(a), you must comply with the requirements of the NESHAP General Provisions (subpart A of this part) as shown in the following table.

    Citation Subject Applies to this subpart EEEEEE? Explanation
    § 63.1(a)(1) , (a)(2), (a)(3), (a)(through (4), (a)(6), and (a)(10) -through (a)(12), (b)(1) , and (b)(3), (c)(1), (c)(2), and (c)(5), (e)ApplicabilityYes.
    § 63.1(a)(5) , and (a)(7) -through (a)(9), (b)(2), (c)(3) , and (c)(4), (d)ReservedNo.
    § 63.2DefinitionsYes.
    § 63.3Units and AbbreviationsYes.
    § 63.4Prohibited Activities and CircumventionYes.
    § 63.5Preconstruction Review and Notification RequirementsNo.
    § 63.6(a), (b)(1) -through (b)(5) , and (b)(7), (c)(1), (c)(2), and (c)(5)Compliance with Standards and Maintenance Requirements—Applicability and Compliance DatesYes.
    § 63.6(e)(1)(i)Operation and Maintenance RequirementsYes/NoOperation and maintenance requirements do not apply to existing sources except that the startup, shutdown, and malfunction requirements in Requirements—general duty to minimize emissionsYes before November 12, 2024
    No on or after November 12, 2024
    See §§ 63.11147(c) and 63.11148(f) for the general duty to minimize emissions at all times at existing sources. See § 63.11149(c)(3) for the general duty to minimize emissions at all times at new sources.
    § 63.6(e)(1)(ii)Requirement to correct malfunctions as soon as practicable.Yes before November 12, 2024
    No on or after November 12, 2024
    Malfunctions are no longer exempt.
    § 63.6(e)(3) are allowed as an alternative to the rule 1)(iii)Yes.
    § 63.6(e)(3)Startup, Shutdown, and Manufacturing PlanYes before November 12, 2024
    No on or after November 12, 2024
    The requirements for emergency situations . Operation and maintenance requirements apply to new sources except that the rule requirements for emergency situations are allowed as an alternative to the startup, shutdown, and malfunction requirements in for existing sources are contained in §§ 63.11147(c)(5) and 63.11148(f)(5). See § 63.11149(d) for the emergency requirements for new sources.
    § 63.6(f)(1)Compliance with Nonopacity Emission StandardsYes before November 12, 2024
    No on or after November 12, 2024
    Emission standards apply at all times. Some requirements of § 63.6(ef)(31) are no longer applicable.
    § 63.6(f), ((2) through (3)Yes.
    § 63.6(g), (i), (j)Compliance with Nonopacity Emission StandardsYes.
    § 63.6(h)(1)Compliance with Opacity and Visible Emission StandardsYes before November 12, 2024
    No on or after November 12, 2024
    Requirements apply to new sources but not existing sources. Emission standards apply at all times. Some requirements of § 63.6(h)(1) are no longer applicable.
    § 63.6(b)(6), (c)(3) , and (c)(4), (d), (e)(2), (e)(3)(ii), (h)(2)(ii), (h)(3), (h)(5)(iv), (i)(15)ReservedNo.
    § 63.6(h)(12) -through (h)(4), (h)(5)(i) -(h)(5)(through (iii), (h)(6) -through (h)(9)Yes/No.Requirements apply to new sources but not existing sources.
    § 63.7(a), (e)(2) through (4), (f), (g), (h)Performance Testing RequirementsYes.
    § 63.7(e)(1)Performance Testing RequirementsNoSee § 63.11148(e) for performance testing requirements.
    § 63.7(b), (c)Yes/NoNotification of performance tests and quality assurance program apply to new sources but not existing sources.
    § 63.8(a)(1) , and (a)(2), (b), (c)(1)(ii), (c)(2) through (8), (f), (g)Monitoring RequirementsYes.
    § 63.8(c)(1)(i) and (iii)General Duty and SSM Plan Requirements for Continuous Monitoring SystemsYes before November 12, 2024.
    No on or after November 12, 2024.
    § 63.8(a)(3)ReservedNo.
    § 63.8(a)(4)NoSubpart EEEEEE This subpart does not require flares.
    § 63.8(d)(1) and (2), (e)Quality ControlYes/NoRequirements for quality control program and performance evaluations apply to new sources but not existing sources.
    § 63.98(a), d)(3)Written Procedures for Continuous Monitoring SystemsYes before November 12, 2024
    No on or after November 12, 2024
    Requirements for quality control program and performance evaluations apply to new sources but not existing sources. See § 63.11149(b)(1)3).
    § 63.9(a), (b)(21), (b2), and (5), (c), (d), (h)(1) -through (h)(3), (h)(5), and (h)(6), (i), (j)Notification RequirementsYes.
    § 63.9(b)(3), (h)(4)ReservedNo.
    § 63.9(b)(4), (f)No.
    § 63.9(e), (g)Yes/NoNotification requirements for performance test and use of continuous monitoring systems apply to new sources but not existing sources.
    § 63.9(k)Electronic submission of notifications or reportsYes.
    § 63.10(a), (b)(1), (d)(1), (d)(2), and (d)(4), (d)(5), (f)Recordkeeping and Reporting RequirementsYes/NoRecordkeeping requirements apply to new sources but not existing sources.
    § 63.10(b)(2)(iii) and (vi) through (xiv), (b)(3), (c)(1), (c)(5) -through (c)(8), and (c)(10) -through (c14)(15), (e)(1) , and (e)(2)Yes/NoRecordkeeping requirements apply to new sources but not existing sources.
    § 63.10(cb)(2)-((i) through (ii) and (iv) through (v)General Recordkeeping Requirements and Actions to Minimize Emissions During Startup, Shutdown, and MalfunctionYes before November 12, 2024
    No on or after November 12, 2024
    Recordkeeping requirements apply to new sources but not existing sources. See § 63.11149(c)(4).
    Startup, Shutdown, and Malfunction are no longer exempt from emission standards. See § 63.11148(g).
    § 63.10(c)(2) and (4) and (9)ReservedNo.
    § 63.10(c)(15)Use of Startup, Shutdown, and Malfunction PlanFor new sources, Yes before November 12, 2024
    No on or after November 12, 2024
    Recordkeeping requirements apply to new sources but not existing sources.
    Startup, Shutdown, and Malfunction Plans are no longer required.
    § 63.10(d)(3), (e)(4)NoReporting requirements apply to new sources but not existing sources.
    § 63.10(d)(5)Startup, Shutdown, and Malfunction ReportingFor new sources, Yes before November 12, 2024
    No on or after November 12, 2024
    Reporting requirements apply to new sources but not existing sources. See §§ 63.11147(e), 63.11148(h), 63.11149(e)(2).
    § 63.10(e)(3)Yes/NoReporting requirements apply to new sources but not existing sources.
    § 63.11Control Device RequirementsNoSubpart EEEEEE This subpart does not require flares.
    § 63.12State Authorities and DelegationsYes.
    § 63.13AddressesYes.
    § 63.14Incorporations by ReferenceYes.
    § 63.15Availability of Information and ConfidentialityYes.
    § 63.16Performance Track ProvisionsYes.

    [89 FR 41722, May 13, 2024]