    To comply with Inspection or monitoring requirement Frequency of inspection or monitoring Method
    Tanks:
    63.133(b)(1) Inspect fixed roof and all openings for leaks Initially Semi-annually Visual.
    63.133(c) Inspect floating roof in accordance with §§ 63.120 (a)(2) and (a)(3) See § 63.120 (a)(2) and (a)(3) Visual.
    63.133(d) Measure floating roof seal gaps in accordance with §§ 63.120 (b)(2)(i) through (b)(4) See § 63.120 (b)(2)(i) through (b)(4).
    - Primary seal gaps Once every 5 years Initially Annually
    - Secondary seal gaps
    63.133(f) 63.133(g) Inspect wastewater tank for control equipment failures and improper work practices Initially Semi-annually Visual.
    Surface impoundments:
    63.134(b)(1) Inspect cover and all openings for leaks Initially Semi-annually Visual.
    63.134(c) Inspect surface impoundment for control equipment failures and improper work practices Initially Semi-annually Visual.
    Containers:
    63.135(b)(1), 63.135(b)(2) (ii) Inspect cover and all openings for leaks Initially Semi-annually Visual.
    63.135(d)(1) Inspect enclosure and all openings for leaks Initially Semi-annually Visual.
    63.135(e) Inspect container for control equipment failures and improper work practices Initially Semi-annually Visual.
    Individual Drain Systemsa:
    63.136(b)(1) Inspect cover and all openings to ensure there are no gaps, cracks, or holes Initially Semi-annually Visual.
    63.136(c) Inspect individual drain system for control equipment failures and improper work practices Initially Semi-annually Visual.
    63.136(e)(1) Verify that sufficient water is present to properly maintain integrity of water seals Initially Semi-annually Visual.
    63.136(e)(2), 63.136(f)(1) Inspect all drains using tightly-fitted caps or plugs to ensure caps and plugs are in place and properly installed Initially Semi-annually Visual.
    63.136(f)(2) Inspect all junction boxes to ensure covers are in place and have no visible gaps, cracks, or holes Initially Semi-annually Visual or smoke test or other means as specified.
    63.136(f)(3) Inspect unburied portion of all sewer lines for cracks and gaps Initially Semi-annually Visual.
    Oil-water separators:
    63.137(b)(1) Inspect fixed roof and all openings for leaks Initially Semi-annually Visual.
    63.137(c) Measure floating roof seal gaps in accordance with 40 CFR 60.696(d)(1) Initiallyb See 40 CFR 60.696(d)(1).
    - Primary seal gaps Once every 5 years
    63.137(c) - Secondary seal gaps Initiallyb Annually
    63.137(d) Inspect oil-water separator for control equipment failures and improper work practices Initially Semi-annually Visual.