Table 10 to Subpart HHHHH of Part 63 - Applicability of General Provisions to This Subpart  


Latest version.
  • Table 10 to Subpart HHHHH of Part 63 - Applicability of General Provisions to This Subpart

    As specified in § 63.8095, the parts of the general provisions that apply to you are shown in the following table:

    Table 10 to Subpart HHHHH of Part 63 - Applicability of General Provisions to This Subpart

    Citation Subject Explanation
    § 63.1 Applicability Yes.
    § 63.2 Definitions Yes.
    § 63.3 Units and Abbreviations Yes.
    § 63.4 Prohibited Activities Yes.
    § 63.5 Construction/Reconstruction Yes.
    § 63.6(a) Applicability Yes.
    § 63.6(b)(1)-(4) Compliance Dates for New and Reconstructed sources Yes.
    § 63.6(b)(5) Notification Yes.
    § 63.6(b)(6) [Reserved]
    § 63.6(b)(7) Compliance Dates for New and Reconstructed Area Sources That Become Major Yes.
    § 63.6(c)(1)-(2) Compliance Dates for Existing Sources Yes.
    § 63.6(c)(3)-(4) [Reserved]
    § 63.6(c)(5) Compliance Dates for Existing Area Sources That Become Major Yes.
    § 63.6(d) [Reserved]
    § 63.6(e)(1)(i) General Duty to Minimize Emissions Yes, before the compliance date specified in § 63.7995(e). No, on and after the compliance date specified in § 63.7995(e). See § 63.8000(e) for the general duty requirement.
    § 63.6(e)(1)(ii) Requirement to Correct Malfunctions as Soon as Possible Yes, before the compliance date specified in § 63.7995(e). No, on and after the compliance date specified in § 63.7995(e).
    § 63.6(e)(1)(iii)-(2) Operation and Maintenance Yes.
    § 63.6(e)(3) SSM Plan Yes, before the compliance date specified in § 63.7995(e). No, on and after the compliance date specified in § 63.7995(e).
    § 63.6(f)(1) Compliance with Non-Opacity Standards Except During SSM No. See § 63.8000(a).
    § 63.6(f)(2)-(3) Methods for Determining Compliance Yes.
    § 63.6(g)(1)-(3) Alternative Standard Yes.
    § 63.6(h)(1) Compliance with Opacity/Visible Emission (VE) Standards Except During SSM No. See § 63.8000(a).
    § 63.6(h)(2)-(9) Opacity/VE Standards Only for flares for which Method 22 of 40 CFR part 60, appendix A-7, observations are required as part of a flare compliance assessment.
    § 63.6(i)(1)-(14) Compliance Extension Yes.
    § 63.6(j) Presidential Compliance Exemption Yes.
    § 63.7(a)(1)-(2) Performance Test Dates Yes, except substitute 150 days for 180 days.
    § 63.7(a)(3)-(4) CAA Section 114 Authority, Force Majeure Yes, and these paragraphs also apply to flare compliance assessments as specified under § 63.997(b)(2).
    § 63.7(b)(1) Notification of Performance Test Yes.
    § 63.7(b)(2) Notification of Rescheduling Yes.
    § 63.7(c) Quality Assurance/Test Plan Yes, except the test plan must be submitted with the notification of the performance test if the control device controls process vessels.
    § 63.7(d) Testing Facilities Yes.
    § 63.7(e)(1) Conditions for Conducting Performance Tests Yes, before the compliance date specified in § 63.7995(e), except that performance tests for process vessels must be conducted under worst-case conditions as specified in § 63.8005. No, on and after the compliance date specified in § 63.7995(e). See § 63.8005(d).
    § 63.7(e)(2) Conditions for Conducting Performance Tests Yes.
    § 63.7(e)(3) Test Run Duration Yes.
    § 63.7(f) Alternative Test Method Yes.
    § 63.7(g) Performance Test Data Analysis Yes.
    § 63.7(h) Waiver of Tests Yes.
    § 63.8(a)(1) Applicability of Monitoring Requirements Yes.
    § 63.8(a)(2) Performance Specifications Yes.
    § 63.8(a)(3) [Reserved]
    § 63.8(a)(4) Monitoring with Flares Yes.
    § 63.8(b)(1) Monitoring Yes.
    § 63.8(b)(2)-(3) Multiple Effluents and Multiple Monitoring Systems Yes.
    § 63.8(c)(1) Monitoring System Operation and Maintenance Yes.
    § 63.8(c)(1)(i) Maintain and operate CMS Yes, before the compliance date specified in § 63.7995(e). No, on and after the compliance date specified in § 63.7995(e). See § 63.8000(e) for the general duty to maintain and operate each CMS.
    § 63.8(c)(1)(ii) Routine repairs Yes.
    § 63.8(c)(1)(iii) Requirement to develop SSM plan for CMS Yes, before the compliance date specified in § 63.7995(e). No, on and after the compliance date specified in § 63.7995(e).
    § 63.8(c)(2)-(3) Monitoring System Installation Yes.
    § 63.8(c)(4) Requirements Only for CEMS; requirements for CPMS are specified in referenced subpart SS of this part. This subpart does not contain requirements for continuous opacity monitoring systems (COMS).
    § 63.8(c)(4)(i) CMS Requirements No. This subpart does not require COMS.
    § 63.8(c)(4)(ii) CMS requirements Yes.
    § 63.8(c)(5) COMS Minimum Procedures No. This subpart does not contain opacity or VE limits.
    § 63.8(c)(6) CMS Requirements Only for CEMS; requirements for CPMS are specified in referenced subpart SS of this part.
    § 63.8(c)(7)-(8) CMS Requirements Only for CEMS. Requirements for CPMS are specified in referenced subpart SS of this part.
    § 63.8(d)(1)-(2) CMS Quality Control Only for CEMS; requirements for CPMS are specified in referenced subpart SS of this part.
    § 63.8(d)(3) Written procedures for CMS Yes, before the compliance date specified in § 63.7995(e). No, on and after the compliance date specified in § 63.7995(e). See § 63.8000(d)(8).
    § 63.8(e) CMS Performance Evaluation Section 63.8(e)(6)(ii) does not apply because this subpart does not require COMS. Other sections apply only for CEMS; requirements for CPMS are specified in referenced subpart SS of this part.
    § 63.8(f)(1)-(5) Alternative Monitoring Method Yes, except you may also request approval using the precompliance report.
    § 63.8(f)(6) Alternative to Relative Accuracy Test Only for CEMS.
    § 63.8(g)(1)-(4) Data Reduction Only when using CEMS, except § 63.8(g)(2) does not apply because data reduction requirements for CEMS are specified in § 63.8000(d)(4)(iv).
    The requirements for COMS do not apply because this subpart has no opacity or VE limits.
    § 63.8(g)(5) Data Reduction No. Requirements for CEMS are specified in § 63.8000(d)(4). Requirements for CPMS are specified in referenced subpart SS of this part.
    § 63.9(a) Notification Requirements Yes.
    § 63.9(b)(1)-(5) Initial Notifications Yes.
    § 63.9(c) Request for Compliance Extension Yes.
    § 63.9(d) Notification of Special Compliance Requirements for New Source Yes.
    § 63.9(e) Notification of Performance Test Yes.
    § 63.9(f) Notification of VE/Opacity Test No. This subpart does not contain opacity or VE limits.
    § 63.9(g) Additional Notifications When Using CMS Only for CEMS; requirements for CPMS are specified in referenced subpart SS of this part.
    § 63.9(h)(1)-(6) Notification of Compliance Status Yes, except this subpart has no opacity or VE limits, and § 63.9(h)(2) does not apply because § 63.8075(d) specifies the required contents and due date of the notification of compliance status report.
    § 63.9(i) Adjustment of Submittal Deadlines Yes.
    § 63.9(j) Change in previous information Yes, for change in major source status, otherwise § 63.8075(e)(8) specifies reporting requirements for process changes.
    § 63.9(k) Electronic reporting procedures Yes, as specified in § 63.9(j).
    § 63.10(a) Recordkeeping/Reporting Yes.
    § 63.10(b)(1) Recordkeeping/Reporting Yes.
    § 63.10(b)(2)(i)-(ii) Records related to SSM No. Before the compliance date specified in § 63.7995(e), see § 63.998(c)(1)(ii)(D) through (G) and (d)(3) for recordkeeping requirements for periods of SSM. On and after the compliance date specified in § 63.7995(e), see § 63.8080(i).
    § 63.10(b)(2)(iii) Records related to maintenance of air pollution control equipment Yes.
    § 63.10(b)(2)(iv)-(v) Records related to SSM Yes, before the compliance date specified in § 63.7995(e). No, on and after the compliance date specified in § 63.7995(e).
    § 63.10(b)(2)(vi), (x), and (xi) CMS Records Only for CEMS; requirements for CPMS are specified in referenced subpart SS of this part.
    § 63.10(b)(2)(vii)-(ix) Records Yes.
    § 63.10(b)(2)(xii) Records Yes.
    § 63.10(b)(2)(xiii) Records Yes.
    § 63.10(b)(2)(xiv) Records Yes.
    § 63.10(b)(3) Records Yes.
    § 63.10(c)(1)-(6), (9)-(14) Records Only for CEMS; requirements for CPMS are specified in referenced subpart SS of this part.
    § 63.10(c)(7)-(8), (15) Records No. Recordkeeping requirements are specified in § 63.8080.
    § 63.10(d)(1) General Reporting Requirements Yes.
    § 63.10(d)(2) Report of Performance Test Results Yes.
    § 63.10(d)(3) Reporting Opacity or VE Observations No. This subpart does not contain opacity or VE limits.
    § 63.10(d)(4) Progress Reports Yes.
    § 63.10(d)(5)(i) SSM Reports No. Before the compliance date specified in § 63.7995(e), see § 63.8075(e)(5) and (6) for the SSM reporting requirements. On and after the compliance date specified in § 63.7995(e), these requirements no longer apply.
    § 63.10(d)(5)(ii) Immediate SSM reports No.
    § 63.10(e)(1)-(2) Additional CMS Reports Only for CEMS, but § 63.10(e)(2)(ii) does not apply because this subpart does not require COMS.
    § 63.10(e)(3) Reports No. Reporting requirements are specified in § 63.8075.
    § 63.10(e)(3)(i)-(iii) Reports No. Reporting requirements are specified in § 63.8075.
    § 63.10(e)(3)(iv)-(v) Excess Emissions Reports No. Reporting requirements are specified in § 63.8075.
    § 63.10(e)(3)(vi-viii) Excess Emissions Report and Summary Report No. Reporting requirements are specified in § 63.8075.
    § 63.10(e)(4) Reporting COMS data No. This subpart does not contain opacity or VE limits.
    § 63.10(f) Waiver for Recordkeeping/Reporting Yes.
    § 63.11 Control and work practice requirements Yes.
    § 63.12 Delegation Yes.
    § 63.13 Addresses Yes.
    § 63.14 Incorporation by Reference Yes.
    § 63.15 Availability of Information Yes.

    [85 FR 49749, Aug. 14, 2020, as amended at 85 FR 73914, Nov. 19, 2020]