§ 62.15040 - What are the requirements for meeting increments of progress and achieving final compliance?  


Latest version.
  • § 62.15040 What are the requirements for meeting increments of progress and achieving final compliance?

    (a) Class I units. If you plan to achieve compliance more than 1 year following the effective date of this subpart and a permit modification is not required, or more than 1 year following the date of issuance of a revised construction or operation permit if a permit modification is required, you must meet five increments of progress:

    (1) Submit a final control plan.

    (2) Submit a notification of retrofit contract award.

    (3) Initiate onsite construction.

    (4) Complete onsite construction.

    (5) Achieve final compliance.

    (b) Class II units. If you plan to achieve compliance more than 1 year following the effective date of this subpart and a permit modification is not required, or more than 1 year following the date of issuance of a revised construction or operation permit if a permit modification is required, you must meet two increments of progress:

    (1) Submit a final control plan.

    (2) Achieve final compliance.