§ 1515.404-472 - Other methods.  


Latest version.
  • 1515.404-472 Other methods.

    (a) Contracting officers may use methods other than those prescribed in 1515.404-470 for establishing profit or fee objectives under the following types of contracts and circumstances:

    (1) Architect-engineering contracts;

    (2) Personal service contracts;

    (3) Management contracts, e.g., for maintenance or operation of Government facilities;

    (4) Termination settlements;

    (5) Services under labor-hour and time and material contracts which provide for payment on an hourly, daily, or monthly basis, and where the contractor's contribution constitutes the furnishing of personnel.

    (6) Construction contracts; and

    (7) Cost-plus-award-fee contracts.

    (b) Generally, it is expected that such methods will:

    (1) Provide the contracting officer with a technique that will ensure consideration of the relative value of the appropriate profit factors described under “Profit Factors,” in FAR 15.404-4(d) and