§ 215.971-3 - Contract type risk and working capital adjustment.  


Latest version.
  • (a) Description. The contract type risk factor focuses on the degree of cost risk accepted by the contractor under varying contract types. The working capital adjustment is an adjustment added to the profit objective for contract type risk. It only applies to fixed-price contracts that provide for progress payments. Though it uses a formula approach, it is not intended to be an exact calculation of the cost of working capital. Its purpose is to give general recognition to the contractor's cost of working capital under varying contract circumstances, financing policies, and the economic environment.

    (b) Determination. The following extract from the DD 1547 is annotated to explain the process.

    ItemContractor risk factorsAssigned valueBase (Item 18)Profit objective25 Contract Type Risk (1) (2) (3) Cost financedLength factorInterest rate26 Working Capital (4) (5) (6) (7) (8)

    (1) Select a value from the list of contract types in paragraph (c) of this subsection using the evaluation criteria in paragraph (d) of this subsection.

    (2) Insert the amount from Block 18, i.e., the total allowable costs excluding general and administrative expenses, independent research and development/bid proposal expenses, and facilities capital cost of money.

    (3) Multiply (1) by (2).

    (4) Only complete this Block when the prospective contract is a fixed-price contract containing provisions for progress payments.

    (5) Insert the amount computed per paragraph (e) of this subsection.

    (6) Insert the appropriate figure from paragraph (f) of this subsection.

    (7) Use the interest rate established by the Secretary of the Treasury (230.7101(a)). Do not use any other interest rate.

    (8) Multiply (5) by (6) by (7). This is the working capital adjustment. It shall not exceed 4 percent of the contract costs in Block 20.

    (c) Values: Normal and designated ranges.

    Contract typeNotesNormal value (percent)Designated range (percent)Firm fixed-price, no financing (1) 5 4 to 6.Firm fixed-price, with financing (2) 3 2 to 4.Fixed-price-incentive, no financing (1) 3 2 to 4.Fixed-price with redeterminable provision (3) Fixed-price-incentive, with financing (2) 1 0 to 2.Cost-plus-incentive-fee (4) 1 0 to 2.Cost-plus-fixed-fee (4) .5 0 to 1.Time and material contracts (including overhaul contracts priced on time and material basis) (5) .5 0 to 1.Labor-hour contracts (5) .5 0 to 1.Firm fixed-price-level-of-effort-term (5) .5 0 to 1.

    (1) No financing means that the contract either does not provide progress payments, or provides them only on a limited basis, such as financing of first articles. Do not compute a working capital adjustment.

    (2) With financing means progress payments. When progress payments are present, compute a working capital adjustment (Block 26).

    (3) For the purposes of assigning profit values, treat a fixed-price contract with redeterminable provisions as if it were a fixed-price-incentive contract with below normal conditions.

    (4) Cost-plus contracts shall not receive the working capital adjustment.

    (5) These types of contracts are considered cost-plus-fixed-fee contracts for the purposes of assigning profit values. They shall not receive the working capital adjustment in Block 26. However, they may receive higher than normal values within the designated range to the extent that portions of cost are fixed.

    (d) Evaluation criteria—(1) General. The contracting officer should consider elements that affect contract type risk such as—

    (i) Length of contract;

    (ii) Adequacy of cost data for projections;

    (iii) Economic environment;

    (iv) Nature and extent of subcontracted activity;

    (v) Protection provided to the contractor under contract provisions (e.g., economic price adjustment clauses);

    (vi) The ceilings and share lines contained in incentive provisions; and

    (vii) Risks associated with contracts for foreign military sales (FMS) which are not funded by U.S. appropriations.

    (2) Mandatory—The contracting officer shall assess the extent to which costs have been incurred prior to definitization of the contract action (see also 217.7404-6(a)). The assessment shall include any reduced contractor risk on both the contract before definitization and the remaining portion of the contract. When costs have been incurred prior to definitization, generally regard the contract type risk to be in the low end of the designated range. If a substantial portion of the costs have been incurred prior to definitization, the contracting officer may assign a value as low as 0%, regardless of contract type.

    (3) Above normal conditions. The contracting officer may assign a higher than normal value when there is substantial contract type risk. Indicators of this are—

    (i) Efforts where there is minimal cost history;

    (ii) Long-term contracts without provisions protecting the contractor, particularly when there is considerable economic uncertainty;

    (iii) Incentive provisions (e.g., cost and performance incentives) which place a high degree of risk on the contractor; or

    (iv) FMS sales (other than those under DoD cooperative logistics support arrangements or those made from U.S. Government inventories or stocks) where the contractor can demonstrate that there are substantial risks above those normally present in DoD contracts for similar items.

    (4) Below normal conditions. The contracting officer may assign a lower than normal value when the contract type risk is low. Indicators of this are—

    (i) Very mature product line with extensive cost history;

    (ii) Relatively short-term contracts;

    (iii) Contractual provisions which substantially reduce the contractor's risk; or

    (iv) Incentive provisions which place a low degree of risk on the contractor.

    (e) Costs financed. (1) Costs financed equal total costs multiplied by the portion (percent) of costs financed by the contractor.

    (2) Total costs equal Block 20 (i.e., all allowable costs, including general and administrative and independent research and development/bid and proposal, but excluding facilities capital cost of money), reduced as appropriate when—

    (i) The contractor has little cash investment (e.g., subcontractor progress payments liquidated late in period of performance);

    (ii) Some costs are covered by special financing provisions, such as advance payments; or

    (iii) The contract is multiyear and there are special funding arrangements.

    (3) The portion financed by the contractor is generally the portion not covered by progress payments, i.e., 100% minus the customary progress payment rate (FAR 32.501). For example, if a contractor receives progress payments at 75%, the portion financed by the contractor is 25%. On contracts that provide flexible progress payments (252.232-7003) or progress payments to small businesses, use the customary progress payment rate for large businesses.

    (f) Contract length factor. (1) This is the period of time that the contractor has a working capital investment in the contract. It—

    (i) Is based on the time necessary for the contractor to complete the substantive portion of the work;

    (ii) Is not necessarily the period of time between contract award and final delivery (or final payment), as periods of minimal effort should be excluded;

    (iii) Should not include periods of performance contained in option provisions; and

    (iv) Should not, for multiyear contracts, include periods of performance beyond that required to complete the initial program year's requirements.

    (2) The contracting officer—

    (i) Should use the following table to select the contract length factor;

    (ii) Should develop a weighted average contract length when the contract has multiple deliveries; and

    (iii) May use sampling techniques provided they produce a representative result.

    TablePeriod to perform substantive portion (in months)Contract length factor21 or less .4022 to 27 .6528 to 33 .9034 to 39 1.1540 to 45 1.4046 to 51 1.6552 to 57 1.9058 to 63 2.1564 to 69 2.4070 to 75 2.6576 or more 2.90

    (3) Example: A prospective contract has a performance period of 40 months with end items being delivered in the 34th, 36th, 38th, and 40th months of the contract. The average period is 37 months and the contract length factor is 1.15.