§ 243.105 - Availability of funds.  


Latest version.
  • (a)(i) 10 U.S.C. 2405 prohibits adjustments in price under a shipbuilding contract entered into after December 7, 1983, for a claim, request for equitable adjustment, or demand for payment under the contract, arising out of events occurring more than 18 months before submission of the claim, request, or demand.

    (ii) In accordance with 10 U.S.C. 983, do not provide funds by contract or contract modification, or make contract payments, to an institution of higher education that has a policy or practice of hindering Senior Reserve Officer Training Corps units or military recruiting on campus as described at 209.470.