§ 633.23 FTA review of PMPa project management plan.
Within 60 days of receipt of a project management plan, the Administrator will notify the recipient that:
(a) The plan is approved;
(b) The plan is disapproved, including the reasons for the disapproval;
(c) The plan will require modification, as specified, before approval; or
(d) The Administrator has not yet completed review of the plan, and state when it will be reviewed.