§ 1710.208 RUS criteria for approval of all load forecasts by power supply borrowers and by distribution borrowers required to maintain an approved load forecast on an ongoing basis.
All load forecasts submitted by power supply borrowers and by distribution borrowers required to maintain an approved load forecast must satisfy the following criteria:
(a) The borrower objectively analyzed all known relevant factors that influence the consumption of electricity and the known number of customers served at the time the study was developed;
(b) The borrower considered and identified all loads on its system of RE Act beneficiaries and non-RE Act beneficiaries;
(c) The borrower developed an adequate supporting database and analyzed a reasonable range of relevant assumptions and alternative futures;
(d) The borrower adopted methods and procedures in general use by the electric utility industry to develop its load forecast;
(e) The borrower used valid and verifiable analytical techniques and models;
(f) The borrower provided RUS with adequate documentation and assistance to allow for a thorough and independent review; and
(g) In the case of a power supply borrower required to maintain an approved load forecast on an ongoing basis, the borrower adequately coordinated the preparation of the load forecast work plan and load forecast with its member systems.
[65 FR 14786, Mar. 20, 2000, as amended at 84 FR 32611, July 9, 2019]