§ 3015.41 - General program income.  


Latest version.
  • (a) Applicability. This section applies to “general program income” as defined in Appendix A.

    (b) Use. (1) General program income shall be retained by the recipient and used in accordance with one or a combination of the alternatives in paragraphs (c), (d), and (e) of this section, as follows: The alternative in paragraph (c) may always be used by recipients and must be used if neither of the other two alternatives is permitted by the provisions of the grant award. The alternatives in paragraph (d) or (e) of this section may be used only if expressly permitted by the provisions of the grant award. In specifying alternatives that may be used, the provisions of the grant award may distinguish between income earned by the recipient and income earned by subrecipients and between the sources, kinds, or amounts of income.

    (2) The provisions of a subgrant award may restrict the use of general program income earned by the subrecipient to only one or some of the alternatives permitted by the provisions of the grant, but the alternative in paragraph (c) of this section shall always be permitted.

    (c) Deduction alternative. (1) Under this alternative, the income is used for allowable costs of the project or program. If there is a cost-sharing or matching requirement, costs supported by the income may not count toward satisfying that requirement. Therefore, the maximum percentage of Federal cost-sharing is applied to the net amount determined by deducting the income from total allowable costs and third party in-kind contributions. The income shall be used for current costs unless the awarding agency authorizes the income to be used in a later period.

    (2) To illustrate this alternative, assume a project in which the recipient incurs $100,000 of allowable costs and receives no third party in-kind contributions. If the recipient earns $10,000 in general program income and this alternative applies, that $10,000 must be deducted from the $100,000 before applying the maximum percentage of Federal cost-sharing. If that percentage is 90 percent, the most that could be paid to the recipient would therefore be $81,000 (90 percent times $90,000).

    (d) Cost-sharing or matching alternative. (1) Under this alternative, the income is used for allowable costs of the project or program but, in this case, the costs supported by the income may count toward satisfying a cost-sharing or matching requirement. Therefore, the maximum percentage of Federal cost-sharing is applied to total allowable costs and third party in-kind contributions. The income shall be used for current costs unless the awarding agency authorizes its use in a later period.

    (2) To illustrate this alternative, assume the same situation as in paragraph (c)(2) of this section. Under this alternative, the 90 percent maximum percentage of Federal cost-sharing would be applied to the full $100,000, and $90,000 could therefore be paid to the recipient.

    (e) Additional costs alternative. Under this alternative, the income is used for costs which are in addition to the allowable costs of the project or program but which nevertheless further the objectives of the Federal statute under which the grant was made. Provided that the costs supported by the income further the broad objectives of that statute, they need not be of a kind that would be permissible as charges to Federal funds. Examples of purposes for which the income may be used are:

    (1) Expanding the project or program.

    (2) Continuing the project or program after grant or subgrant support ends.

    (3) Supporting other projects or programs that further the broad objectives of the statute.

    (4) Obtaining equipment or other assets needed for the project or program or for other activities that further the statute's objectives.