2011-29935. KC Hydro LLC of New Hampshire; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications  

  • Start Preamble

    On August 8, 2011, KC Hydro LLC of New Hampshire filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act (FPA), proposing to study the feasibility of the Manchester Goffs Falls Dam Hydropower Project (Goffs Falls Dam Project or project) to be located on Great Cohas Brook, near the City of Manchester, Hillsborough County, New Hampshire. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land-disturbing activities or otherwise enter upon lands or waters owned by others without the owners' express permission.

    The proposed project would consist of the following: (1) The existing 150-foot-long, 19-foot-high Goffs Falls Dam, which is owned by the City of Manchester and includes a 75-foot-long spillway; (2) an existing 54 acre impoundment with 243 acre-feet of storage capacity at the spillway crest elevation; (3) a newly constructed powerhouse; (4) new electrical generating equipment with total hydraulic capacity of 246 cubic feet per second (cfs) and total installed generating capacity of between 0.265 megawatts (MW) to .585 MW; (5) a 260-foot-long to 1,060-foot-long penstock; (6) rehabilitated intake gate structure and trash racks; (7) a newly excavated 125-foot-long tailrace; (8) an approximately 150-foot-long to 750-foot-long transmission line; and (9) appurtenant facilities. The estimated annual generation of the Goffs Falls Dam Project would be between 0.85 gigawatt-hours (GWH) to 1.85 GWH.

    Applicant Contact: Ms. Kelly Sackheim, Principal, KC Hydro LLC of New Hampshire, 5096 Cocoa Palm Way, Fair Oaks, CA 95628; phone: (301) 401-5978.

    FERC Contact: John Ramer; phone: (202) 502-8969.

    Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Competing applications and notices of intent must meet the requirements of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site http://www.ferc.gov/​docs-filing/​efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at http://www.ferc.gov/​docs-filing/​ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at 1-(866) 208-3676, or for TTY, (202) 502-8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and seven copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426.

    More information about this project, including a copy of the application, can be viewed or printed on the “eLibrary” link of Commission's Web site at http://www.ferc.gov/​docs-filing/​elibrary.asp. Enter the docket number (P-14246-000) in the docket number field to access the document. For assistance, contact FERC Online Support.

    Start Signature

    Dated: November 14, 2011.

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    [FR Doc. 2011-29935 Filed 11-18-11; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Comments Received:
0 Comments
Published:
11/21/2011
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2011-29935
Pages:
71961-71961 (1 pages)
Docket Numbers:
Project No. 14246-000
PDF File:
2011-29935.pdf