DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Alaska Project Nos. 11597 and 11599]
Ketchikan Public Utilities (Whitman Lake and Connell Lake
Hydroelectric Projects); Notice of Scoping Meetings and Site Visits and
Soliciting Scoping Comments
February 11, 1999.
The Federal Energy Regulatory Commission (Commission) regulations
allow applicants to prepare their own Environmental Assessment (EA) for
hydropower projects and file it with the Commission along with their
license application as part of the applicant-prepared EA (APEA)
process. Ketchikan Public Utilities (KPU) received approval from the
Commission to prepare an EA for the proposed Whitman and Connell Lakes
Hydroelectric Projects, No. 11597 and No. 11599, respectively.
KPU will hold three scoping meetings, pursuant to the National
Environmental Policy Act (NEPA) of 1969, to identify the scope of
environmental issues that should be analyzed in the EA. At the scoping
meetings, KPU will: (1) summarize the environmental issues tentatively
identified for analysis in the EA: (2) outline any resources they
believe would not require a detailed analysis; (3) identify reasonable
alternatives to be addressed in the EA: (4) solicit from the meeting
participants all available information, especially quantitative data,
on the resources at issue; and (5) encourage statements from experts
and the public on issues that should be analyzed in the EA.
Scoping Meetings
The times and locations of the three scoping meetings are:
Agency Scoping Meetings
March 3, 1999
Whitman Lake, 8:30 AM to 11:30 AM, Ted Ferry Civic Center, 888
Venetia Avenue, Ketchikan, Alaska
March 3, 1999
Connell Lake, 1:00 PM to 4:00 PM, Ted Ferry Civic Center, 888
Venetia Avenue, Ketchikan, Alaska
Public Scoping Meeting
March 3, 1999
Whitman and Connell Lakes, 7:00 PM to 10:00 PM, Ted Ferry Civic
Center, 888 Venetia Avenue, Ketchikan, Alaska
All interested individuals, organizations, and agencies are invited
and encouraged to attend either or both meetings to assist in
identifying and clarifying the scope of environmental issues that
should be analyzed in the EA.
To help focus discussions at the meetings, KPU prepared and
distributed an Initial Stage Consultation Document (ISCD) and a Scoping
Document in January 1999. Copies of the ISCD and the Scoping Document
can be obtain by calling Mr. Don Thompson of Wescorp, KPU's agent at
(206) 275-1000. Copies of both documents will also be available at all
scoping meetings.
Site Visit
For those who intend to participate in scoping, KPU will also
conduct site visits to the proposed Whitman Lake and Connell Lake
projects on Thursday, March 4, 1999, if sufficient interest exists.
Those attending the site visit should arrange their own transportation
and meet at Connell Lake dam at 9:00 A.M. We will continue to Ward Cove
and the Whitman Lake hatchery by vehicle. From Whitman Creek, those who
wish may hike the 0.5 miles up the hatchery water supply pipe to
Whitman dam. Hikers may need to sign a waiver of liability. Because of
the remoteness and difficult access to the Whitman dam site, those
attending the site visit should be physically fit and must wear
appropriate clothing and footgear. Participants must provide their own
sack lunches. Those wishing to visit the project sites should notify
Mr. Don Thompson at (206) 275-1000, no later than Feb 28, 1999.
Meeting Procedures
The meetings will be conducted according to the procedures used at
Commission scoping meetings. Because this meeting will be a NEPA
scoping meeting under the APEA process, the Commission will not conduct
a NEPA scoping meeting after the application and draft EA are filed
with the Commission.
Both scoping meetings will be recorded by a stenographer or tape
recorder, and will become part of the formal record of the proceedings
for this project.
those who choose not to speak during the scoping meetings may
instead submit written comments on the project. Written comments must
be submitted by May 3, 1999, and should be mailed to: Mr. Don Thompson,
Wescorp, 3035 Island Crest Way, Suite 200, Mercer Island, Washington
98040. All correspondence should show one of the following captions on
the first page:
Scoping Comments, Whitman Lake Hydroelectric Project, Project No.
11597, Alaska, or
Scoping Comments, Connell Lake Hydroelectric Project, Project No.
11599, Alaska.
For further information please contact Don Thompson at (206) 275-
1000, or E-mail thompson@wescorp.net, or Carter Kruse of the Commission
at (202) 219-3023, or E-mail carter.kruse@ferc.fed.us.
Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 99-3899 Filed 2-17-99; 8:45 am]