[Federal Register Volume 64, Number 39 (Monday, March 1, 1999)]
[Notices]
[Pages 9986-9987]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 99-4880]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP99-213-000]
Reliant Energy Gas Transmission Company; Notice of Request Under
Blanket Authorization
February 23, 1999.
Take notice that on February 16, 1999, Reliant Energy Gas
Transmission Company (Reliant), formerly NorAm Gas Transmission
Company,\1\ 1111
[[Page 9987]]
Louisiana Street, Houston, Texas 77002-5231, filed in Docket No. CP99-
213-000 a request pursuant to Sections 157.205 and 157.211 of the
Commission's Regulations under the Natural Gas Act (18 CFR 157.205 and
157.211) for authorization to construct, and operate certain facilities
in Oklahoma. Reliant makes such request under its blanket certificate
issued in Docket Nos. CP82-384-000 and CP82-384-001 pursuant to Section
7 of the Natural Gas Act, all as more fully set forth in the request on
file with the Commission. The application may be viewed on the web at
www.ferc.us/online/rims.htm (call (202) 208-2222 for assistance).
---------------------------------------------------------------------------
\1\ Effective February 2, 1999, as part of a corporate name
change, NorAm Gas Transmission Company changed its name to Reliant
Energy Gas Transmission Company.
---------------------------------------------------------------------------
Reliant proposes to construct and operate a 2-inch delivery tap and
first-cut regulator to serve Reliant Energy Arkla (Arkla), a division
of Reliant Energy, Incorporated. It is stated that Arkla will construct
and operate a domestic meter setting, and that Reliant will own and
operate the delivery tap and first-cut regulator. The tap and regulator
is proposed to be installed on Reliant's Line 10 at pipeline station
637+24 in Stephens County, Oklahoma, at an estimated cost of $1,500.
Reliant states that all construction will occur on the existing right-
of-way. It is stated that Arkla has agreed to reimburse Reliant's
construction cost.
The estimated volumes to be delivered to this tap are 85 Dt
annually and 0.25 Dt on a peak day. It is averred that Reliant will
transport gas to Arkla and provide service under its tariff, and that
the volumes proposed for delivery are within Arkla's certificated
entitlements. Reliant further states that its tariff does not prohibit
the addition of new delivery points, and that Reliant has sufficient
capacity to accomplish the deliveries without detriment or disadvantage
to its other customers.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to section 157.205 of
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to
the request. If no protest is filed within the time allowed therefor,
the proposed activity shall be deemed to be authorized effective the
day after the time allowed for filing a protest. If a protest is filed
and not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to section 7 of the Natural Gas Act.
David P. Boergers,
Secretary.
[FR Doc. 99-4880 Filed 2-26-99; 8:45 am]
BILLING CODE 6717-01-M