99-7248. ANR Pipeline Company; Notice of Application  

  • [Federal Register Volume 64, Number 57 (Thursday, March 25, 1999)]
    [Notices]
    [Pages 14437-14438]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-7248]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Docket No. CP99-241-000]
    
    
    ANR Pipeline Company; Notice of Application
    
    March 19, 1999.
        Take notice that on March 8, 1999, as supplemented on March 19, 
    1999 ANR Pipeline Company (ANR), 500 Renaissance Center, Detroit, 
    Michigan 48243, filed an application pursuant to Section 7(c) of the 
    Natural Gas Act and Subpart A of Part 157 of the Commission's 
    regulations for a certificate of public convenience and necessity 
    authorizing ANR to construct, own, and operate an expansion of its 
    mainline facilities located west of its Joliet Compressor Station near 
    Joliet, Illinois, and to its mainline facilities located in eastern 
    Wisconsin (the Wisconsin Expansion Phase II facilities), all as more 
    fully set forth in the application which is on file with the Commission 
    and open to public inspection. This filing may be viewed on the web at 
    http://www.ferc.fed.us/online/rims.htm (call 202-208-2222 for 
    assistance).
        In order to meet increasing gas requirements in the State of 
    Wisconsin by November 1, 2000, ANR proposes to install certain 
    additional loop pipeline, compression, tie-line, and related facilities 
    on parts of its existing mainline facilities located in Wisconsin and 
    Illinois. ANR states that these facilities will increase its 
    transmission capacity into Wisconsin by up to 194,000 dekatherms per 
    day (194 
    Mdt/d), thereby enabling ANR to provide additional firm transportation 
    service for shippers from the ANR Joliet Hub to the Wisconsin market 
    area for ANR's system. In order to allow sufficient time for 
    construction of the proposed facilities and to meet the proposed in-
    service date, ANR requests that the Commission issue a preliminary 
    determination order by August 1, 1999 and a final order by no later 
    than February 1, 2000.
        Specifically, ANR seeks authority to construct: (1) approximately 
    3.0 miles of 42-inch diameter loop pipeline between milepost 801 and 
    milepost 804 along ANR's existing Michigan Leg South in Kendall County, 
    Illinois; (2) two 10,000 horsepower (hp) turbine compressor units to be 
    located at ANR's existing Woodstock Compressor Station in McHenry 
    County, Illinois; (3) one 1,500 hp turbine compressor unit to be 
    located at ANR's existing Weyauwega Compressor Station in Waupaca 
    County, Wisconsin; (4) 0.11 mile of 16-mile diameter pipeline 
    traversing from the Weyauwega Compressor Station to the Marinette 
    Junction tap site on ANR's existing 24-inch mainline; (5) one 1,500 hp 
    reciprocating compressor unit to be located at ANR's existing 
    Janesville Compressor Station in Rock County, Wisconsin; and (6) minor 
    related facilities. ANR states that these facilities are estimated to 
    cost $37,516,622.
        ANR states that the proposed 3.0 miles of 42-inch loopline along 
    the Michigan Leg South comprise an extension of a 15.9 mile segment of 
    certain Michigan Leg South loopline facilities that are currently 
    pending approval in Docket No. CP97-319-000 (ANR's ``SupplyLink'' 
    project). ANR contends that, although the design for the facilities 
    proposed herein includes this pending 15.9 mile loopline segment, the 
    facilities proposed here are required to serve different market needs 
    in Wisconsin, and are not part of Docket No. CP97-319-000. ANR presumes 
    that the SupplyLink facilities will be in service by the time ANR 
    places the
    
    [[Page 14438]]
    
    facilities proposed herein in service.\1\ In the event that the 
    SupplyLink loopline facilities are not available in the proposed time 
    frame, ANR states that it will be required to seek appropriate 
    authorizations from the Commission in this Docket to accommodate any 
    such delays.
    ---------------------------------------------------------------------------
    
        \1\ In Docket No. CP97-319-000, ANR proposed to place the 
    SupplyLink facilities in service by November 1, 1999.
    ---------------------------------------------------------------------------
    
        ANR proposes to charge the subscribing shippers rates that do not 
    exceed its currently effective Mainline Area rates under the provisions 
    of its rate schedules for firm service under its existing Second 
    Revised Volume No. 1 to its FERC Gas Tariff.
        ANR states that it recently conducted an open season. As a result, 
    a number of shippers expressed an interest in receiving firm 
    transportation service on ANR. According to ANR, these shippers desired 
    service from various existing and proposed pipeline interconnecting 
    points located near or within the vicinity of the ANR Joliet Hub near 
    Chicago, to markets located within the State of Wisconsin. ANR states 
    that those non-affiliated shippers have entered into executed precedent 
    agreements with ANR for new services that will utilize 94 Mdt/d of the 
    new capacity proposed herein. ANR is also proposing to construct as 
    part of this project 100 Mdt/d of presently uncommitted capacity that 
    will be used to serve, on a timely basis, the projected near term 
    demand growth in Wisconsin.
        According to ANR, a report recently published by the Wisconsin 
    energy Bureau, entitled Wisconsin Energy Statistics 1998, indicates 
    that, from 1987-1997, natural gas demand in Wisconsin grew at an annual 
    rate of approximately 2.6 percent. ANR states that it currently serves 
    firm peak day entitlements of approximately 2,200 Mdt/d, which equates 
    to an annual growth in peak day requirements on the ANR system of 
    approximately 57 Mdt per year. ANR contends that when this proposed 
    project is placed in service approximately two years from now, normal 
    growth patterns indicate that the 100 Mdt/d of additional capacity will 
    be required in Wisconsin.
        ANR submits that its proposal to build additional facilities to 
    meet projected growth in demand is in the overall public interest, and 
    is consistent with Commission precedent. According to ANR, additional 
    unsubscribed capacity for future growth as required has been previously 
    approved as part of an application to replace mainline facilities.\2\ 
    ANR further states that building all the necessary facilities as part 
    of one single project will also reduce the potential for repeated 
    environmental disturbance that might occur in the same location if the 
    facilities were constructed on a piecemeal basis as part of two 
    different projects.\3\
    ---------------------------------------------------------------------------
    
        \2\ ANR cites Columbia Gas Transmission Corporation, 72 FERC 
    para. 61,018 (1995).
        \3\ ANR cites Pacific Gas Transmission Company, 70 FERC para. 
    61,016 at 61,043 (1995).
    ---------------------------------------------------------------------------
    
        ANR argues that its expansion at the level proposed is justified, 
    given that during the last two winter heating seasons ANR has 
    experienced peak day throughout levels at or near capacity, despite the 
    fact that both winters were warmer than normal. ANR states that its 
    capacity expansion is an appropriate response to existing increased 
    demands on its system, and the 100 Mdt/d of additional capacity 
    represents only approximately four percent of ANR's current capacity 
    into the State of Wisconsin.
        ANR also states that it has also contacted shippers whose capacity, 
    if reduced or released permanently, would reduce the need for the 
    proposed new construction, in order to ensure that the new facilities 
    are appropriately sized. ANR states that no shipper offered to reduce 
    or release its capacity on a permanent basis.
        Any person desiring to be heard or to make any protest with 
    reference to said amendment should on or before April 9, 1999, file 
    with the Federal Energy Regulatory Commission, 888 First Street, N.E., 
    Washington, D.C. 20426, a motion to intervene or a protest in 
    accordance with the requirements of the Commission's Rules of Practice 
    and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the 
    Natural Gas Act (18 CFR 157.10). All protests filed with the Commission 
    will be considered by it in determining the appropriate action to be 
    taken but will not serve to make the protestants parties to the 
    proceeding. The Commission's rules require that protestors provide 
    copies of their protests to the party or parties directly involved. Any 
    person wishing to become a party to a proceeding or to participate as a 
    party in any hearing therein must file a motion to intervene in 
    accordance with the Commission's Rules.
        A person obtaining intervenor status will be placed on the service 
    list maintained by the Secretary of the Commission and will receive 
    copies of all documents filed by the applicant and every one of the 
    intervenors. An intervenor can file for rehearing of any Commission 
    order and can petition for court review of any such order. However, an 
    intervenor must submit copies of comments or any other filing it makes 
    with the Commission to every other intervenor in the proceeding, as 
    well as 14 copies with the Commission.
        A person does not have to intervene, however, in order to have 
    comments considered. A person, instead, may submit two copies of 
    comments to the Secretary of the Commission. Commenters will be placed 
    on the Commission's environmental mailing list, will receive copies of 
    environmental documents and will be able to participate in meetings 
    associated with the Commission's environmental review process. 
    Commenters will not be required to serve copies of filed documents on 
    all other parties. However, commenters will not receive copies of all 
    documents filed by other parties or issued by the Commission and will 
    not have the right to seek rehearing or appeal the Commission's final 
    order to a federal court.
        The Commission will consider all comments and concerns equally, 
    whether filed by commenters or those requesting intervenor status.
        Take further notice that, pursuant to the authority contained in 
    and subject to jurisdiction conferred upon the Federal Energy 
    Regulatory Commisson by Sections 7 and 15 of the Natural Gas Act and 
    the Commission's Rules of Practice and procedure, a hearing will be 
    held with further notice before the Commisson or its designee on this 
    application if no motion to intervene is filed within the time required 
    herein, or if the Commission on its own review of the matter finds that 
    permission and approval for the proposed certificate are required by 
    the public convenience and necessity. If a motion for leave to 
    intervene is timely filed, or if the Commission on its own motion 
    believes that a formal hearing is required, further notice of such 
    hearing will be duly given.
        Under the procedure herein provided for, unless otherwise advised, 
    it will be unnecessary for ANR to appear or be represented at the 
    hearing.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 99-7248 Filed 3-24-99 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
03/25/1999
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
99-7248
Pages:
14437-14438 (2 pages)
Docket Numbers:
Docket No. CP99-241-000
PDF File:
99-7248.pdf