99-7756. Wolf Creek Nuclear Operating Corporation; Wolf Creek Generating Station; Environmental Assessment and Finding of No Significant Impact  

  • [Federal Register Volume 64, Number 60 (Tuesday, March 30, 1999)]
    [Notices]
    [Pages 15186-15189]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-7756]
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket No. 50-482]
    
    
    Wolf Creek Nuclear Operating Corporation; Wolf Creek Generating 
    Station; Environmental Assessment and Finding of No Significant Impact
    
        The U.S. Nuclear Regulatory Commission (the Commission) is 
    considering the issuance of an amendment to Facility Operating License 
    No. NPF-42 that was issued to Wolf Creek Nuclear Operating Corporation 
    (the licensee) for operation of the Wolf Creek Generating Station 
    (WCGS), located in Coffey County, Kansas.
    
    Environmental Assessment
    
    Identification of the Proposed Action
    
        The proposed amendment will revise the current Technical 
    Specifications (CTS) for WCGS in their entirety based on the guidance 
    provided in NUREG-1431, ``Standard Technical Specifications, 
    Westinghouse Plants,'' Revision 1, dated April 1995, and in the 
    Commission's ``Final Policy Statement on Technical Specifications 
    Improvements for Nuclear Power Reactors,'' published on July 22, 1993 
    (58 FR 39132). The proposed action is in accordance with the licensee's 
    amendment request dated May 15, 1997, as supplemented by (1) the 
    letters in 1998 dated June 30, August 5, August 28, September 24, 
    October 16, October 23, November 24, December 2, December 17, and 
    December 21, and (2) the letters in 1999 dated February 4 and March 5 
    (3 letters).
    
    The Need for the Proposed Action
    
        It has been recognized that nuclear safety in all nuclear power 
    plants would benefit from an improvement and standardization of plant 
    Technical Specifications (TS). The NRC's ``Interim Policy Statement on 
    Technical Specification Improvements for Nuclear Power Plants,'' (52 FR 
    3788) contained proposed criteria for defining the scope of TS. Later, 
    the NRC's ``FinalPolicy Statement on Technical Specifications 
    Improvements for Nuclear Power Reactors,'' published on July 22, 1993 
    (58 FR 39132), incorporated lessons learned since publication of the 
    interim policy statement and formed the basis for revisions to 10 CFR 
    50.36, ``Technical Specifications.'' The ``Final Rule'' (60 FR 36953) 
    codified criteria for determining the content of TS. To facilitate the 
    development of standard TS for nuclear power reactors, each power 
    reactor vendor owners' group (OG) and the NRC staff developed standard 
    TS. For WCGS, the Improved Standard Technical Specifications (ISTS) are 
    in NUREG-1431. This document formed the basis for the WCGS Improved 
    Technical Specifications (ITS) conversion. The NRC Committee to Review 
    Generic Requirements (CRGR) reviewed the ISTS, made note of its safety 
    merits, and indicated its support of the conversion by operating plants 
    to the ISTS.
    
    Description of the Proposed Change
    
        The proposed changes to the CTS are based on NUREG-1431 and on 
    guidance provided by the Commission in its Final Policy Statement. The 
    objective of the changes is to completely rewrite, reformat, and 
    streamline the CTS (i.e., to convert the CTS to the ITS). Emphasis is 
    placed on human factors principles to improve clarity and understanding 
    of the TS. The Bases section of the ITS has been significantly expanded 
    to clarify and better explain the purpose and foundation of each 
    specification. In addition to NUREG-1431, portions of the CTS were also 
    used as the basis for the development of the WCGS ITS. Plant-specific 
    issues (e.g., unique design features, requirements, and operating 
    practices) were discussed with the licensee, and generic matters with 
    Westinghouse and other OGs.
        This conversion is a joint effort in concert with three other 
    utilities: Pacific Gas & Electric Company for Diablo Canyon Power 
    Plant, Units 1 and 2 (Docket Nos. 50-275 and 50-323); TU Electric for 
    Comanche Peak Steam Electric Station, Units 1 and 2 (Docket Nos. 50-445 
    and 50-446); and Union Electric Company for Callaway Plant, Unit 1 
    (Docket No. 50-483). It was a goal of the four utilities to make the 
    ITS for all the plants as similar as possible. This joint effort 
    includes a common methodology for the licensees in marking-up the CTS 
    and NUREG-1431 specifications, and the NUREG-1431 Bases, that has been 
    accepted by the staff.
        This common methodology is discussed at the end of Enclosure 2, 
    ``Mark-Up of Current TS''; Enclosure 5a, ``Mark-Up of NUREG-1431 
    Specifications''; and Enclosure 5b, ``Mark-Up of NUREG-1431 Bases'', 
    for each of the 14 separate ITS sections that were submitted with the 
    licensee's application. Each of the 14 ITS sections also includes the 
    following enclosures:
         Enclosure 1, ``Cross-Reference Table,'' provides the 
    cross-reference table connecting each CTS specification (i.e., limiting 
    condition for operation, required action, or surveillance requirement) 
    to the associated ITS specification, sorted by both CTS and ITS 
    specifications.
         Enclosures 3A and 3B, ``Description of Changes to Current 
    TS'' and ``Conversion Comparison Table,'' provides the description of 
    the changes to the CTS section and the comparison table showing which 
    plants (of the four licensees in the joint effort) that each change 
    applies.
         Enclosure 4, ``No Significant Hazards Considerations,'' 
    provides the no significant hazards consideration (NHSC) of 10 CFR 
    50.91 for the changes to the CTS. A description of the NSHC 
    organization is provided, followed by generic NHSCs for administrative, 
    more restrictive, relocation, and moving-out-of-CTS changes, and 
    individual NHSCs for less restrictive changes.
         Enclosures 6A and 6B, ``Differences From NUREG-1431'' and 
    ``Conversion Comparison Table,'' provides the descriptions of the 
    differences from NUREG-1431 specifications and the comparison table 
    showing which plants (of the four licensees in the joint effort) that 
    each difference applies.
        The common methodology includes the convention that, if the words 
    in a CTS specification are not the same as the words in the ITS 
    specification, but the CTS words have the same meaning or have the same 
    requirements as the words in the ITS specification, then the licensees 
    do not have to indicate or describe a change to the CTS. In general, 
    only technical changes have been identified; however, some non-
    technical changes have also been identified. The portion of any 
    specification which is being deleted is struck through (i.e., the 
    deletion is annotated using the strike-out feature of the word 
    processing computer program or crossed out by hand). Any text being 
    added to a specification is shown by shading the text, placing a circle 
    around the new
    
    [[Page 15187]]
    
    text, or by writing the text in by hand. The text being struck through 
    or added is shown in the marked-up CTS and ISTS pages in Enclosures 2 
    (CTS pages) and 5 (ISTS and ISTS Bases pages) for each ITS section 
    attachment to the application. Another convention of the common 
    methodology is that the technical justifications for the less 
    restrictive changes are in the NHSCs.
        The proposed changes can be grouped into the following four 
    categories: relocated requirements, administrative changes, less 
    restrictive changes involving deletion of requirements, and more 
    restrictive changes. These categories are as follows:
        1. Relocated requirements (i.e., the licensee's ``LG'' or ``R'' 
    changes) are items which are in the CTS but do not meet the criteria 
    set forth in the Final Policy Statement. The Final Policy Statement 
    establishes a specific set of objective criteria for determining which 
    regulatory requirements and operating restrictions should be included 
    in the TS. Relocation of requirements to documents with an established 
    control program, controlled by the regulations or the TS, allows the TS 
    to be reserved only for those conditions or limitations upon reactor 
    operation which are necessary to obviate the possibility of an abnormal 
    situation or event giving rise to an immediate threat to the public 
    health and safety, thereby focusing the scope of the TS. In general, 
    the proposed relocation of items from the CTS to the Updated Safety 
    Analysis Report (USAR), appropriate plant-specific programs, station 
    procedures, or ITS Bases follows the guidance of NUREG-1431. Once these 
    items have been relocated to other licensee-controlled documents, the 
    licensee may revise them under the provisions of 10 CFR 50.59 or other 
    NRC-approved control mechanisms, which provide appropriate procedural 
    means to control changes by the licensee.
        2. Administrative changes (i.e., the licensee's ``A'' changes) 
    involve the reformatting and rewording of requirements, consistent with 
    the style of the ISTS in NUREG-1431, to make the TS more readily 
    understandable to station operators and other users. These changes are 
    purely editorial in nature, or involve the movement or reformatting of 
    requirements without affecting the technical content. Application of a 
    standardized format and style will also help ensure consistency is 
    achieved among specifications in the TS. During this reformatting and 
    rewording process, no technical changes (either actual or 
    interpretational) to the TS will be made unless they are identified and 
    justified.
        3. Less restrictive changes and the deletion of requirements 
    involves portions of the CTS (i.e., the licensee's ``LS'' and ``TR'' 
    changes) which (1) provide information that is descriptive in nature 
    regarding the equipment, systems, actions, or surveillances, (2) 
    provide little or no safety benefit, and (3) place an unnecessary 
    burden on the licensee. This information is proposed to be deleted from 
    the CTS and, in some instances, moved to the proposed Bases, USAR, or 
    procedures. The removal of descriptive information to the Bases of the 
    TS, USAR, or procedures is permissible because these documents will be 
    controlled through a process that utilizes 10 CFR 50.59 and other NRC-
    approved control mechanisms. The relaxations of requirements were the 
    result of generic NRC actions or other analyses. They will be justified 
    on a case-by-case basis for the WCGS and described in the safety 
    evaluation to be issued with the license amendment.
        4. More restrictive requirements (i.e., the licensee's ``M'' 
    changes) are proposed to be implemented in some areas to impose more 
    stringent requirements than are in the CTS. In some cases, these more 
    restrictive requirements are being imposed to be consistent with the 
    ISTS. Such changes have been made after ensuring the previously 
    evaluated safety analysis for the WCGS was not affected. Also, other 
    more restrictive technical changes have been made to achieve 
    consistency, correct discrepancies, and remove ambiguities from the TS. 
    Examples of more restrictive requirements include: placing a Limiting 
    Condition for Operation (LCO) on station equipment which is not 
    required by the CTS to be operable; more restrictive requirements to 
    restore inoperable equipment; and more restrictive surveillance 
    requirements.
        There are twenty-two other proposed changes to the CTS that may be 
    included in the proposed amendment to convert the CTS to the ITS. These 
    are beyond scope issues (BSIs) in that they are changes to both the CTS 
    and the ISTS. For the WCNGS, these are the following:
        1. Change 1-05-M (CTS Section
    3/4.4). The change would add a note under CTS 3.4.1.2 (ITS 3.4.5) to 
    establish secondary side temperature restrictions on starting an idle 
    reactor coolant pump when below the low temperature overpressurization 
    arming temperature of 368 degrees F. The change would also add similar 
    notes to CTS 3.4.1.3 and 3.4.1.4.1 (ITS 3.4.6 and 3.4.7). The notes 
    would help ensure the assumptions in the WCNGS low temperature 
    overpressurization event analysis remain valid.
        2. Change 1-15-M (CTS Section
    3/4.4). CTS Surveillance Requirements (SRs) 4.4.1.2.2 and 4.4.1.3.2 
    require steam generator (SG) levels to be periodically verified to be 
    greater than or equal to 10 percent wide range water level. The 
    proposed change would revise the SG level value to 6 percent narrow 
    range water level. This change would help ensure that the SG level is 
    sufficient to cover all SG tubes so that the SGs would provide an 
    adequate heat sink for removal for decay heat. The proposed change 
    would similarly revise CTS 3.4.1.4.b, which currently requires, for 
    operational Mode 5, that the SG level be maintained greater than 10 
    percent wide range level. The change would increase this level value to 
    greater than 66 percent wide range, which again would help ensure the 
    SG tubes remain covered in Mode 5.
        3. Change 7-10-LS-9 (CTS Section
    3/4.6). The proposed change would add a note to CTS SRs 4.6.1.7.2 and 
    4.6.1.7.4 stating that containment purge valves with resilient seals 
    are not required to be leak rate tested when the penetration flow path 
    is isolated by leak-tested blank flange.
        4. Change 2-20-A (2-20-A has two changes associated with it. This 
    is the first of two.) (CTS Section 3/4.8). The proposed change would 
    increase the minimum battery cell float voltages for DC sources in CTS 
    Table 4.8-2 by 0.01 to 0.02 volts.
        5. Change 2-20-A (Second change associated with 2-20-A) (CTS 
    Section 3/4.8). A change would be made to decrease the total required 
    battery terminal voltage for a DC subsystem in CTS SR 4.8.2.1. These 
    proposed changes in minimum cell float voltage and corresponding total 
    required battery voltage would reflect a recent design modification 
    made by the licensee that replaced the Gould manufactured square cell 
    batteries with AT&T manufactured round cell batteries.
        6. Change 2-27-M (CTS Section
    3/4.8). The proposed change would revise the battery performance 
    discharge test acceptance criteria in CTS 4.8.2.1.e to reflect a recent 
    design modification that replaced the Gould manufactured square cell 
    batteries with AT&T manufactured round cell batteries.
        The above six BSIs are given in the licensee's application. The 
    remaining sixteen BSIs may have been revised by the licensee's 
    responses to the NRC requests for additional information (RAIs). The 
    format for the sixteen BSIs listed below is the associated change 
    number, RAI number, RAI response
    
    [[Page 15188]]
    
    submittal date, and description of the change.
        7. Change 1-22-M (CTS Section
    3/4.3), question Q3.3-49, response letter dated November 24, 1998. The 
    proposed change would add quarterly channel operational tests (COTs) to 
    CTS Table 4.3-1 for the power range neutron flux-low, intermediate 
    range neutron flux, and source range flux trip functions. The CTS only 
    require a COT prior to startup for these functions. A new note (Note 
    19) would be added to require that the new quarterly COT be performed 
    within 12 hours after reducing power below P-10 for the power range and 
    intermediate range instrumentation if not performed within the previous 
    92 days (P-10 is the dividing point marking the applicability for these 
    trip functions). A new note (Note 20) would also be added requiring the 
    P-6 and P-10 interlocks be verified to be in their required state 
    during all COTs on the power range neutron flux-low and intermediate 
    range neutron flux trip functions.
        8. Change 1-7-LS-3 (CTS Section 3/4.3), question Q3.3-107, response 
    letter dated December 2, 1998. The proposed changes would (1) extend 
    the completion time for CTS Action 3.b from no time specified to 24 
    hours for intermediate range channel restoration or changing the power 
    level to either below P-6 or above P-10, (2) reduce the applicability 
    of the intermediate range neutron flux channels and delete CTS Action 
    3.a as being outside the revised applicability, and (3) add a less 
    restrictive new action that requires immediate suspension of operations 
    involving positive reactivity additions and a power reduction below P-6 
    within 2 hours, but no longer requires a reduction to Mode 3.
        9. Change 1-9-A (CTS Section 6.0), question Q5.2-1, response letter 
    dated September 24, 1998. The proposed change would revise requirements 
    concerning overtime control by replacing CTS 6.2.2.e with a reference 
    to administrative procedures for the control of working hours.
        10. Change 1-15-A (CTS Section 6.0), question Q5.2-1, response 
    letter dated September 24, 1998. The proposed change would revise CTS 
    6.2.2.G to eliminate the title of Shift Technical Advisor. The 
    engineering expertise is maintained on shift, but a separate individual 
    would not be required as allowed by a Commission Policy Statement.
        11. Change 2-18-A (CTS Section 6.0), question Q5.2-1, response 
    letter dated September 24, 1998. The proposed change would revise the 
    dose rate limits in the Radioactive Effluent Controls Program for 
    releases to areas beyond the site boundary would be revised to reflect 
    10 CFR Part 20 requirements.
        12. Change 2-22-A (CTS Section 6.0), question Q5.2-1, response 
    letter dated September 24, 1998. The proposed change would revise the 
    Radioactive Effluent Controls Program to include clarification 
    statements denoting that the provisions of CTS 4.0.2 and 4.0.3, which 
    allow extensions to surveillance frequencies, are applicable to these 
    activities.
        13. Change 3-11-A (CTS Section 6.0), question Q5.2-1, response 
    letter dated September 24, 1998. CTS provides alternative high 
    radiation area access control alternatives pursuant to 10 CFR 
    20.203(c)(2). The proposed change would revise CTS 6.12 to meet the 
    current requirements in 10 CFR Part 20 and the guidance in NRC 
    Regulatory Guide 8.38, ``Control of Access to High and Very High 
    Radiation Areas in Nuclear Power Plants'' for such access controls.
        14. Change 3-18-LS-5 (CTS Section 6.0), question Q5.2-1, response 
    letter dated September 24, 1998. The proposed change would delete the 
    CTS 6.9.1.8 requirement to provide documentation of all challenges to 
    the power operated relief valves (PORVs) and safety valves on the 
    reactor coolant system. This proposed change is based on Generic Letter 
    97-02, ``Revised Contents of the Monthly Operating Report,'' which 
    reduced the requirements for submitting such information to the NRC. GL 
    97-02 did not include these valves for information to be submitted.
        15. Change 9-17-LS-24 (CTS Section 3/4.4), question Q3.4.12-5, 
    response letter dated September 24, 1998. The proposed change would add 
    four notes to CTS 3.4.9.3 to reflect CTS SR 4.5.3.2, LCO 3.5.4 actions, 
    LCO 3.5.4 applicability notes and the accumulator action proposed under 
    Change 9-10-M for CTS 3/4.4. Note 1 on centrifugal charging pump (CCP) 
    swap operations would be a relaxation of the CTS because it would allow 
    both CCPs to be capable of injecting into the RCS for up to 4 hours 
    throughout low temperature protection applicability.
        16. Change 10-20-LS-39 (CTS Section 3/4.7), question Q3.7.10-14, 
    response letter dated October 16, 1998. The proposed change would 
    revise and add an action to CTS LCOs 3.7.6 and 3.7.7 for ventilation 
    system pressure envelope degradation that allows 24 hours to restore 
    the control room pressure envelope through repairs before requiring the 
    unit to perform an orderly shutdown. The new action has a longer 
    allowed outage time than LCO 3.0.4 which the CTS would require to be 
    entered immediately. The new action has a longer allowed outage time 
    than LCO 3.0.4 which the CTS would require to be entered immediately. 
    This change recognizes that the ventilation trains associated with the 
    pressure envelope would still be operable.
        17. Change 4-8-LS-34 (CTS Section 3/4.4), question Q3.4.11-2, 
    response letter dated September 24, 1998. The proposed change would 
    limit the CTS SRs 4.4.4.1 and 4.4.4.2 requirements to perform the 92-
    day surveillance of the pressurizer PORV block valves and the 18-month 
    surveillance of the pressurizer PORVs (i.e., perform one complete cycle 
    of each valve) to only Modes 1 and 2.
        18. Change 4-9-LS-36 (CTS Section 3/4.4), question Q3.4.11-4, 
    response letter dated September 24, 1998. The proposed change would add 
    a note to CTS LCO 3.4.4 Action (d) that would state that the action 
    does not apply when the PORV block valves are inoperable as a result of 
    power being removed from the valves in accordance with Actions (b) and 
    (c) for an inoperable PORV.
        19. Change 1-60-A (CTS Section
    
    3/4.3), question TR3.3-0073.3, response letter dated December 21, 1998. 
    The proposed change would revise the frequency for conducting the trip 
    actuating device operational test (TADOT) for the turbine trip of the 
    reactor trip instrumentation surveillance requirements in CTS Table 
    4.3-1 from ``prior to reactor startup'' to ``prior to exceeding the P-9 
    interlock whenever the unit has been in Mode 3.''
        20. Change 1-70-M (CTS Section
    
    3/4.8), question Q3.8.2-04, response letter dated December 17, 1998. 
    The proposed change would add shutdown requirements (including actions) 
    for the load shedder and emergency load sequencer (LSELS) to CTS LCO 
    3.8.1.2 and surveillance requirements in SR 4.8.1.2. These requirements 
    would reflect current practice.
        21. Change 2-25-LS-23 (CTS Section 3/4.8), question Q3.8.4-08, 
    response letter dated December 17, 1998. The proposed change would 
    allow substitution of the service test with a performance discharge 
    test in CTS 4.8.2.1.
        22. Change 14-9-M (CTS Section
    
    3/4.7), question Q3.7.16-3, response letter dated February 4, 1999. The 
    proposed change would provide a new LCO, Actions and SRs based on the 
    ISTS to impose limitations on the boron concentration in the fuel 
    storage pool. The BSI for the conversion to ITS is that a minimum value 
    for boron concentration would be added that is currently not in the 
    CTS, and the
    
    [[Page 15189]]
    
    Actions would be revised to reflect additional regions of fuel storage 
    based on approval of reracking the spent fuel pool prior to issuance of 
    the ITS.
    
    Environmental Impacts of the Proposed Action
    
        The Commission has completed its evaluation of the proposed 
    conversion of the CTS to the ITS for WCGS, including the beyond scope 
    issues discussed above. Changes which are administrative in nature have 
    been found to have no effect on the technical content of the TS. The 
    increased clarity and understanding these changes bring to the TS are 
    expected to improve the operators' control of WCGS in normal and 
    accident conditions.
        Relocation of requirements from the CTS to other licensee-
    controlled documents does not change the requirements themselves. 
    Future changes to these requirements may then be made by the licensee 
    under 10 CFR 50.59 and other NRC-approved control mechanisms which will 
    ensure continued maintenance of adequate requirements. All such 
    relocations have been found consistent with the guidelines of NUREG-
    1431 and the Commission's Final Policy Statement.
        Changes involving more restrictive requirements have been found to 
    enhance station safety.
        Changes involving less restrictive requirements have been reviewed 
    individually. When requirements have been shown to provide little or no 
    safety benefit, or to place an unnecessary burden on the licensee, 
    their removal from the TS was justified. In most cases, relaxations 
    previously granted to individual plants on a plant-specific basis were 
    the result of a generic action, or of agreements reached during 
    discussions with the OG, and found to be acceptable for WCGS. Generic 
    relaxations contained in NUREG-1431 have been reviewed by the NRC staff 
    and found to be acceptable.
        In summary, the proposed revisions to the TS were found to provide 
    control of station operations such that reasonable assurance will be 
    provided that the health and safety of the public will be adequately 
    protected.
        The proposed action will not increase the probability or 
    consequences of accidents, will not change the quantity or types of any 
    effluent that may be released offsite, and will not significantly 
    increase the occupational or public exposure. Also, these changes do 
    not increase the licensed power and allowable effluents for the 
    station. The changes will not create any new or unreviewed 
    environmental impacts that were not considered in the Final 
    Environmental Statement related to the operation of WCNGS, NUREG-0878, 
    dated June 1982. Therefore, there are no significant radiological 
    impacts associated with the proposed action.
        With regard to potential non-radiological impacts, the proposed 
    action only involves features located entirely within the restricted 
    area for the station defined in 10 CFR Part 20 and does not involve any 
    historic sites. The proposed action does not affect non-radiological 
    station effluents and has no other environmental impact. It does not 
    increase any discharge limit for the station. Therefore, there are no 
    significant non-radiological environmental impacts associated with the 
    proposed action.
        Accordingly, the Commission concludes that there are no significant 
    environmental impacts associated with the proposed action.
    
    Alternatives to the Proposed Action
    
        As an alternative to the proposed action, the staff considered 
    denial of the proposed action (i.e., the ``no-action'' alternative). 
    Denial of the licensee's application would result in no change in 
    current environment impacts. The environmental impacts of the proposed 
    action and the alternative action are similar.
    
    Alternative Use of Resources
    
        This action does not involve the use of any resources not 
    previously considered in the Final Environmental Statement for the Wolf 
    Creek Generating Station dated June 1982.
    
    Agencies and Persons Consulted
    
        In accordance with its stated policy, on March 22, 1999, the staff 
    consulted with the Kansas State official, Mr. Vick Cooper, Kansas 
    Department of Health and Environment, regarding the environmental 
    impact of the proposed action. The State official had no comments.
    
    Finding of No Significant Impact
    
        Based upon the environmental assessment, the Commission concludes 
    that the proposed action will not have a significant effect on the 
    quality of the human environment. Accordingly, the Commission has 
    determined not to prepare an environmental impact statement for the 
    proposed action.
    
        For further details with respect to the proposed action, see the 
    licensee's application dated May 15, 1997, as supplemented by (1) 
    the letters in 1998 dated June 30, August 5, August 28, September 
    24, October 16, October 23, November 24, December 2, December 17, 
    and December 21, and (2) the letters in 1999 dated February 4 and 
    March 5 (3 letters) which are available for public inspection at the 
    Commission's Public Document Room, The Gelman Building, 2120 L 
    Street, NW., Washington, DC, and at the local public document rooms 
    located at the Emporia State University, William Allen White 
    Library, 1200 Commercial Street, Emporia, Kansas 66801, and Washburn 
    University School of Law Library, Topeka, Kansas 66621.
    
        Dated at Rockville, Maryland, this 24th day of March 1999.
    
        For the Nuclear Regulatory Commission.
    Jack N. Donohew,
    Senior Project Manager, Project Directorate IV-1, Division of Licensing 
    Project Management, Office of Nuclear Reactor Regulation.
    [FR Doc. 99-7756 Filed 3-29-99; 8:45 am]
    BILLING CODE 7590-01-U
    
    
    

Document Information

Published:
03/30/1999
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
99-7756
Pages:
15186-15189 (4 pages)
Docket Numbers:
Docket No. 50-482
PDF File:
99-7756.pdf